Section H - Special Contract Requirements

View the file

Other files for this federal contract opportunity

Other files attached to SPECIALIZED ENGINEERING AERONAUTICS AND MANUFACTURING, newest first.
File Type Posted
SEAM_Source_Selection_Statement.pdf PDF
Amendment_3_-_SEAM_Sec_L_-_Instructions_Conditions_and_Notices_to_Offerors.docx DOCX document
Amendment_3_-_SEAM_Questions_and_Answers_Part_3.docx DOCX document
Amendment_3_-_SEAM_NNJ16567749R.pdf PDF
Amendment_3_-_SEAM_Sec_A_-_Coversheet_and_Table_of_Contents.pdf PDF
Amendment_3_-_SEAM_Sec_H_-_Special_Contract_Requirements.docx DOCX document
Amendment_2_-_SEAM_NNJ16567749R.pdf PDF
Amendment_2_-_SEAM_Sec_L_-_Instructions_Conditions_and_Notices_to_Offerors.docx DOCX document
Amendment_2_-_SEAM_Questions_and_Answers_Part_2.docx DOCX document
Amendment_1_-_SEAM_Sec_L_-_L_16_3_-_Past_Performance_Questionnaire.docx DOCX document
Amendment_1_-_SEAM_NNJ16567749R.pdf PDF
Amendment_1_-_SEAM_Sec_L_-_Instructions_Conditions_and_Notices_to_Offerors.docx DOCX document
Amendment_1_-_SEAM_Sec_M_-_Evaluation_Factors_for_Award.docx DOCX document
Amendment_1_-_SEAM_Questions_and_Answers_Part_1.docx DOCX document
Amendment_1_-_SEAM_Sec_I_-_Contract_Clauses.docx DOCX document
Amendment_1_-_SEAM_Sec_J_-_List_of_Documents_Exhibits_and_Other_Attachments.docx DOCX document
Amendment_1_-_SEAM_Sec_L_-_L_16_5_-_Price_Templates.xlsx XLSX spreadsheet
Amendment_1_-_SEAM_Sec_A_-_Coversheet_and_Table_of_Contents.pdf PDF
SEAM_Sec_L_-_L_16_2__Past_Performance_Reference_Table.xlsx XLSX spreadsheet
SEAM_Sec_F_-_Deliveries_and_Performance.docx DOCX document
SEAM_Sec_E_-_Inspection_and_Acceptance.docx DOCX document
SEAM_Sec_D_-_Packaging_and_Marking.docx DOCX document
SEAM_Sec_M_-_Evaluation_Factors_for_Award.docx DOCX document
SEAM_Sec_G_-_Contract_Administration_Data.docx DOCX document
SEAM_Sec_A_-_Coversheet_and_Table_of_Contents.pdf PDF
SEAM_Sec_B_-_Supplies_or_Services_and_Prices.docx DOCX document
SEAM_Sec_C_-_Statement_of_Work.docx DOCX document
SEAM_RFP_NNJ16567749R_-_Cover_Letter.pdf PDF
SEAM_Sec_L_-_Instructions _Conditions _and_Notices_to_Offerros.docx DOCX document
SEAM_Sec_L_-_L_16_5_Price_Templates.xlsx XLSX spreadsheet
SEAM_Sec_I_-_Contract_Clauses.docx DOCX document
SEAM_Sec_J_-_List_of_Documents _Exhibits_and_Other_Attachments.docx DOCX document
SEAM_Sec_K_-_Representations _Certifications _and_Other_Statements_to_Offerors.docx DOCX document
SEAM_Sec_L_-_L_16_3__Past_Performance_Questionaire.docx DOCX document
SEAM_Sec_L_-_L_16_1__Relevant_Past_Performance_Matrix.xlsx XLSX spreadsheet
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NNJ16RN23B Specialized Engineering, Aeronautics, and Manufacturing Section H

H. SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES INCORPORATED BY REFERENCE

Clause(s) at the beginning of this Section are incorporated by reference, with the same force and effect as if they were given in full text. Clauses incorporated by reference which require a fill-in by the Government include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire clause.

The following contract clauses pertinent to this section are hereby incorporated by reference:

I. FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1)

CLAUSE

NUMBER DATE TITLE

NONE INCORPORATED BY REFERENCE

II. NASA FAR SUPPLEMENT (48 CFR CHAPTER 18) PROVISIONS

CLAUSE

NUMBERDATETITLE
1852.208-81 NOV 2004RESTRICTIONS ON PRINTING AND

DUPLICATING

1852.223-70 DEC 2015 SAFETY AND HEALTH MEASURES AND

MISHAP REPORTING

1852.223-75FEB 2002MAJOR BREACH OF SAFETY OR SECURITY
1852.242-72OCT 2015DENIED ACCESS TO NASA FACILITIES

(End of Clause)

H.2EXPORT LICENSES (NFS 1852.225-70) (FEB 2000)
(a)The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the Export Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at NASA Johnson Space Center and other locations as identified in the SOW, where the foreign person will have access to export-controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

(End of Clause) H.3 SUBMISSION OF VOUCHERS FOR PAYMENT (FAR 52.216-92) (MAY 2014) (JSC PROCUREMENT INSTRUCTION)

(a) Except for classified vouchers, the Contractor shall submit interim and final cost vouchers electronically using the Department of Defense (DoD) Wide Area Work Flow (WAWF) system. Vouchers will be reviewed by the Defense Contract Audit Agency based upon a risk-based review process.

(1) To access the DoD WAWF system, the Contractor shall be required to have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov and be registered to use the DoD WAWF at https://wawf.eb.mil following the step-by-step procedures for self-registration available at this web site.

(2) NASA voucher payment information can be obtained at the NASA Shared Services Center (NSSC) Vendor Payment information web site at: https://www.nssc.nasa.gov/vendorpayment For technical WAWF help, contact the WAWF helpdesk at 1-866-618-5988. For additional questions, contact the NSSC Customer Contact Center at 1-877-677-2123.

(3) The Contractor shall ensure that the payment request includes appropriate contract line item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all required back-up documentation to support each payment request.

(b) Vouchers for payment of fee resulting from contract performance or provisional fee (if authorized under this contract) shall be prepared using a Standard Form (SF) 1034 and submitted electronically to the following address for payment:

E-mail address: NSSC-AccountsPayable@nasa.gov
Mailing address:NSSC - FMD Accounts Payable
Bldg. 1111, C Road
Stennis Space Center, MS 39529
Fax Number: 1-866-209-5415

(c) For both cost and fee voucher submissions, a concurrent copy of the voucher shall be provided electronically to the NASA Contracting Officer outside of WAWF. The Contracting Officer may designate other recipients as required.

(d) The NSSC is the designated billing office for cost and fee vouchers for purpose of the Prompt Payment clause of this contract.

(e) In the event that amounts are withheld from payment in accordance with terms of this contract, a separate voucher for the amount withheld will be required before payment for that amount may be made.

(End of Clause)

H.4 SMALL BUSINESS SUBCONTRACTING GOALS (FAR 52.219-90) (OCT 2006) (JSC PROCUREMENT INSTRUCTION)- ONLY APPLICABLE TO LARGE BUSINESSES For purposes of this clause, the terms, “HUBZone Small Business Concern,” “Small Disadvantaged Business (SDB) Concern,” “Service-Disabled, Veteran-Owned Small Business Concern, “Veteran-Owned Small Business Concern,”” “Women-Owned Small Business Concern,” and “Historically Black College or University (HBCU)” are defined in paragraph 2.101 of the Federal Acquisition Regulation (FAR).

The total small business goal, expressed as a percent of total contract value including options, is ______ percent. The small business percentage goal, includes the following goals expressed as a percent of total contract value:

Small Disadvantaged Business Concerns __________ percent
Woman-Owned Small Business Concerns __________ percent
HUBZone Small Business Concerns ___________ percent
Veteran-Owned Small Business Concerns ___________ percent
Service-Disabled, Veteran-Owned ___________ percent
Small Business Concerns
HBCU’s (includes other minority institutions) ___________ percent

[OFFEROR TO FILL-IN]

(End of Clause) H.5 ENVIROMENTAL AND ENERGY CONSERVATION REQUIREMENTS (FAR 52.223-93) (FEB 2011) (JSC PROCUREMENT INSTRUCTION)

(a) The Contractor shall ensure that all work performed and equipment used to fulfill the requirements of this contract are in compliance with all Federal, state, and local regulations and public laws, and the following NASA JSC directives: JPR 8550.1, JSC Environmental Compliance Procedural Requirements; JPR 8553.1, JSC Environmental Management System Manual; JWI 8553.1, EMS Aspect/Impact Assessment and EMP Process; NPR 8570.1, Energy Efficiency and Water Conservation; and JWI 8570.1, Energy Conservation. The Contractor shall provide data on affirmative procurement, waste reduction activity, energy efficient product procurement, and ozone depleting substances in accordance with NPR 8530.1.

(b) The Government remains the owner and operator of record for all environmental activities conducted at NASA owned properties unless otherwise documented in a signed agreement between NASA and the Contractor. The Contractor is advised that activities performed at JSC and associated facilities are subject to Federal, state and local regulatory agency inspections to review compliance with environmental laws and regulations. For on-site issues, JSC's Environmental Office will be the single point of contact with Federal and state regulatory agencies and their representatives unless otherwise directed by the Contracting Officer or the Environmental Office. The Contractor shall immediately notify the JSC Environmental Office when contacted by external regulatory agency representatives and shall cooperate fully. The Contractor shall complete, maintain, and make available to the Contracting Officer, JSC Environmental Office, JSC Energy Manager, or regulatory agency personnel all documentation relating to environmental compliance matters under applicable laws. The Contractor shall immediately notify the JSC Environmental Office upon issuance of a Notice of Violation or noncompliance to the Contractor.

(c) Should a Notice of Violation, Notice of Noncompliance, Notice of Deficiency, or similar regulatory agency notice be issued to the Government as a facility owner/operator on account of the actions or inactions of the Contractor or one of its subcontractors in the performance of work under this contract, the Contractor shall fully cooperate with the Government in correcting any problems and defending against regulatory assessment of any civil fines or penalties arising out of such actions or inactions.

(End of Clause)

H.6 ADMINISTRATIVE LEAVE (FAR 52.242-94) (SEP 2008)(JSC PROCUREMENT INSTRUCTION)

(a) When the NASA installation grants administrative leave to its Government employees (e.g., as a result of inclement weather, potentially hazardous conditions, or other special circumstances), the following personnel should also be dismissed upon notification of a center closure provided by the Contracting Officer:

1. Contractor personnel working on-site; and

2. Contractor personnel dedicated to the contract effort who are:

a) working off-site within 10 miles of JSC; and

b) unable to perform their NASA contract duties at their off-site location because their normal place of business has been or is expected to be negatively impacted by an emergency situation (e.g. has sustained damage, has been evacuated, etc.).

However, the contractor shall provide sufficient on-site personnel to perform round-the-clock requirements of critical work already in process, unless otherwise instructed by the Contracting Officer or authorized representative.

(b) Administrative leave granted under this clause shall be subject to modification or termination by the Contracting Officer and in all instances shall be subject to the availability of funds. The cost of salaries and wages to the Contractor for the period of any such excused absence shall be a reimbursable item of cost under this contract for effected employees in accordance with the Contractor's established accounting policy.

1. If a labor hour-based contract, administrative leave granted under this clause shall be accounted for consistent with productive hours under this contract for employees in accordance with the Contractor's established accounting policy.

2. For fixed price contracts based on other than labor hours for deliverables, the Contracting Officer and Contractor shall as a precondition to any reimbursement negotiate an advanced agreement to determine the appropriate method in which to grant administrative leave under this clause.

3. All invoices requesting payment under this clause shall be marked as “Administrative Leave in accordance with 52.242-94, Administrative Leave.” All such invoices paid will be subject to review, audit, and revision when routine operations re-commence.

(c) The Contractor shall include this clause in all services subcontracts that include personnel in the categories described in (a) above.

(End of Clause)

H.7 ASSOCIATE CONTRACTOR AGREEMENTS

(a) In order to achieve the requirements of this contract, the Contractor shall establish the means for coordination and exchange of information with associate contractors. The information to be exchanged shall be that required by the associate contractors in the execution of their respective contract requirements. The associate contractors contemplated include the following contracts or their successors:

Key Contract(s):

· NNJ09HD46C; Facilities Development and Operations Contract (FDOC)

· NNJ10HD35C; Neutral Buoyancy Laboratory and Space Vehicle Mockup Facility Operations Contract (NSOC)

· NNJ14RA01B; Integrated Mission Operations Contract (IMOC II)

· NNJ12JC05C; Aircraft Maintenance and Operations Contract (AMOS)

(b) The Contractor is not relieved of any contract requirements or entitled to any adjustments to the contract terms because of the failure to resolve a disagreement with an associate contractor. Liability for the improper disclosure of any proprietary data contained in or referenced by any agreement shall rest with the parties to the agreement, and not the Government.

(End of Clause)

[END OF SECTION]