RELEASED 11-R-0020 AMD 0006.doc

DOC document 221 KB Posted

Attached to
Turboprop Engine Test Instrumentation system (TPTI)
Solicitation number
N68335-11-R-0020
Issued by

About this file

AMENDMENT 0006

View the file

Other files

File Type Posted
EXHIBITS A L TPTI CDRLs 3-9-11.doc DOC document
RELEASED 11-R-0020 AMD 0005.doc DOC document
Attach 10 PBP milestones 2-28-11.xls XLS spreadsheet
RELEASED 11-R-0020 AMD 0003.doc DOC document
RELEASED 11-R-0020 AMD 0002.doc DOC document
Attach 10 PBP milestones 2-17-11.xls XLS spreadsheet
RELEASED 11-R-0020 AMD 0001.doc DOC document
EXHIBITS A L TPTI CDRLs 2-10-11.doc DOC document
EXHIBITS A L TPTI CDRLs 7-30-10.doc DOC document
Attach 9 TPTI ILSSOW 10-14-10.doc DOC document
RELEASED N68335-11-R-0020 RFP TPTI.doc DOC document
Attach 6 System Software Configuration COTS and GFP.doc DOC document
Attach 10 PBP milestones 11-24-10.xls XLS spreadsheet
Attach 1 TPTI Production SOW 7-30-10.doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

1. The purpose of this amendment is to provide technical clarification to offerors on solicitation N68335-11-R-0020 Turboprop Test Instrumentation (TPTI) system as follows:

QUESTION 1:

Do you want receipt via email of signed amendments to solicitation N68335-11-R-0020 or only the original and hard copy that will be included in Volume IV of our proposal?

ANSWER 1:

Proposals are not to be submitted via facsimile or electronically via e-mail. Signed amendments shall be submitted in accordance with Section L of the solicitation.

QUESTION 2:

There are some CLINs/CDRLs that appear to be required, at least from a funding standpoint, in only Yr 1 (e.g. CLIN 0018/CDRL A014 Incident Reports, CLIN 0007, CDRL A003 PSR: list is not all inclusive). Please confirm whether these type of CLINs/CDRLs will only be required in Yr 1 or whether they will require delivery throughout the 3 year life of the contract. If these type of CLINs/CDRLs are required throughout the life of the contract, but are funded in only year 1, will they be fully paid in Year 1?

ANSWER 2:

CDRLs A003 and A014 will be required in Years 2 and 3 as well. See Sections A, B, C, D, E, J, M and FAR 52.211-8.

2. The solicitation closing date is not extended.

3. Contracts POC: Sarah McCarty, 732-323-4479 or sarah.mccarty@navy.mil

SECTION A - SOLICITATION/CONTRACT FORM

The following have been modified:

SECTION A

1. This will be a Fixed-Price Indefinite Delivery/Indefinite Quantity (ID/IQ) contract for the procurement of one (1) pilot production Turboprop Test Instrumentation (TPTI) system; up to eleven (11) TPTI production units; two (2) pilot production Test Program Sets (TPS); up to two (2) TPS production units; technical and logistics data items; package, deliver and install of pilot production and production TPTI and TPS systems; up to 1,300 hours of Engineering Support Services; up to 700 hours of Technical Representative Support Services; up to $75,000 in travel costs for the Technical Representative Support Services; up to 1,200 hours of Integrated Logistics Support (ILS) Contractor Support; and T-19A Site Survey and Analysis in accordance with Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010; Attachment 3, "TPTI System Acceptance Test Procedure," dated 16 December 2010; Attachment 4, "T56-A-425/427 TPS Acceptance Test Procedure," dated 16 December 2010; Attachment 5, "T56-A-427A TPS Acceptance Test Procedure," dated 16 December 2010; Attachment 6, "System Software Configuration – COTS and GFP," dated 16 December 2010; Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010; Attachment 8, "T56-A-427A Technical Data Package (TDP) 3654AS8800 Series," dated 16 December 2010; Attachment 9, "Integrated Logistics Support Statement of Work," dated 14 October 2010; Exhibit A, DD Form 1423, CDRLs, dated 30 July 2010; and Exhibit L, DD Form 1423, CDRLs, dated 30 July 2010.

2. A Single-Award contract is intended to be issued for this requirement.

3. The guaranteed minimum for the contract is one (1) Pilot Production TPTI system (CLIN 0001); two (2) Pilot Production Test Program Sets (TPS) (CLINs 0002 and 0003); and package, deliver and install of pilot production TPTI and TPS systems (CLIN 0004). The guaranteed minimum will be met on Delivery Order 0001 upon award of the basic contract.

4. The maximum quantity that may be ordered under the contract is twelve (12) TPTI systems, including Pilot Production Units (PPUs); four (4) TPSs, including PPUs; all technical and logistics data items; package, deliver and install of pilot production and production TPTI and TPS systems; 1,300 hours of Engineering Support Services; 700 hours of Technical Representative Support Services; $75,000 in travel costs for the Technical Representative Support Services; 1,200 hours of Integrated Logistics Support (ILS) Contractor Support; and T-19A Site Survey and Analysis.

5. Delivery Orders may be placed as follows:

Year 1 CLINs 0001 through 0032: at contract award

Year 1 CLIN 0033 through 0046: from date of contract award through 365 days after Government release for production.

Year 1 CLINs 0047 through 0050: from date of contract award through 365 days after contract award (DAC).

Year 2 CLINs 0100 through 0116: from date of Government release for production through 365 days after Government release for production.

Year 2 CLINs 0117 through 0131: from 366 DAC through 730 DAC.

Year 3 CLINs 0200 through 0218: from 366 days after Government release for production through 730 days after Government release for production.

Year 3 CLINs 0219 through 0225: from 730 DAC through 1,095 DAC.

6. The completion of Contractor and Government Pilot Production Testing, Release for Production, and the issuance of delivery orders are separate events. Release for Production must be granted before production may commence. In no case will release for production be granted prior to successful completion of Contractor and Government Pilot Production Testing.

7. For clarification purposes, the term Pilot Production is synonymous with First Article.

8. The Pilot Production Units are not considered part of the production quantity. The contractor will deliver up to 12 TPTI systems (including Pilot Production Units) and four (4) Test Program Sets (including Pilot Production Units).

9. Two (2) pilot production TPS will be ordered in conjunction with the one (1) Pilot Production Unit, and two (2) production TPS will be ordered in conjunction with the first TPTI production unit. The TPS for the remaining TPTI Systems will be developed separately and provided as GFE at a later date.

10. This contract contains export-controlled technical data, subject to disclosure restrictions. Attention is directed to the following clauses contained in this contract:

DFARS 252.204-7008, Requirements for Contracts Involving Export-Controlled Items (Apr 2010)

NAVAIR 5252.227-9507, Notice Regarding the Handling and Dissemination of Export-Controlled Technical Data (NAVAIR)(OCT 2005)

11. In addition to the Government Property identified in NAVAIR clause 5252.245-9500 Government Property for the Performance of this Contract, the Government will also provide Government-furnished software, specifically TPTI DAQ software, as detailed in Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; see Section J.

12. Proposal validity shall be for 180 days or longer as annotated by the offeror in Block 12 of the cover page of the SF33.

13. The Government point of contact is:

Sarah McCarty

Contract Specialist sarah.mccarty@navy.mil

14. Mail Proposals to:

NAWCAD Contracts Dept.

Attn: Sarah McCarty, Code: 2.5.2.1.1

HWY 547

Bldg, 562-3

Lakehurst, NJ 08733

In accordance with Section L, sealed offers with original and five (5) copies of the Technical, Experience and Past Performance Volumes and one (1) copy of the Price Volume for furnishing the supplies or services in the Schedule are due by 04:00 PM Eastern Time on 25 February 2011. Proposals are not to be submitted via facsimile or electronically via e-mail.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0130 is added as follows:

ITEM NO
SUPPLIES/SERVICES
MAX QUANTITY
UNIT
UNIT PRICE
MAX AMOUNT
1
Lot

Year 2 Program Status Reports

FFP

IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003

NOT SEPARATELY PRICED

FOB: Destination

MAX

NET AMT

CLIN 0131 is added as follows:

ITEM NO
SUPPLIES/SERVICES
MAX QUANTITY
UNIT
UNIT PRICE
MAX AMOUNT
1
Lot

Year 2 Incident Reports

Incident Reports / Failure Report and Corrective Action (FRACAS)

IAW Engineering SOW Paragraph 3.26 and Exhibit A, CDRL A014

MAX

CLIN 0224 is added as follows:

ITEM NO
SUPPLIES/SERVICES
MAX QUANTITY
UNIT
UNIT PRICE
MAX AMOUNT
1
Lot

Year 3 Program Status Reports

IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003

NOT SEPARATELY PRICED

MAX

CLIN 0225 is added as follows:

ITEM NO
SUPPLIES/SERVICES
MAX QUANTITY
UNIT
UNIT PRICE
MAX AMOUNT
1
Lot

Year 3 Incident Reports

Incident Reports / Failure Report and Corrective Action (FRACAS)

IAW Engineering SOW Paragraph 3.26 and Exhibit A, CDRL A014

MAX

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

SECTION C

Item 0001 – Year 1 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.

Item 0002 – Year 1 – The contractor shall provide Pilot Production Unit -- Test Program Set (TPS) for T56-425/-427, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.

Item 0003 – Year 1 – The contractor shall provide Pilot Production Unit -- Test Program Set (TPS) for T56-427A, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” dated 16 December 2010.

Item 0004 – Year 1 – The contractor shall Package, Deliver, and Install the A/E37T-17A Mobile Turboprop Engine Test System for CLINs 0001, 0002, and 0003: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NAS Norfolk.

Item 0005 – Year 1 – The contractor shall provide Integrated Master Plan IAW Engineering SOW Paragraph 3.6 and Exhibit A, CDRL A001.

Item 0006 – Year 1 – The contractor shall provide Integrated Master Schedule IAW Engineering SOW Paragraph 3.7 and Exhibit A, CDRL A002.

Item 0007 – Year 1 – The contractor shall provide Program Status Reports IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003.

Item 0008 – Year 1 – The contractor shall provide Meeting Agendas IAW Engineering SOW Paragraph 3.9 and Exhibit A, CDRL A004.

Item 0009 – Year 1 – The contractor shall provide Meeting Minutes IAW Engineering SOW Paragraph 3.12 and Exhibit A, CDRL A005.

Item 0010 – Year 1 – The contractor shall provide Configuration Management Plan IAW Engineering SOW Paragraph 3.18 and Exhibit A, CDRL A006.

Item 0011 – Year 1 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.

Item 0012 – Year 1 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.

Item 0013 – Year 1 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.

Item 0014 – Year 1 – The contractor shall provide Conformity Inspection Plan IAW Engineering SOW Paragraph 3.21.2.1 and Exhibit A, CDRL A010.

Item 0015 – Year 1 – The contractor shall provide Conformity Inspection Report IAW Engineering SOW Paragraph 3.21.2.2 and Exhibit A, CDRL A011.

Item 0016 – Year 1 – The contractor shall provide Technical Data Package (TDP) Updates IAW Engineering SOW Paragraph 3.23 and Exhibit A, CDRL A012.

Item 0017 – Year 1 – The contractor shall provide Quality Assurance (QA) Plan IAW Engineering SOW Paragraph 3.16 and Exhibit A, CDRL A013.

Item 0018 – Year 1 – The contractor shall provide Incident Reports / Failure Report and Corrective Action (FRACAS) IAW Engineering SOW Paragraph 3.26 and Exhibit A, CDRL A014.

Item 0019 – Year 1 – The contractor shall provide Component Data IAW Engineering SOW Paragraph 3.35 and Exhibit A, CDRL A015.

Item 0020 – Year 1 – The contractor shall provide Integration & Production Test Plan IAW Engineering SOW Paragraph 4.2 and Exhibit A, CDRL A016.

Item 0021 – Year 1 – The contractor shall provide Acceptance Test Report -- Pilot Production Unit (PPU) IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A017.

Item 0022 – Year 1 – The contractor shall provide Long Lead Items List IAW Engineering SOW Paragraph 3.32.1.13 and Exhibit A, CDRL A019.

Item 0023 – Year 1 – The contractor shall provide Hazardous Material Management Report IAW Engineering SOW Paragraph 3.29 and Exhibit A, CDRL A020.

Item 0024 – Year 1 – The contractor shall provide Item Unique Identification (IUID) Plan IAW Engineering SOW Paragraph 3.36.3 and Exhibit A, CDRL A021.

Item 0025 – Year 1 – The contractor shall provide Production Manufacturing Review IAW Engineering SOW Paragraph 3.14 and Exhibit A, CDRL A023.

Item 0026 – Year 1 – The contractor shall provide Obsolescence Management Plan IAW Engineering SOW Paragraph 3.24.1.1 and Exhibit A, CDRL A024.

Item 0027 – Year 1 – The contractor shall provide Obsolescence Reports IAW Engineering SOW Paragraph 3.24.1.2 and Exhibit A, CDRL A025.

Item 0028 – Year 1 – The contractor shall provide Trade Study IAW Engineering SOW Paragraph 3.24.1.4 and Exhibit A, CDRL A026.

Item 0029 – Year 1 – The contractor shall provide Regression Test Plan IAW Engineering SOW Paragraph 3.24.1.5 and Exhibit A, CDRL A027.

Item 0030 – Year 1 – The contractor shall provide Vendor Data IAW Integrated Logistics Support (ILS) SOW Paragraph 1.1.3.3.2 and Exhibit L, CDRL L001.

Item 0031 – Year 1 – The contractor shall provide Meeting Agenda, ILSMT IAW ILSSOW Paragraph 1.1.3.4.2.d and Exhibit L, CDRL L002.

Item 0032 – Year 1 – The contractor shall provide Meeting Minutes, ILSMT IAW ILSSOW Paragraph 1.1.3.4.2.f and Exhibit L, CDRL L003.

Item 0033 – Year 1 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.

Item 0034 – Year 1 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.

Item 0035 – Year 1 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.

Item 0036 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0034 and 0035: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0037 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0038 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0039 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0040 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0041 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0042 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0043 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0044 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0045 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0046 – Year 1 – The contractor shall provide Acceptance Test Report--Production Units IAW Engineering SOW Paragraph 4.6.4 and Exhibit A, CDRL A018.

Item 0047 – Year 1 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0048 – Year 1 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0049 – Year 1 – The contractor shall provide Travel for CLIN 0048 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.

Item 0050 – Year 1 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.

Item 0100 – Year 2 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.

Item 0101 – Year 2 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.

Item 0102 – Year 2 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.

Item 0103 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0101 and 0102: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0104 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0105 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0106 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0107 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0108 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0109 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0110 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0111 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0112 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0113 – Year 2 – The contractor shall provide Acceptance Test Report--Production Units IAW Engineering SOW Paragraph 4.6.4 and Exhibit A, CDRL A018.

Item 0114 – Year 2 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.

Item 0115 – Year 2 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.

Item 0116 – Year 2 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.

Item 0117 – Year 2 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0118 – Year 2 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0119 – Year 2 – The contractor shall provide Travel for CLIN 0118 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.

Item 0120 – Year 2 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.

Item 0121 – Year 2 – The contractor shall provide T-19A site survey and functional/requirements analysis IAW Para 3.32.1.3 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0122 – Year 2 – The contractor shall provide T-19A Facility Design IAW Engineering SOW Paragraph 3.32.1.3 and Exhibit A, CDRL A028.

Item 0123 – Year 2 – The contractor shall provide T-19A Installation Control drawings (ICD) IAW Engineering SOW Paragraph 3.32.1.4 and Exhibit A, CDRL A029.

Item 0124 – Year 2 – The contractor shall provide T-19A Installation Hardware Kit Drawing IAW Engineering SOW Paragraph 3.32.1.6 and Exhibit A, CDRL A030.

Item 0125 – Year 2 – The contractor shall provide Engineering Drawing Package T-19A IAW Engineering SOW Paragraph 3.32.1.7.2 and Exhibit A, CDRL A031.

Item 0126 – Year 2 – The contractor shall provide T-19A Technical Reviews IAW Engineering SOW Paragraph 3.32.1.8 and Exhibit A, CDRL A032.

Item 0127 – Year 2 – The contractor shall provide Update Maintenance Plan Data IAW ILSSOW Paragraph 1.1.4.1.5 and Exhibit L, CDRL L004.

Item 0128 – Year 2 – The contractor shall provide Technical Manual Change Data IAW ILSSOW Paragraph 1.1.5.1 and Exhibit L, CDRL L005.

Item 0129 – Year 2 – The contractor shall provide Contractor Support (ILS) IAW Attachment 9, "Integrated Logistics Support Statement of Work," dated 14 October 2010.

Item 0130 – Year 2 – The contractor shall provide Program Status Reports IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003.

Item 0131 – Year 2 – The contractor shall provide Acceptance Test Report -- Pilot Production Unit (PPU) IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A017.

Item 0200 – Year 3 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.

Item 0201 – Year 3 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.

Item 0202 – Year 3 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.

Item 0203 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0201 and 0202: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0204 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0205 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0206 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0207 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0208 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0209 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0210 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0211 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0212 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0213 – Year 3 – The contractor shall provide Fixed Turboprop Engine Test System, Part Number 3654AS7300-2, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0214 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-19A Fixed Turboprop Engine Test System for 1 unit under CLIN 0205: provide Navy acceptance testing at/for/to: NAS Misawa, Japan. The TPS for the TPTI production unit under CLIN 0205 is not a part of this contract. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0215 – Year 3 – The contractor shall provide Acceptance Test Report -- Production Unit IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A018.

Item 0216 – Year 3 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.

Item 0217 – Year 3 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.

Item 0218 – Year 3 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.

Item 0219 – Year 3 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0220 – Year 3 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Item 0221 – Year 3 – The contractor shall provide Travel for CLIN 0220 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.

Item 0222 – Year 3 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.

Item 0223 – Year 3 – The contractor shall provide Contractor Support (ILS) IAW Attachment 9, "Integrated Logistics Support Statement of Work," dated 14 October 2010.

Item 0224 – Year 3 – The contractor shall provide Program Status Reports IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003.

Item 0225 – Year 3 – The contractor shall provide Acceptance Test Report -- Pilot Production Unit (PPU) IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A017.

SECTION D - PACKAGING AND MARKING

The following have been modified:

Items 0001-0003, 0033-0035, 0100-0102, and 0200-0202, 0213 – The Contractor shall package, pack and mark supplies in accordance with NAVAIR clauses 5252.223-9502, “Hazardous Material”; 5252.247-9509, “Preservation, Packaging, Packing and Marking”; 5252.247-9503, “Marking Of Warranted Items”; and 5252.247-9508, “Prohibited Packing Materials.”

Items 0005-0032, 0046, 0050, 0113-0116, 0120, 0122-0128, 0130-0131, 0215-0218, 0222, and 0224-0225 – The Contractor shall package, pack and mark data items in with Exhibits A and L in accordance NAVAIR clause 5252.247-9507, “Packaging and Marking of Reports; and 5252.247-9503, “Marking Of Warranted Items.”

Items 0004, 0036-0045, 0047-0049, 0103-0112, 0117-0119, 0121, 0213-0212, 0214, 0219-0221, and 0223 – Not Applicable

SECTION E - INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0130:

INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
Destination
Government
Destination
Government

The following Acceptance/Inspection Schedule was added for CLIN 0131:

INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
Destination
Government
Destination
Government

The following Acceptance/Inspection Schedule was added for CLIN 0224:

INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
Destination
Government
Destination
Government

The following Acceptance/Inspection Schedule was added for CLIN 0225:

INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
Destination
Government
Destination
Government

SECTION E

Inspection and Acceptance of the TPTI shall be in accordance with Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.

Items 0001-0003, 0033-0035, 0100-0102, 0200-0202 and 0213 – Initial inspection of the supplies to be furnished hereunder shall be made by DCMA Quality Assurance Representative at the contractor’s or subcontractor’s plant located at Contractor's Facility. Final inspection and acceptance shall be made by US Navy at Receiving Activity.

Items 0005-0032, 0046, 0050, 0113-0116, 0120, 0122-0128, 0130-0131, 0215-0218, 0222, and 0224-0225 – Destination inspection and acceptance of all data items to be furnished hereunder will be made in accordance with Exhibits A and L, Contract Data Requirements List, DD Form 1423.

Items 0004, 0036-0045, 0103-0112, 0121, 0203-0212 and 0214 – Inspection and acceptance of Package, Delivery and Install and of T-19A Site Survey and Analysis at destination shall be made by US Navy at Receiving Activity.

Items 0047, 0117, and 219 – Inspection and acceptance of the services to be furnished hereunder will be made at Contractor's Facility or such locations as designated by the Procuring Contracting Officer (PCO).

Items 0048-0049, 0118-0119, 0129, 0220-0221 and 223 – Inspection and acceptance of the services to be furnished hereunder will be made at destination as designated by the Procuring Contracting Officer (PCO).

SECTION F - DELIVERIES OR PERFORMANCE

The following have been modified:

Items 0001-0050, 0100-0131 and 0200-0225 – Deliveries of the supplies, services and data items to be furnished hereunder shall be in accordance with FAR 52.211-8, “Time Of Delivery.”

52.211-8

TIME OF DELIVERY (JUN 1997)

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

Required Delivery Schedule

ITEM NUMBER
QTY
WITHIN DAYS AFTER DATE OF

CONTRACT (DAC) AWARD

DELIVERY ADDRESS

0001
1 EA
Year 1 – Pilot Production Unit--TPTI A/E37T-17A

Contractor Testing of PPUs shall be completed within 270 days after contract award (DAC).

Pilot Production Units are separate from production units and will not be counted as production units.

Contractor testing commences at contractor facility

Specific delivery address for Government testing will be provided at a later date.

NAS Norfolk

DODAAC: N00188

FOB: DESTINATION

0002
1 EA
Year 1 – Pilot Production Unit -- Test Program Set (TPS) for T56-425/-427

SAME AS CLIN 0001

Contractor testing commences at contractor facility

Specific delivery address for Government testing will be provided at a later date.

NAS Norfolk

DODAAC: N00188

FOB: DESTINATION

0003
1 EA
Year 1 – Pilot Production Unit -- Test Program Set (TPS) for T56-427A

SAME AS CLIN 0001

Contractor testing commences at contractor facility

Specific delivery address for Government testing will be provided at a later date.

NAS Norfolk

DODAAC: N00188

FOB: DESTINATION

0004
1 EA
Year 1 – Package, Deliver and Install for CLINs 0001, 0002, and 0003: NAS Norfolk

SAME AS CLIN 0001

Contractor testing commences at contractor facility

Specific delivery address will be provided at a later date.

NAS Norfolk

DODAAC: N00188

FOB: DESTINATION

0005-0020
1 LOT
Year 1 – IAW DD FORM 1423

DODAAC: N68335

FOB: DESTINATION

0021
3 EA
Year 1 Acceptance Test Report -- PPU

DODAAC: N68335

FOB: DESTINATION

0022-0032
1 LOT
Year 1 – IAW DD FORM 1423

DODAAC: N68335

0033
MAX 10 EA
Year 1 – Production Unit--TPTI A/E37T-17A

Delivery of production units shall commence 180 days after award of the delivery order at a rate of one (1) every 120 days, provided release for production has been granted.

SEE NOTE 1 BELOW

IAW Package, Deliver, Install CLINs

0034
1 EA
Year 1 – Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine

SAME AS CLIN 0033

SEE NOTE 1 BELOW

IAW Package, Deliver, Install CLINs

FOB: DESTINATION

0035
1 EA
Year 1 – Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine

SAME AS CLIN 0033

IAW Package, Deliver, Install CLINs

0036
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system and TPSs from CLINs 0034 and 0035: NWS Pt Mugu, CA

SAME AS CLIN 0033

Specific delivery address will be provided at a later date.

NWS Pt Mugu, CA

DODAAC: N0429A

FOB: DESTINATION

0037
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

Specific delivery address will be provided at a later date.

NAS Jacksonville, FL

DODAAC: N00207

FOB: DESTINATION

0038
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

Specific delivery address will be provided at a later date.

DODAAC: N00207

FOB: DESTINATION

0039
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: NAS Whidbey Island, WA

SAME AS CLIN 0033

Specific delivery address will be provided at a later date.

NAS Whidbey Island, WA

DODAAC: N00620

FOB: DESTINATION

0040
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: JRB Fort Worth, TX

SAME AS CLIN 0033

Specific delivery address will be provided at a later date.

JRB Fort Worth, TX

DODAAC: N44487

FOB: DESTINATION

0041
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: NAS Patuxent River, MD

Specific delivery address will be provided at a later date.

NAS Patuxent River, MD

DODAAC: N39782

FOB: DESTINATION

0042
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: MALS-49 Stewart AFB, Newburgh, NY

Specific delivery address will be provided at a later date.

MALS-49 Stewart AFB, Newburgh, NY

DODAAC: N55555

FOB: DESTINATION

0043
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: MCAS Kaneohe Bay, HI

Specific delivery address will be provided at a later date.

MCAS Kaneohe Bay, HI

DODAAC: N09124

FOB: DESTINATION

0044
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: NAS JRB New Orleans, LA

Specific delivery address will be provided at a later date.

NAS JRB New Orleans, LA

DODAAC: N44490

FOB: DESTINATION

0045
1 EA
Year 1 – Package, Deliver, and Install for 1 TPTI system: Taiwan

Specific delivery address will be provided at a later date.

Taiwan

DODAAC: TBD

FOB: DESTINATION

0046
MAX

12 EA

Year 1 Acceptance Test Rpt--Prod Units
DODAAC: N68335

FOB: DESTINATION

0047
MAX

500 HOURS

Year 1 – Engineering Support Services

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0048
MAX

200 HOURS

Year 1 – Technical Rep Support Services

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0049
1 EA
Year 1 – Travel for CLIN 0040

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0050
MAX

12 EA

Year 1 – IAW DD FORM 1423

DODAAC: N68335

0100
MAX 10 EA
Year 2 – Production Unit--TPTI A/E37T-17A

Delivery of production units shall commence 180 days after award of the delivery order at a rate of one (1) every 120 days, provided release for production has been granted.

SEE NOTE 1 BELOW

IAW Package, Deliver, Install CLINs

FOB: DESTINATION

0101
1 EA
Year 2 – Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine

SAME AS CLIN 0100

SEE NOTE 1 BELOW

IAW Package, Deliver, Install CLINs

FOB: DESTINATION

0102
1 EA
Year 2 – Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine

SAME AS CLIN 0100

SEE NOTE 1 BELOW

IAW Package, Deliver, Install CLINs

FOB: DESTINATION

0103
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system and TPSs from CLINs 0101 and 0102: NWS Pt Mugu, CA

SAME AS CLIN 0100

Specific delivery address will be provided at a later date.

NWS Pt Mugu, CA

DODAAC: N0429A

FOB: DESTINATION

0104
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

SAME AS CLIN 0100

Specific delivery address will be provided at a later date.

DODAAC: N00207

FOB: DESTINATION

0105
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

Specific delivery address will be provided at a later date.

DODAAC: N00207

FOB: DESTINATION

0106
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: NAS Whidbey Island, WA

Specific delivery address will be provided at a later date.

NAS Whidbey Island, WA

DODAAC: N00620

FOB: DESTINATION

0107
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: JRB Fort Worth, TX

SAME AS CLIN 0100

Specific delivery address will be provided at a later date.

JRB Fort Worth, TX

DODAAC: N44487

FOB: DESTINATION

0108
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: NAS Patuxent River, MD

Specific delivery address will be provided at a later date.

DODAAC: N39782

FOB: DESTINATION

0109
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: MALS-49 Stewart AFB, Newburgh, NY

Specific delivery address will be provided at a later date.

DODAAC: N55555

FOB: DESTINATION

0110
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: MCAS Kaneohe Bay, HI

Specific delivery address will be provided at a later date.

DODAAC: N09124

FOB: DESTINATION

0111
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: NAS JRB New Orleans, LA

Specific delivery address will be provided at a later date.

NAS JRB New Orleans, LA

DODAAC: N44490

FOB: DESTINATION

0112
1 EA
Year 2 – Package, Deliver, and Install for 1 TPTI system: Taiwan

Specific delivery address will be provided at a later date.

Taiwan

DODAAC: TBD

FOB: DESTINATION

0113
MAX

12 EA

Year 2 – IAW DD FORM 1423

DODAAC: N68335

0114-0116
1 LOT
Year 2 – IAW DD FORM 1423

DODAAC: N68335

0117
MAX

600 HOURS

Year 2 – Engineering Support Services

TBD

FOB: DESTINATION

0118
MAX

200 HOURS

Year 2 – Technical Rep Support Services

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0119
1 EA
Year 2 – Travel for CLIN 0110

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0120
1 LOT
Year 2 – IAW DD FORM 1423

DODAAC: N68335

0121
1 EA
Year 2 – T-19A Site Survey and Analysis

360 days prior to installation date

TBD

DODAAC: N68335

FOB: DESTINATION

0122-0128
1 LOT
Year 2 – IAW DD FORM 1423

DODAAC: N68335

0129
MAX

600 Hours Year 2 – Contractor Support (ILS)

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0130-0131
1 LOT
Year 2 – IAW DD FORM 1423

DODAAC: N68335

0200
MAX

10 EA

Year 3 – Production Unit--TPTI A/E37T-17A

Delivery of production units shall commence 180 days after award of the delivery order at a rate of one (1) every 120 days, provided release for production has been granted.

IAW Package, Deliver, Install CLINs

0201
1 EA
Year 3 – Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine

SAME AS CLIN 0200

IAW Package, Deliver, Install CLINs

0202
1 EA
Year 3 – Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine

IAW Package, Deliver, Install CLINs

0203
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system and TPSs from CLINs 0101 and 0102: NWS Pt Mugu, CA

SAME AS CLIN 0200

Specific delivery address will be provided at a later date.

NWS Pt Mugu, CA

DODAAC: N0429A

FOB: DESTINATION

0204
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

Specific delivery address will be provided at a later date.

DODAAC: N00207

FOB: DESTINATION

0205
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: NAS Jacksonville, FL

Specific delivery address will be provided at a later date.

DODAAC: N00207

FOB: DESTINATION

0206
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: NAS Whidbey Island, WA

Specific delivery address will be provided at a later date.

NAS Whidbey Island, WA

DODAAC: N00620

FOB: DESTINATION

0207
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: JRB Fort Worth, TX

SAME AS CLIN 0200

Specific delivery address will be provided at a later date.

JRB Fort Worth, TX

DODAAC: N44487

FOB: DESTINATION

0208
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: NAS Patuxent River, MD

Specific delivery address will be provided at a later date.

DODAAC: N39782

FOB: DESTINATION

0209
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: MALS-49 Stewart AFB, Newburgh, NY

Specific delivery address will be provided at a later date.

DODAAC: N55555

FOB: DESTINATION

0210
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: MCAS Kaneohe Bay, HI

Specific delivery address will be provided at a later date.

DODAAC: N09124

FOB: DESTINATION

0211
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: NAS JRB New Orleans, LA

SAME AS CLIN 0200

Specific delivery address will be provided at a later date.

NAS JRB New Orleans, LA

DODAAC: N44490

FOB: DESTINATION

0212
1 EA
Year 3 – Package, Deliver, and Install for 1 TPTI system: Taiwan

SAME AS CLIN 0200

Specific delivery address will be provided at a later date.

Taiwan

DODAAC: TBD

FOB: DESTINATION

0213
1 EA
Year 3 – TPTI A/E37T-19A

Contractor Testing shall be completed within 270 days after award of the delivery order.

Contractor testing commences at contractor facility

Specific delivery address for Government testing will be provided at a later date.

NAS Misawa, Japan

DODAAC: N68212

FOB: DESTINATION

0214
1 EA
Year 3 – Package, Deliver, and Install for 1 unit under CLIN 0213: NAS Misawa, Japan

SAME AS CLIN 0213

Specific delivery address will be provided at a later date.

NAS Misawa, Japan

DODAAC: N68212

FOB: DESTINATION

0215
MAX

13 EA

Year 3 – IAW DD FORM 1423

DODAAC: N68335

0216-0218
1 LOT
Year 3 – IAW DD FORM 1423

DODAAC: N68335

0219
MAX

200 HOURS

Year 3 – Engineering Support Services

TBD

FOB: DESTINATION

0220
MAX

300 HOURS

Year 3 – Technical Rep Support Services

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0221
1 EA
Year 3 – Travel for CLIN 0212

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0222
1 LOT
Year 3 – IAW DD FORM 1423

DODAAC: N68335

0223
MAX

600 Hours Year 3 – Contractor Support (ILS)

As Required

TBD

DODAAC: N68335

FOB: DESTINATION

0224-0225
1 LOT
Year 3 – IAW DD FORM 1423

DODAAC: N68335

NOTE 1: The award of delivery orders and release for production are separate events. Both must occur before production may commence.