This is a labor rates and costs attachment supporting an unloaded labor rate proposal for a federal contract opportunity. The document outlines staffing requirements and associated labor hours across multiple contract periods for engineering and production control support services at two primary locations: Bahrain and Rota. The solicitation is issued under the SeaPort NxG contract vehicle by the Department of the Navy Naval Supply Systems Command for FDRMC Engineering Support Services (Solicitation N6817126RN005), structured as a Cost Plus Fixed Fee task order limited to active SeaPort contract holders.
The labor categories specified include Engineering Technicians (Mechanical Auxiliary, Mechanical Hydraulics, and Marine Gas Turbine Inspector), Production Controllers (D-level planner, IMA Planner, and Dive Planner), Technicians (METCAL Program), and Combat System Technicians (CANES/Afloat Network and SPY Technician). The base period requires 14,784 total labor hours, while Option Periods 1 and 2 each require 14,784 hours. Option Periods 3 and 4 each increase to 19,008 hours, and a six-month extension option specifies 9,504 hours. The document provides columns for unloaded labor rates, costs, and notes on the basis of salary compensation (referencing current employees, salary surveys, or subcontractor rates), though specific rate values are not populated in this template version. This amendment (Amendment 01) updates the proposal to reflect revised scope, labor requirements, and extended solicitation closing dates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2.00a Attachment 01 Past Performance Information - Amendment 01.doc | DOC document | |
| QandA.pdf | ||
| 26RN005 Schedule B - Amendment 01.xlsx | XLSX spreadsheet | |
| 2.00d Attachment 04 Calculation of Indirect Costs - Amendment 01.xlsx | XLSX spreadsheet | |
| Solicitation Amendment N6817126RN0050001 SF 30.pdf | ||
| Attachment 01 Past Performance Information.doc | DOC document | |
| Attachment 02 Past Performance Questionnaire.docx | DOCX document | |
| Attachment 04 Calculation of Indirect Costs.xlsx | XLSX spreadsheet | |
| Attachment 09 CDRL_A0003_ODC REPORT.pdf | ||
| Attachment 05 Support for Unloaded Labor Rates and Costs.xlsx | XLSX spreadsheet | |
| Attachment 10 CDRL_A0004_TRIP REPORT.pdf | ||
| Attachment 07 CDRL_A0001_CO MGMT REPORT.pdf | ||
| Attachment 08 CDRL_A0002_ROSTER.pdf | ||
| Attachment 03 DD Form 254_ENG.pdf | ||
| Solicitation - N6817126RN005.pdf | ||
| Attachment 06 QUALITY ASSURANCE SURVEILLANCE PLAN.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Period
| Base | Base | |||||
| Period | Period | |||||
| Unloaded | Unloaded | |||||
| SOW | Labor | Labor | ||||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Costs | Notes on Basis of Salary such as current employee, salary survey, subcontractor, labor category rates etc. |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 2112 | |||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 2112 | |||
| 3.2.1 | Bahrain | Production Controller - D level planner | ||||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | ||||
| 3.2.3 | Rota | Production Controller - Dive Planner | 2112 | |||
| 3.1.6 | Rota | Technician - METCAL Program | 2112 | |||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 2112 | |||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 2112 | |||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 2112 | |||
| Hours | 14784 |
Option Period 1
| Base | Base | |||||
| Period | Period | |||||
| Unloaded | Unloaded | |||||
| SOW | Labor | Labor | ||||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Costs | Notes on Basis of Salary such as current employee, salary survey, subcontractor, labor category rates etc. |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 2112 | |||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 2112 | |||
| 3.2.1 | Bahrain | Production Controller - D level planner | ||||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | ||||
| 3.2.3 | Rota | Production Controller - Dive Planner | 2112 | |||
| 3.1.6 | Rota | Technician - METCAL Program | 2112 | |||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 2112 | |||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 2112 | |||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 2112 | |||
| Hours | 14784 |
Option Period 2
| Base | Base | |||||
| Period | Period | |||||
| Unloaded | Unloaded | |||||
| SOW | Labor | Labor | ||||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Costs | Notes on Basis of Salary such as current employee, salary survey, subcontractor, labor category rates etc. |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 2112 | |||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 2112 | |||
| 3.2.1 | Bahrain | Production Controller - D level planner | 2112 | |||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | 2112 | |||
| 3.2.3 | Rota | Production Controller - Dive Planner | 2112 | |||
| 3.1.6 | Rota | Technician - METCAL Program | 2112 | |||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 2112 | |||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 2112 | |||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 2112 | |||
| Hours | 19008 |
Option Period 3
| Base | Base | |||||
| Period | Period | |||||
| Unloaded | Unloaded | |||||
| SOW | Labor | Labor | ||||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Costs | Notes on Basis of Salary such as current employee, salary survey, subcontractor, labor category rates etc. |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 2112 | |||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 2112 | |||
| 3.2.1 | Bahrain | Production Controller - D level planner | 2112 | |||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | 2112 | |||
| 3.2.3 | Rota | Production Controller - Dive Planner | 2112 | |||
| 3.1.6 | Rota | Technician - METCAL Program | 2112 | |||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 2112 | |||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 2112 | |||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 2112 | |||
| Hours | 19008 |
Option Period 4
| Base | Base | |||||
| Period | Period | |||||
| Unloaded | Unloaded | |||||
| SOW | Labor | Labor | ||||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Costs | Notes on Basis of Salary such as current employee, salary survey, subcontractor, labor category rates etc. |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 2112 | |||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 2112 | |||
| 3.2.1 | Bahrain | Production Controller - D level planner | 2112 | |||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | 2112 | |||
| 3.2.3 | Rota | Production Controller - Dive Planner | 2112 | |||
| 3.1.6 | Rota | Technician - METCAL Program | 2112 | |||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 2112 | |||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 2112 | |||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 2112 | |||
| Hours | 19008 |
-8 Extension
| Option | Six | Six | |||||
| Year | Month | Month | |||||
| Four | EXT | EXT | |||||
| SOW | Unloaded | Escalation | Unloaded | Labor | |||
| PWS | Location | Labor Category Description per PWS | Hours | Rate | Percent | Rate | Costs |
| 3.1.5.1 | Bahrain | Engineering Technician - Mechanical Auxiliary | 1056 | ||||
| 3.1.5.2 | Bahrain | Engineering Technician - Mechanical Hydraulics | 1056 | ||||
| 3.2.1 | Bahrain | Production Controller - D level planner | 1056 | ||||
| 3.2.2 | Bahrain | Production Controller - IMA Planner | 1056 | ||||
| 3.2.3 | Rota | Production Controller - Dive Planner | 1056 | ||||
| 3.1.6 | Rota | Technician - METCAL Program | 1056 | ||||
| 3.1.5.3 | Rota | Engineering Technician - Marine Gas Turbine Inspector | 1056 | ||||
| 3.1.5.5 | Rota | Combat System Technician - CANES/Afloat Network | 1056 | ||||
| 3.1.5.4 | Rota | Combat System Technician - SPY Technician | 1056 | ||||
| Hours | 9504 |