Section E

View the file

Other files for this federal contract opportunity

Other files attached to Joint Operations and Integrated Systems Technology (JOIST), newest first.
File Type Posted
Section_L_Am_1.docx DOCX document
DRFP_Questions_Round_3_.pdf PDF
Attachment_L-07_IDIQ_EPM_Template_Am_1.xlsx XLSX spreadsheet
NNJ17580323R_Final_RFP_Amendment_1.pdf PDF
FRFP_Questions_Round_1.pdf PDF
Attachment_L-03_-_Strategic_Projects_TO_Am_1.docx DOCX document
Attachment_J-13_-_IT_Security_Management_Plan.docx DOCX document
JOIST-DRD-12-Environmental_and_Energy_Compliance_Reports.docx DOCX document
Section_J.docx DOCX document
Attachment_J-04_-_List_of_Government-Furnished_Computer_Software.docx DOCX document
JOIST-DRD-09-Emergency_Preparedness_and_Disaster_Recovery_and_Continuity_of_Operations_Plan_(DRCOP).docx DOCX document
BD-SEB-16-227_-_JOIST_-_FRFP_Cover_Letter.pdf PDF
Attachment_J-04B_-_GFCS_-_Baseline_B.pdf PDF
JOIST-DRD-10B-WBS_(Baseline_B).docx DOCX document
Attachment_J-09_-_Total_Compensation_Plan.docx DOCX document
Section_I.docx DOCX document
Attachment_J-05B_-_IAGP_-_Baseline_B.pdf PDF
Section_D.docx DOCX document
Attachment_J-18_-_ER_Plan.docx DOCX document
JOIST-DRD-06-Information_Technolgy_(IT)_Security_Managment_Plan_and_Reports.docx DOCX document
Attachment_L-01_Standard_Labor_Categories.docx DOCX document
JOIST-DRD-02_Total_Compensation_Plan.docx DOCX document
JOIST-DRD-18_Montly_Performance_Report_FFP_IDIQ.docx DOCX document
Section_A.docx DOCX document
Attachment_L-03_-_Strategic_Projects_TO.docx DOCX document
Section_F.docx DOCX document
Section_L.docx DOCX document
Attachment_J-04A_-_GFCS_-_Baseline_A.pdf PDF
Attachment_J-14_-_Government_Property_Management_Plan.docx DOCX document
Attachment_J-07_-_List_of_Applicable_Documents.docx DOCX document
JOIST-DRD-07-Government_Property_Management_Plan_(PMP).docx DOCX document
Attachment_L-07_IDIQ_EPM_Template.xlsx XLSX spreadsheet
JOIST-DRD-14-Equipment_Replacement_(ER)_Plan.docx DOCX document
Attachment_J-17_-_WBS.docx DOCX document
Section_C.docx DOCX document
Document_Change_Log_(DRFP_to_FRFP).pdf PDF
JOIST-DRD-11-Reports_Required_for_Logistics.docx DOCX document
Attachment_L-07_CF_EPM_Template.xlsx XLSX spreadsheet
Attachment_L-09_SF1408.pdf PDF
Attachment_J-03_Standard_Labor_Categories.docx DOCX document
Section_K.docx DOCX document
JOIST-DRD-15-Status_Reports_and_Reviews.docx DOCX document
Attachment_J-06_-_List_of_Government-Provided_Facilities.docx DOCX document
Attachment_J-01_-_Data_Requirements_List.docx DOCX document
Section_G.docx DOCX document
Section_M.docx DOCX document
JOIST-DRD-08-Safety_and_Health_Plan_and_Reports.docx DOCX document
Attachment_J-12_-_Organizational_Conflict_of_Interest_(OCI)_Mitigation_Plan.docx DOCX document
Attachment_L-07_IDIQ_EPM_Template_09-19.xlsx XLSX spreadsheet
JOIST_DRFP_09-19a.pdf PDF
Show all 50

Joint Operations and Integrated Systems Technology (JOIST) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section E – Inspection and Acceptance E.1 Listing of Clauses Incorporated by Reference NOTICE: The following contract clauses pertinent to this section are hereby incorporated by reference:

I. Federal Acquisition Regulation (48 CFR Chapter 1)

Provision Number
Date
Title
52.246-2
Aug 1996
Inspection of Supplies – Fixed Price
52.246-3
May 2001
Inspection of Supplies – Cost-Reimbursement
52.246-4
Aug 1996
Inspection of Services – Fixed Price
52.246-5
Apr 1984
Inspection of Services – Cost Reimbursement
52.246-7
Aug 1996
Inspection of Research and Development – Fixed Price
52.246-8
May 2001
Inspection of Research and Development – Cost Reimbursement
52.246-16
Apr 1984
Responsibility for Supplies

II. NASA FAR Supplement (48 CFR Chapter 18)

Provision Number
Date
Title

None incorporated by reference.

(End of Clause) E.2 FAR 52.246-11 Higher-Level Contract Quality Requirement (Dec 2014) The Contractor shall comply with the higher-level quality standard(s) listed below.

JSC Quality Management System.

The Contractor shall establish a software development process that complies with current version of JSC 63756 MOD Software Management Plan (SMP).

For Baseline A, the Contractor shall possess certification of its quality assurance/quality control processes applicable to software development in accordance with the Software Engineering Institute’s Capability Maturity Model (CMM) or Capability Maturity Model-Integrated (CMMI) Level 3. An independent certifying authority must provide this certification.

For Tier 1 IDIQ task orders, the Contractor shall possess certification of its quality assurance/quality control processes applicable to software development in accordance with the Software Engineering Institute’s Capability Maturity Model (CMM) or Capability Maturity Model-Integrated (CMMI) Level 3 or higher standard or similar Government-approved configuration management standard. An independent certifying authority must provide this certification.

The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in— Any subcontract for critical and complex items (see 46.203(b) and (c)); or When the technical requirements of a subcontract require— Control of such things as design, work operations, in-process control, testing, and inspection; or Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of Clause)

E.3 NFS 1852.246-72 Material Inspection and Receiving Report (Apr 2015) At the time of each delivery to the Government under this contract, the Contractor shall prepare and furnish a Material Inspection and Receiving Report (DD Form 250 series). The forms shall be prepared and distributed as follows: in triplicate (an original and two copies). Upon delivery of product to the destination, each copy of the Material Inspection and Receiving Report shall be signed by the receiver. The original shall remain with the Contractor’s driver making the delivery, and two copies shall be retained by the receiving destination as proof of delivery.

The Contractor shall prepare the DD Form 250 in accordance with NASA FAR Supplement 1846.6. The Contractor shall enclose the copies of the DD Form 250 in the package or seal them in a waterproof envelope, which shall be securely attached to the exterior of the package in the most protected location.

When more than one package is involved in a shipment, the Contractor shall list on the DD Form 250, as additional information, the quantity of packages and the package numbers. The Contractor shall forward the DD Form 250 with the lowest numbered package of the shipment and print the words "CONTAINS DD FORM 250" on the package.

(End of Clause) [End of Section]

NNJ17580323R E-1

File details come from the government source that posted it. Updated .