This document is an Amendment to Solicitation for a Design-Build project at the Lebanon VA Medical Center in Pennsylvania. Amendment 001 extends the Request for Information (RFI) date from 10/20/2025 to 10/24/2025 at 3:00 PM and provides additional technical documentation, including safety requirements specifications, door and frame details, and revised floor plans for a fire barrier upgrade. The solicitation is for a Firm-Fixed-Price contract to replace door frames in Building 104, with the proposal due date remaining 11/10/2025 at 4:00 PM Eastern Time.
The project, identified as Project Number 595-24-105, requires a Design-Build team to provide comprehensive design and construction services for door frame replacement. The contractor must comply with VA guidelines, EPA requirements, and VA specifications specific to the Lebanon VA Medical Center. The procurement seeks a prime contractor who will partner with an Architect Engineering firm to complete design and construction, with all work requiring tools, labor, materials, permits, and supervision to meet VA Master Construction Requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW - Replace Door Frames Building 104 D-B -Rev1 11042025.docx | DOCX document | |
| 36C24426R0016 0002.pdf | ||
| 595-24-105 Replace Door Frames 104 - Prebid Sign In 10142025.pdf | ||
| 36C2442600016 Amend 2 Door Frames 104 RFI responses.docx | DOCX document | |
| 36C24426R0016 0002_1.docx | DOCX document | |
| LB-104-01AR - Rev1 11042025-Model.pdf | ||
| LB-104-01ME-Model.pdf | ||
| AE-102 Doors-Frames-Details - Rev2.pdf | ||
| 013526 Lebanon Safety Requirements Spec 20240516.docx | DOCX document | |
| RM Language for Contracts_01.docx | DOCX document | |
| 36C24426R0016 0001_1.docx | DOCX document | |
| AE-101 Wall Types.pdf | ||
| AE-100 Floor Plan - Fire Barrier Upgrade.pdf | ||
| P03 07.08.2025 Service Determination.pdf | ||
| Davis-Bacon Act WD PA20250093 10.3.25.pdf | ||
| 36C24426R0016 10.14.25.pdf | ||
| RM Language for Contracts.docx | DOCX document | |
| SOW - Replace Door Frames Building 104 D-B.docx | DOCX document | |
| 36C24426R0016_1.docx | DOCX document | |
| P03 36C24426AP0236 liquidated damages formulation Lebanon signed.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 595-24-105 00244 Department of Veterans Affairs Network Contracting Office 4
00244 Department of Veterans Affairs Network Contracting Office 4
To all Offerors/Bidders
36C24426R0016
X X X The purpose of this modification is for the following:
1) Extend the RFI date from 10/20/2025 to 10/24/2025 at 3:00PM
2) Provide additional drawings, specification section and RM language.
3) Proposal due date remains 11/10/2025 at 4:00 Eastern Time.
See attached document: 013526 Lebanon Safety Requirements Spec 20240516.
See attached document: AE-102 Doors-Frames-Details - Rev2.
See attached document: RM Language for Contracts.
See attached document: AE-100 Floor Plan - Fire Barrier Upgrade.