This document contains an attachment for a daily verification survey template to be used on a cemetery section renovation and headstone raising project at the National Memorial Cemetery of the Pacific. The template requires listing the cemetery sections and headstones worked on for the day, any discrepancies or issues noted, and confirmation that all issues were resolved or reported to the district office if unresolved. The foreman, work leader, or other designated person must fill out and sign the template prior to the completion of each workday to verify the headstones were correctly raised and realigned.
The related federal contract opportunity is a multiple award task order contract for cemetery shrine maintenance and repair services at the National Memorial Cemetery of the Pacific and Willamette National Cemetery. The solicitation was issued by the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Memorial Cemetery of the Pacific National Shrine Project – FY23 Cemetery Section Renovation - Phase V Project No.: 899-Mill-FY23-002
ATTACHMENT 5
DAILY HEADSTONE/MARKER RAISE & REALIGN VERIFICATION SURVEY
Station Number:__________ Date:_____________________
Cemetery: _______________ Cemetery Director: _______________
COR: ___________________
Instructions: Prior to the completion of the workday, the Cemetery Director/COR/Foreman/Work Leader/designee MUST perform a re-verification survey for ALL completed work of headstones/markers included in the scope of work. The Cemetery Director/COR/Foreman/Work Leader/designee will use the original Burial Register Report and Gravesite Layout Map used for the Initial Verification Survey.
List Sections and Headstones/Markers R&R: __________________________________
List discrepancy/issue: ___________________________________________________
All discrepancies/issues resolved: Y/N ______
Cemetery Director/COR/Foreman/ Work Leader/designee informed District Office Director and Contracting Officer of all unresolved discrepancies/issues: Y/N _______
By signing below, I certify the Headstone/Marker re-verification survey was completed.
Daily Headstone Verification:
Date: __________ Time Completed: ______________
COR/Director/Foreman/Work Leader/designee Signature: ________________________