24R1328 Note7-Issued.pdf

PDF 355 KB Posted

Attached to
INDO-PACIFIC MULTIPLE AWARD CONSTRUCTION CONTRACT FOR PROJECTS IN THE NAVFAC PACIFIC AREA OF OPERATIONS
Solicitation number
N62742-24-R-1328
Issued by

About this file

This document is a Notice containing questions and answers related to Request for Proposal (RFP) N62742-24-R-1328 for an Indo-Pacific Multiple Award Construction Contract (MACC) for projects in the NAVFAC Pacific area of operations.

The RFP is for construction services to support the Pacific Deterrence Initiative program with the Exercise Related Construction (ERC), Unspecified Minor Military Construction (UMMC), US Code Title 10 Security Cooperation and other repair projects. Key details include: the contract will be an Indefinite Delivery, Indefinite Quantity (IDIQ) type MACC; it may include projects in various Asia-Pacific countries; contractors will be expected to perform a wide variety of construction tasks; and the selected contractors will be responsible for all labor, engineering, materials, and transportation. The Notice provides responses to 6 questions related to fire alarm systems, LAN outlets, electrical service, window requirements, and toilet compartments. The responses clarify or provide additional details on the RFP requirements.

View the file

Other files

File Type Posted
24R1328 Note11-Issued.pdf PDF
24R1328 Note10-Issued.pdf PDF
24R1328 Note9.pdf PDF
24R1328-Amd08-Issued.pdf PDF
24R1328-Amd07-Issued.pdf PDF
24R1328 Note8-Issued.pdf PDF
IMACC Seed PPSV Sign-In.pdf PDF
24R1328-Amd06-Issued.pdf PDF
24R1328-Amd05-Issued.pdf PDF
24R1328-AMD4.pdf PDF
24R1328 Note6.pdf PDF
24R1328 Note5.pdf PDF
24R1328 Note4.pdf PDF
24R1328-AMD3.pdf PDF
24R1328 Note3.pdf PDF
24R1328-AMD2.pdf PDF
24R1328 Note2.pdf PDF
24R1328-AMD1.pdf PDF
24R1328 Note1-Issued.pdf PDF
RFPN6274224R1328 IMACC.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC

258 MAKALAPA DR STE 100

PEARL HARBOR HI 96860-3134

RFP N62742-24-R-1328

Notice No. 7

8 Aug 2024

PRE-PROPOSAL QUESTIONS & ANSWERS

INDO-PACIFIC MULTIPLE AWARD CONSTRUCTION CONTRACT FOR PROJECTS IN

THE NAVFAC PACIFIC AREA OF OPERATIONS

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

64. In reference to Part 3, Page 14 of 16, D40 states “Comply with all applicable requirements of UFC 1-201-01, Non-Permanent DoD Facilities in Support of Military Operations for fire alarm, detection, and notification.

- Please confirm that the KTR has to consider radio frequency type antenna system for Fire Alarm system or not

ANSWER: Fire alarm radio transmitter and antenna are not required as there’s no central receiver on base (CMDC). Fire alarm system is required for in-building notification only.

65. In reference to Part 3, Page 14 of 16, 4.2 Building Requirements #8 - Provide duplex electrical power outlets (220V) and LAN line wall outlets every 1.20 meter in the large open bay area and conference room.

- Please clarify how the building will get FO/Copper Cable Connection from local authority or KTR has to do the provision for LAN outlets from Server Room.

ANSWER: Contractor has to do the provision for LAN outlets from Server Room.

66. In reference to Part 3, Page 14 of 16, 4.2 Building Requirements #18 - Building shall be connected to local electrical service (e.g. ISELCO II) and shall be metered. Contractor shall provide additional new transformers as necessary.

- Please provide the available distribution line voltage on the existing distribution pole.

ANSWER: Contractor shall coordinate directly with ISELCO II to get the needed information.

67. In reference to Part 4, Page 5 of 21, B2020 EXTERIOR WINDOWS, states “a. Provide insulating laminated glass with a minimum 0.75mm interlayer (plastic polyvinyl butyral sheet) between glass sheets. Aluminum Sliding Windows, using E-Series Sections (Imported) Heavy Duty, Powder Coated Finish, equipped with Double Roller, Flush Lock, Channel Glazing Vinyl, Anti-Bumper, Complete Accessories, Glazed with 18 mm IGU Glass Annealed Bronze (6.0 mm Glass + 6.0 mm Air Space + 6.0 mm Glass). Incorporated with Dow Corning Silicone Sealant.”

However, Part 4, Page 5 of 21, B2020 EXTERIOR WINDOWS states, “c. Overall thickness of glass shall be a minimum of 50mm (½”) thick.

- Please confirm the exact thickness of window glass.

ANSWER: Designer-of-Record shall determine the glass thickness, but not less than the minimum required thickness mentioned in the RFP documents.

68. In reference to Part 3, page 11 of 16, C1030 SPECIALTIES states “Compartments - Toilet and shower partitions shall be reinforced concrete with floor and wall tiles spanning from floor up to 1.80 m. high. However, in Part 6, page 11 of 23, FIGURE 10: SAMPLE of ACCEPTABLE MATERIALS shows toilet compartments in phenolic board.

- Please confirm if compartments shall be reinforced concrete or phenolic board.

ANSWER: Toilet compartments in phenolic board, as shown in Part 6, is acceptable. See

Amendment No. 0005.

69. In reference to Part 6, Figure 8 – Conceptual Floor Plans it includes the Doors and Windows Legend. However, the Doors and Windows schedule is missing from the RFP package.

- Please provide the Doors and Windows schedule.

ANSWER: Designer-of-Record shall determine appropriate doors and windows meeting the minimum contract requirements and shall provide doors and windows schedule.