This solicitation amendment modifies solicitation N69450-20-R-0013 to design and construct a new Aircraft Component Repair Facility and administrative headquarters office building for Naval Air Station Corpus Christi, Texas. The amendment extends the proposal due date to May 29, 2020. It revises language related to design experience and past performance requirements. It also replaces or modifies several specification sections and drawings related to testing and balancing, computer room air conditioning units, spray foam insulation, doors and frames, glazing, roller shades, and building layouts. The work will consist of two new facilities totaling over 200,000 square feet to support rotary wing aircraft component rebuild activities. Both buildings will include administrative space, rest rooms, support space, and connecting utilities systems. The repair facility will feature flexible manufacturing space while both buildings aim to achieve sustainability and energy efficiency goals.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
AMENDMENT 0005 to N69450-20-R-0013 POWERTRAIN FACILITY - MACHINING NAS CORPUS CHRISTI, TX
Offerors must acknow ledge this amendment in w riting.
See Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-May-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945020R0013
X 9B. DATED (SEE ITEM 11)
15-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-May-2020
CODE
NAVFAC SOUTHEAST
CORE CONSTRUCTION
BLDG 903 YORKTOWN
PO BOX 0030
JACKSONVILLE FL 32212-0030
N69450 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6945020R0013
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been added by full text:
AMENDMENT 0005
The purpose of this amendment is to:
1. Extend the proposal due date to Friday, May 29, 2020 at 3:30 PM Eastern Time.
2. Revise RFP language page 19 related to Design Experience.
3. Revise ANNEX Specification SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.
4. Revise ANNEX Specification SECTION 23 81 23.00 20 COMPUTER ROOM AIR CONDITIONING UNITS.
5. Add ANNEX Specification Section 07 27 36 SPRAY FOAM INSULATION.
6. Revise ANNEX Specification Section 08 11 16 ALUMINUM DOORS AND FRAMES.
7. Revise ANNEX Specification Section 08 81 00 GLAZING.
8. Revise ANNEX Specification Section 12 24 13 ROLLER WINDOW SHADES.
9. Revise ANNEX Drawings A101, A101A, A101B, and A722.
2. Amend RFP language page 19 related to Design Experience
In first paragraph, first sentence, following “performing relevant construction” DELETE: “and design projects” Under Factor 3 - Past Performance (a) (a) Solicitation Submittal Requirements DELETE: Entire second sentence: “If a completed AE Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for design experience.”
In third sentence, following “for each project included in Factor 2” d DELETE: “both” and “and Design Experience”.
3. ANNEX Specification Section 23 05 93 Testing, Adjusting, and Balancing for HVAC:
DELETE: entire section titled “23 05 93” ADD: new section titled “23 05 93 REV 1 20200504,” which is attached. Note Appendix D updated.
4. ANNEX Specification SECTION 23 81 23.00 20 Computer Room Air Conditioning Units:
DELETE: entire section titled “23 81 23.00 20” ADD: new section title “23 81 23.00 20 REV 1 20200504,” which is attached. Note updated section 2.1.
5. ANNEX Specification Section 07 27 36 SPRAY FOAM INSULATION:
ADD: Entire specification section 07 27 36 is attached.
6. ANNEX Specification Section 08 11 16 ALUMINUM DOORS AND FRAMES:
DELETE: In Section 1.5.1 Shop Drawing, delete the last sentence, “A qualified blast engineer must perform testing or calculations for door system design resistance to specified blast loads.”
7. ANNEX Specification Section 08 81 00 GLAZING:
DELETE: In Section 2.1.2 Laminated Glass, delete the 2nd paragraph, “Design window glazing using a dynamic analysis or testing from airblast loading in accordance with ASTM F1642/F1642M by an independent testing agency regularly engaged in blast
N6945020R0013 testing to prove the glazing will provide performance equivalent to or better than a low] hazard rating in accordance with ASTM F2912.”
8. ANNEX Specification Section 12 24 13 ROLLER WINDOW SHADES:
In Paragraph 1.5.1.1 Manufacturer’s Qualifications:
DELETE: “Obtain motor-controlled roller shades through one source from a single manufacturer with a minimum of twenty years of experience and minimum of three projects of similar scope and size in manufacturing products comparable to those specified in this section.”
ADD: “Obtain roller shades through one source from a single manufacturer with a minimum of twenty years of experience and minimum of three projects of similar scope and size in manufacturing products comparable to those specified in this section.”
9. ANNEX DRAWINGS:
Revised Sheet “200506_A101_REV1” is attached. The revision corrects the footnote designation from “4” to “5” in the partition types, directing the reader to the GWB notes.
Revised Sheet “200507_A101A_REV1” is attached. The revised drawing provides the missing room names and room numbers, provides shelving requirements for Storage 128 and Storage 129 and provides a description of for the NEX Retail 110.
Revised Sheet “200507_A101B_REV1” is attached. The revised drawing provides the missing room names and room numbers.
Revised Sheet “200507_A722_REV1” which is attached. The revised drawing provides a screen panel in Casework Elevation 5 for Security 102.
(End of Summary of Changes)