RELEASED 11-R-0020 AMD 0002.doc
DOC document 92 KB Posted
- Solicitation number
- N68335-11-R-0020
About this file
AMENDMENT 0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EXHIBITS A L TPTI CDRLs 3-9-11.doc | DOC document | |
| RELEASED 11-R-0020 AMD 0006.doc | DOC document | |
| RELEASED 11-R-0020 AMD 0005.doc | DOC document | |
| Attach 10 PBP milestones 2-28-11.xls | XLS spreadsheet | |
| RELEASED 11-R-0020 AMD 0003.doc | DOC document | |
| Attach 10 PBP milestones 2-17-11.xls | XLS spreadsheet | |
| RELEASED 11-R-0020 AMD 0001.doc | DOC document | |
| EXHIBITS A L TPTI CDRLs 2-10-11.doc | DOC document | |
| EXHIBITS A L TPTI CDRLs 7-30-10.doc | DOC document | |
| Attach 9 TPTI ILSSOW 10-14-10.doc | DOC document | |
| RELEASED N68335-11-R-0020 RFP TPTI.doc | DOC document | |
| Attach 6 System Software Configuration COTS and GFP.doc | DOC document | |
| Attach 10 PBP milestones 11-24-10.xls | XLS spreadsheet | |
| Attach 1 TPTI Production SOW 7-30-10.doc | DOC document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
1. The purpose of this amendment is to a) provide technical clarification to offerors on solicitation N68335-11-R-0020 Turboprop Test Instrumentation (TPTI) system and b) extend the solicitation closing date.
a. Technical clarification to offerors on solicitation N68335-11-R-0020 Turboprop Test Instrumentation (TPTI) system is hereby provided as follows:
QUESTION 1:
There are three Travel CLINS (0019, 0119 and 0221). They are for travel associated with other CLINS (0040, 0110 and 0212) respectively. Can you verify that the associated CLINS are correct?
ANSWER 1:
Travel CLIN 0049 is for travel associated with CLIN 0048; travel CLIN 0119 is for travel associated with CLIN 0118; and travel CLIN 0221 is for travel associated with CLIN 0220. Sections B and C have been revised.
QUESTION 2:
There are missing drawings from the TDP. Those are: 3654AS9762, 3654AS7999, 3654AS7905. Can you provide an update to include these drawings?
ANSWER 2:
Drawings 3654AS9762, 3654AS7999, 3654AS7905, 3654AS9709, and 3654AS900 will be mailed to all potential offerors who have been provided the technical data package.
QUESTION 3:
Can you confirm that FAR 52.209-3 First Article Approval - Contractor Testing and 52.209-4 & First Article Approval – Government Testing which both state, “…(g or h): Before first article approval, the acquisition of materials or components for, or the commencement of the costs thereof shall not be allocable to this contract for (1) performance-based payments….” found on page 95 of 135 of solicitation will be updated so that they will support the Performance-Based Payment Attachment 10 also included in the solicitation package? Attachment 10 seems to be in conflict with the inserted wording in these two FAR clauses as the Pilot Production Units (PPUs) and their corresponding CLINs do have PBP events: 35% at the order and receipt of major equipment for the TPTI in excess of $200K, 40% successful factory TPTI System ATP SOW 4.5.1, & 15% at successful on-site TPTI system ATP SOW 4.5.2.
ANSWER 3:
Attachment 10 has been updated to be consistent with FAR 52.209-3 First Article Approval - Contractor Testing and 52.209-4 First Article Approval – Government Testing. See Section J.
2. The solicitation closing date is is hereby extended from 25 February 2011 at 4:00 PM ET to 2 March 2011 at 4:00 PM ET.
3. Contracts POC: Sarah McCarty, 732-323-4479 or sarah.mccarty@navy.mil
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0049
The CLIN description has changed from Year 1 Travel for CLIN 0040 to Year 1 Travel for CLIN 0048.
CLIN 0119
The CLIN description has changed from Year 2 Travel for CLIN 0112 to Year 2 Travel for CLIN 0118.
CLIN 0221
The CLIN description has changed from Year 3 Travel for CLIN 0214 to Year 3 Travel for CLIN 0220.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
Item 0001 – Year 1 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.
Item 0002 – Year 1 – The contractor shall provide Pilot Production Unit -- Test Program Set (TPS) for T56-425/-427, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.
Item 0003 – Year 1 – The contractor shall provide Pilot Production Unit -- Test Program Set (TPS) for T56-427A, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” dated 16 December 2010.
Item 0004 – Year 1 – The contractor shall Package, Deliver, and Install the A/E37T-17A Mobile Turboprop Engine Test System for CLINs 0001, 0002, and 0003: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NAS Norfolk.
Item 0005 – Year 1 – The contractor shall provide Integrated Master Plan IAW Engineering SOW Paragraph 3.6 and Exhibit A, CDRL A001.
Item 0006 – Year 1 – The contractor shall provide Integrated Master Schedule IAW Engineering SOW Paragraph 3.7 and Exhibit A, CDRL A002.
Item 0007 – Year 1 – The contractor shall provide Program Status Reports IAW Engineering SOW Paragraph 3.8 and Exhibit A, CDRL A003.
Item 0008 – Year 1 – The contractor shall provide Meeting Agendas IAW Engineering SOW Paragraph 3.9 and Exhibit A, CDRL A004.
Item 0009 – Year 1 – The contractor shall provide Meeting Minutes IAW Engineering SOW Paragraph 3.12 and Exhibit A, CDRL A005.
Item 0010 – Year 1 – The contractor shall provide Configuration Management Plan IAW Engineering SOW Paragraph 3.18 and Exhibit A, CDRL A006.
Item 0011 – Year 1 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.
Item 0012 – Year 1 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.
Item 0013 – Year 1 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.
Item 0014 – Year 1 – The contractor shall provide Conformity Inspection Plan IAW Engineering SOW Paragraph 3.21.2.1 and Exhibit A, CDRL A010.
Item 0015 – Year 1 – The contractor shall provide Conformity Inspection Report IAW Engineering SOW Paragraph 3.21.2.2 and Exhibit A, CDRL A011.
Item 0016 – Year 1 – The contractor shall provide Technical Data Package (TDP) Updates IAW Engineering SOW Paragraph 3.23 and Exhibit A, CDRL A012.
Item 0017 – Year 1 – The contractor shall provide Quality Assurance (QA) Plan IAW Engineering SOW Paragraph 3.16 and Exhibit A, CDRL A013.
Item 0018 – Year 1 – The contractor shall provide Incident Reports / Failure Report and Corrective Action (FRACAS) IAW Engineering SOW Paragraph 3.26 and Exhibit A, CDRL A014.
Item 0019 – Year 1 – The contractor shall provide Component Data IAW Engineering SOW Paragraph 3.35 and Exhibit A, CDRL A015.
Item 0020 – Year 1 – The contractor shall provide Integration & Production Test Plan IAW Engineering SOW Paragraph 4.2 and Exhibit A, CDRL A016.
Item 0021 – Year 1 – The contractor shall provide Acceptance Test Report -- Pilot Production Unit (PPU) IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A017.
Item 0022 – Year 1 – The contractor shall provide Long Lead Items List IAW Engineering SOW Paragraph 3.32.1.13 and Exhibit A, CDRL A019.
Item 0023 – Year 1 – The contractor shall provide Hazardous Material Management Report IAW Engineering SOW Paragraph 3.29 and Exhibit A, CDRL A020.
Item 0024 – Year 1 – The contractor shall provide Item Unique Identification (IUID) Plan IAW Engineering SOW Paragraph 3.36.3 and Exhibit A, CDRL A021.
Item 0025 – Year 1 – The contractor shall provide Production Manufacturing Review IAW Engineering SOW Paragraph 3.14 and Exhibit A, CDRL A023.
Item 0026 – Year 1 – The contractor shall provide Obsolescence Management Plan IAW Engineering SOW Paragraph 3.24.1.1 and Exhibit A, CDRL A024.
Item 0027 – Year 1 – The contractor shall provide Obsolescence Reports IAW Engineering SOW Paragraph 3.24.1.2 and Exhibit A, CDRL A025.
Item 0028 – Year 1 – The contractor shall provide Trade Study IAW Engineering SOW Paragraph 3.24.1.4 and Exhibit A, CDRL A026.
Item 0029 – Year 1 – The contractor shall provide Regression Test Plan IAW Engineering SOW Paragraph 3.24.1.5 and Exhibit A, CDRL A027.
Item 0030 – Year 1 – The contractor shall provide Vendor Data IAW Integrated Logistics Support (ILS) SOW Paragraph 1.1.3.3.2 and Exhibit L, CDRL L001.
Item 0031 – Year 1 – The contractor shall provide Meeting Agenda, ILSMT IAW ILSSOW Paragraph 1.1.3.4.2.d and Exhibit L, CDRL L002.
Item 0032 – Year 1 – The contractor shall provide Meeting Minutes, ILSMT IAW ILSSOW Paragraph 1.1.3.4.2.f and Exhibit L, CDRL L003.
Item 0033 – Year 1 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.
Item 0034 – Year 1 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.
Item 0035 – Year 1 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.
Item 0036 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0034 and 0035: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0037 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0038 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0039 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0040 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0041 – Year 1 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0042 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0043 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0044 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0045 – Year 1 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0046 – Year 1 – The contractor shall provide Acceptance Test Report--Production Units IAW Engineering SOW Paragraph 4.6.4 and Exhibit A, CDRL A018.
Item 0047 – Year 1 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0048 – Year 1 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0049 – Year 1 – The contractor shall provide Travel for CLIN 0048 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.
Item 0050 – Year 1 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.
Item 0100 – Year 2 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.
Item 0101 – Year 2 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.
Item 0102 – Year 2 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.
Item 0103 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0101 and 0102: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0104 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0105 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0106 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0107 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0108 – Year 2 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0109 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0110 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0111 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0112 – Year 2 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0113 – Year 2 – The contractor shall provide Acceptance Test Report--Production Units IAW Engineering SOW Paragraph 4.6.4 and Exhibit A, CDRL A018.
Item 0114 – Year 2 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.
Item 0115 – Year 2 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.
Item 0116 – Year 2 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.
Item 0117 – Year 2 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0118 – Year 2 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0119 – Year 2 – The contractor shall provide Travel for CLIN 0118 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.
Item 0120 – Year 2 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.
Item 0121 – Year 2 – The contractor shall provide T-19A site survey and functional/requirements analysis IAW Para 3.32.1.3 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0122 – Year 2 – The contractor shall provide T-19A Facility Design IAW Engineering SOW Paragraph 3.32.1.3 and Exhibit A, CDRL A028.
Item 0237 – Year 2 – The contractor shall provide T-19A Installation Control drawings (ICD) IAW Engineering SOW Paragraph 3.32.1.4 and Exhibit A, CDRL A029.
Item 0124 – Year 2 – The contractor shall provide T-19A Installation Hardware Kit Drawing IAW Engineering SOW Paragraph 3.32.1.6 and Exhibit A, CDRL A030.
Item 0125 – Year 2 – The contractor shall provide Engineering Drawing Package T-19A IAW Engineering SOW Paragraph 3.32.1.7.2 and Exhibit A, CDRL A031.
Item 0126 – Year 2 – The contractor shall provide T-19A Technical Reviews IAW Engineering SOW Paragraph 3.32.1.8 and Exhibit A, CDRL A032.
Item 0127 – Year 2 – The contractor shall provide Update Maintenance Plan Data IAW ILSSOW Paragraph 1.1.4.1.5 and Exhibit L, CDRL L004.
Item 0128 – Year 2 – The contractor shall provide Technical Manual Change Data IAW ILSSOW Paragraph 1.1.5.1 and Exhibit L, CDRL L005.
Item 0129 – Year 2 – The contractor shall provide Contractor Support (ILS) IAW Attachment 9, "Integrated Logistics Support Statement of Work," dated 14 October 2010.
Item 0200 – Year 3 – The contractor shall provide Mobile Turboprop Engine Test System, Part Number 3654AS7400-1, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 2, "TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series," dated 16 December 2010.
Item 0201 – Year 3 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-425,-427 Turboprop Engine, Part Number 3654AS7500-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 7, "T56-A-425/427 Technical Data Package (TDP) 3654AS7500 Series," dated 16 December 2010.
Item 0202 – Year 3 – The contractor shall provide Production Unit -- Test Program Set (TPS) for T56-427A Turboprop Engine, Part Number 3654AS8800-1, IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010; and Attachment 8, “T56-A-427A TDP 3654AS8800 Series,” 16 December 2010.
Item 0203 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system and TPSs from CLINs 0201 and 0202: unite with required TPSs, connect to engine and ancillary equipment, calibrate and provide Navy acceptance testing at/for/to: NWS Pt Mugu, CA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0204 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0205 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Jacksonville, FL. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0206 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Whidbey Island, WA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0207 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: JRB Fort Worth, TX. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0208 – Year 3 – The contractor shall provide Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS Patuxent River, MD. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0209 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MALS-49 Stewart AFB, Newburgh, NY. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0210 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: MCAS Kaneohe Bay, HI. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0211 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: NAS JRB New Orleans, LA. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0212 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-17A Mobile Turboprop Engine Test System for 1 TPTI system: provide Navy acceptance testing at/for/to: Taiwan. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0213 – Year 3 – The contractor shall provide Fixed Turboprop Engine Test System, Part Number 3654AS7300-2, in accordance with (IAW) Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0214 – Year 3 – The contractor shall Package, Deliver, and Install A/E37T-19A Fixed Turboprop Engine Test System for 1 unit under CLIN 0205: provide Navy acceptance testing at/for/to: NAS Misawa, Japan. The TPS for the TPTI production unit under CLIN 0205 is not a part of this contract. IAW Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0215 – Year 3 – The contractor shall provide Acceptance Test Report -- Production Unit IAW Engineering SOW Paragraph 4.4 and Exhibit A, CDRL A018.
Item 0216 – Year 3 – The contractor shall provide Engineering Change Proposal (ECP) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A007.
Item 0217 – Year 3 – The contractor shall provide Notice of Revision (NOR) IAW Engineering SOW Paragraph 3.20 and Exhibit A, CDRL A008.
Item 0218 – Year 3 – The contractor shall provide Request for Deviation (RFD) IAW Engineering SOW Paragraph 3.21.1 and Exhibit A, CDRL A009.
Item 0219 – Year 3 – The contractor shall provide Engineering Support Services IAW Paragraph 3.39 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0220 – Year 3 – The contractor shall provide Technical Rep Support Services Technical Representative Support Services IAW Paragraph 3.38 of Attachment 1, "Engineering Statement of Work for the Production of the Turboprop Engine Test Instrumentation (TPTI) System," dated 30 July 2010.
Item 0221 – Year 3 – The contractor shall provide Travel for CLIN 0220 "Not to Exceed $25,000" Request for travel and billing against this CLIN shall be submitted to the Navy for approval before travel commences and shall be invoiced individually for each approved travel.
Item 0222 – Year 3 – The contractor shall provide Technical Support Report IAW Engineering SOW Paragraph 3.38 and Exhibit A, CDRL A033.
Item 0223 – Year 3 – The contractor shall provide Contractor Support (ILS) IAW Attachment 9, "Integrated Logistics Support Statement of Work," dated 14 October 2010.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Exhibit A |
| Exhibit A, DD Form 1423, CDRLs |
| 32 |
| 30-JUL-2010 |
| Exhibit L |
| Exhibit L, DD Form 1423, CDRLs |
| 5 |
| 10-FEB-2011 |
| Attachment 1 |
| Engineering Statement of Work |
| 38 |
| 30-JUL-2010 |
| Attachment 10 |
| Performance Based Payments Milestones |
| 2 |
| 24-NOV-2010 |
| Attachment 2 |
| TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series |
16-DEC-2010
| Attachment 3 |
| TPTI System Acceptance Test Procedure |
16-DEC-2010
| Attachment 4 |
| T56-A-425/427 TPS Acceptance Test Procedure |
16-DEC-2010
| Attachment 5 |
| T56-A-427A TPS Acceptance Test Procedure |
16-DEC-2010
| Attachment 6 |
| System Software Configuration – COTS and GFP |
16-DEC-2010
| Attachment 7 |
| T56-A-425/427 TDP 3654AS7500 Series |
16-DEC-2010
| Attachment 8 |
| T56-A-427A TDP 3654AS8800 Series |
16-DEC-2010
| Attachment 9 |
| Integrated Logistics Support Statement of Work |
| 4 |
| 14-OCT-2010 |
to:
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Exhibit A |
| Exhibit A, DD Form 1423, CDRLs |
| 32 |
| 30-JUL-2010 |
| Exhibit L |
| Exhibit L, DD Form 1423, CDRLs |
| 5 |
| 10-FEB-2011 |
| Attachment 1 |
| Engineering Statement of Work |
| 38 |
| 30-JUL-2010 |
| Attachment 10 |
| Performance Based Payments Milestones |
| 2 |
| 17-FEB-2011 |
| Attachment 2 |
| TPTI Technical Data Package (TDP), T-17A 3654AS7400 Series |
16-DEC-2010
| Attachment 3 |
| TPTI System Acceptance Test Procedure |
16-DEC-2010
| Attachment 4 |
| T56-A-425/427 TPS Acceptance Test Procedure |
16-DEC-2010
| Attachment 5 |
| T56-A-427A TPS Acceptance Test Procedure |
16-DEC-2010
| Attachment 6 |
| System Software Configuration – COTS and GFP |
16-DEC-2010
| Attachment 7 |
| T56-A-425/427 TDP 3654AS7500 Series |
16-DEC-2010
| Attachment 8 |
| T56-A-427A TDP 3654AS8800 Series |
16-DEC-2010
| Attachment 9 |
| Integrated Logistics Support Statement of Work |
| 4 |
| 14-OCT-2010 |
File details come from the government source that posted it. Updated .