N69450-20-R-0013 0011.pdf
PDF 21 KB Posted
- Solicitation number
- N69450-20-R-0013
About this file
This document contains an amendment to a solicitation and related federal contract opportunity. The amendment revises the requirements for experience to include projects completed within the past 10 years. It also replaces multiple annex drawings with revised versions modifying the north elevation wall veneer from insulated metal panel to brick veneer on metal studs, including structural and architectural changes.
The federal contract opportunity is solicitation number N69450-20-R-0013 to design and construct a 124,670 square foot Aircraft Component Repair Facility and 82,207 square foot administrative headquarters building at Naval Air Station Corpus Christi, Texas. The work includes the buildings, utilities, site work, and energy efficient and sustainable features. The Department of the Navy Naval Facilities Engineering Command is the issuing agency. The closing date is not provided.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
AMENDMENT 0011 to N69450-20-R-0013 POWERTRAIN FACILITY - MACHINING NAS CORPUS CHRISTI, TX
Offerors must acknow ledge this amendment in w riting.
See Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945020R0013
X 9B. DATED (SEE ITEM 11)
15-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Jun-2020
CODE
NAVFAC SOUTHEAST
CORE CONSTRUCTION
BLDG 903 YORKTOWN
PO BOX 0030
JACKSONVILLE FL 32212-0030
N69450 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6945020R0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been added by full text:
AMENDMENT 0011
The purpose of this amendment is to:
1. Revise wording in the RFP associated with a relevant project.
2. Revise the ANNEX DRAWINGS: S101A, S102A, S103A, S502, S512, S523, A101, A101A, A102, A102A, A200, A201, A202, A301, A311, A312, A401, A511, A512, A513, A514, A601, A603, A611, A612, A613 and A614.
1. In the RFP under Factor 2 – Experience; under (a) (1) b.
ADD: (6) And, completed within the past 10 years from the date of RFP issue for this solicitation.
2. ANNEX DRAWINGS:
DELETE: The following sheets in their entirety:
• S101A page 74 of 345
• S102A page 77 of 345
• S103A page 80 of 345
• S502 page 84 of 345
• S512 page 87 of 345
• S523 page 91 of 345
• A101 page 94 of 345
• A101A page 95 of 345
• A102 page 97 of 345
• A102A page 98 of 345
• A200 page 108 of 345
• A201 page 109 of 345
• A202 page 110 of 345
• A301 page 112 of 345
• A311 page 115 of 345
• A312 page 116 of 345
• A401 page 117 of 345
• A511 page 121 of 345
• A512 page 122 of 345
• A513 page 123 of 345
• A514 page 124 of 345
• A601 page 127 of 345
• A603 page 129 of 345
• A611 page 131 of 345
• A612 page 132 of 345
• A613 page 133 of 345
• A614 page 134 of 345
ADD: The following sheets in their entirety, attached:
• 200528_S101A-REV1
• 200528_S102A-REV1
• 200528_S103A-REV1
• 200528_S502-REV1
N6945020R0013
• 200528_S512-REV1
• 200528_S523-REV1
• 200528_A101-REV1
• 200528_A101A-REV3
• 200528_A102-REV1
• 200528_A102A-REV3
• 200528_A200-REV1
• 200528_A201-REV1
• 200528_A202-REV1
• 200528_A301-REV1
• 200528_A311-REV2
• 200528_A312-REV1
• 200528_A401-REV1
• 200528_A511-REV1
• 200528_A512-REV1
• 200528_A513-REV1
• 200528_A514-REV1
• 200528_A601-REV2
• 200528_A603-REV2
• 200528_A611-REV1
• 200528_A612-REV1
• 200528_A613-REV1
• 200528_A614-REV1
The revised drawings modify the wall veneer of the north elevation from insulated metal panel to brick veneer on metal studs. The modifications include both structural and architectural changes, including but not limited to plans, elevations, sections, details and schedules. Note: The wall delineation in the floor plans will be updated to show brick veneer on other disciplines floor plans with the final conformed contract documents.
(End of Summary of Changes)