RELEASED 11-R-0020 AMD 0003.doc

DOC document 39 KB Posted

Attached to
Turboprop Engine Test Instrumentation system (TPTI)
Solicitation number
N68335-11-R-0020
Issued by

About this file

AMENDMENT 0003

View the file

Other files

File Type Posted
EXHIBITS A L TPTI CDRLs 3-9-11.doc DOC document
RELEASED 11-R-0020 AMD 0006.doc DOC document
RELEASED 11-R-0020 AMD 0005.doc DOC document
Attach 10 PBP milestones 2-28-11.xls XLS spreadsheet
RELEASED 11-R-0020 AMD 0002.doc DOC document
Attach 10 PBP milestones 2-17-11.xls XLS spreadsheet
RELEASED 11-R-0020 AMD 0001.doc DOC document
EXHIBITS A L TPTI CDRLs 2-10-11.doc DOC document
EXHIBITS A L TPTI CDRLs 7-30-10.doc DOC document
Attach 9 TPTI ILSSOW 10-14-10.doc DOC document
RELEASED N68335-11-R-0020 RFP TPTI.doc DOC document
Attach 6 System Software Configuration COTS and GFP.doc DOC document
Attach 10 PBP milestones 11-24-10.xls XLS spreadsheet
Attach 1 TPTI Production SOW 7-30-10.doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

1. The purpose of this amendment is to provide technical clarification to offerors on solicitation N68335-11-R-0020 Turboprop Test Instrumentation (TPTI) system as follows:

QUESTION 1:

Attachment 10 was modified under Amendment 0002; however, the percentage in performance-based payments to be paid for CLINs 0001, 0002, and 0003 is 55%, not 90%.

ANSWER 1:

Per FAR 52.209-3 First Article Approval--Contractor Testing and 52.209-4 First Article Approval--Government Testing, before first article approval, the acquisition of materials or components for, or the commencement of production of, shall not be allocable to this contract for performance-based payments. Therefore, the milestone for materials has been removed for the Pilot Production Units, but the contractor will still be able to receive performance-based payments for Successful Factory TPTI System ATP and Successful On-Site TPTI System ATP.

QUESTION 2:

I am having problems locating a vendor for some of the components.

ANSWER 2:

All parts called out on the drawings have a CAGE Code along with the associated part number.

2. Signed amendments shall be submitted in accordance with Section L of the solicitation.

3. The solicitation closing date is not extended.

4. Contracts POC: Sarah McCarty, 732-323-4479 or sarah.mccarty@navy.mil