About this file

This document is Amendment No. 0007 to a Request for Proposal (RFP) for an Indefinite Delivery, Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) to support the Pacific Deterrence Initiative program with Exercise Related Construction (ERC), Unspecified Minor Military Construction (UMMC), US Code Title 10 Security Cooperation, and other repair projects in the Naval Facilities Engineering Command (NAVFAC) Pacific area of operations. The MACC will encompass a wide range of design-build projects that may include new facilities, repair/renovation, and upgrades to various facility types produced in accordance with nationally recognized industry, international, federal, and/or military standards. The contract has a maximum 8-year term and $990,000,000 aggregate ceiling value. Task orders will typically range from $500,000 to $20,000,000 and be competed among the MACC awardees. The amendment revises contract clauses, updates building requirements, and modifies attachments.

View the file

Other files

File Type Posted
24R1328 Note11-Issued.pdf PDF
24R1328 Note10-Issued.pdf PDF
24R1328 Note9.pdf PDF
24R1328-Amd08-Issued.pdf PDF
24R1328 Note8-Issued.pdf PDF
IMACC Seed PPSV Sign-In.pdf PDF
24R1328-Amd06-Issued.pdf PDF
24R1328 Note7-Issued.pdf PDF
24R1328-Amd05-Issued.pdf PDF
24R1328-AMD4.pdf PDF
24R1328 Note6.pdf PDF
24R1328 Note5.pdf PDF
24R1328 Note4.pdf PDF
24R1328-AMD3.pdf PDF
24R1328 Note3.pdf PDF
24R1328-AMD2.pdf PDF
24R1328 Note2.pdf PDF
24R1328-AMD1.pdf PDF
24R1328 Note1-Issued.pdf PDF
RFPN6274224R1328 IMACC.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

24RXXXX

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REQUEST FOR PROPOSAL N62742-24-R-1328, INDO-PACIFIC MULTIPLE AWARD CONSTRUCTION CONTRACT FOR PROJECTS IN THE

NAVFAC PACIFIC AREA OF OPERATIONS

The proposal due date remains unchanged.

Continued on page 2.

See page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6274224R1328

X 9B. DATED (SEE ITEM 11)

06-Jun-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Aug-2024

CODE

NAVFAC PACIFIC

CONSTR CONTRACTS BRANCH (CODE ACQ33)

258 MAKALAPA DR STE 100

JBPHH HI 96860-3134

N62742 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6274224R1328

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

PART 1 – PROPOSAL FORMS AND DOCUMENTS

DOCUMENT 00 70 00 NEGOTIATED CONTRACT CLAUSES

Delete Document 00 70 00, NEGOTIATED CONTRACT CLAUSES, in its entirety and replace with the attached Document 00 70 00, NEGOTIATED CONTRACT CLAUSES.

DOCUMENT 00 73 00 SUPPLEMENTARY CONDITIONS

Delete Document 00 73 00, SUPPLEMENTARY CONDITIONS, in its entirety and replace with the attached Document 00 73 00, SUPPLEMENTARY CONDITIONS.

PART 7, SEED PROJECT

PART 3, STATEMENT OF WORK

4. PROJECT REQUIREMENTS

4.2 Building Requirements

Delete “16. Provide a concrete apron/walkway around the building.” and insert “16. Provide a 1.0m wide concrete walkway around the building with a 1.5m (minimum) roof overhang.”

PART 6, ATTACHMENTS

Delete “Part 6 - Page 1 of 23” and replace with the attached “Part 6 – Page 1 of 24”.

Delete “of 23” on all page numbers and replace with “of 24”.

Insert “FIGURE 12: EXAMPLE PROJECT PLAQUE, Part 6 – Page 24 of 24” at the end of Part 6, Attachments.

--End of Amendment--

INDO-PACIFIC MULTIPLE AWARD CONSTRUCTION CONTRACT FOR PROJECTS IN THE NAVFAC

PACIFIC AREA OF OPERATIONS

RFP N62742-24-R-1328

Amendment No. 0007

DOCUMENT 00 70 00 (ADVERTISE)

DOCUMENT 00 70 00

NEGOTIATED

CONTRACT CLAUSES

6/24

1.1 FAR 52.252-2, CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

FAR: https://www.acquisition.gov/browse/index/far DFARS: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html

1.2 FAR 52.202-1, DEFINITIONS (JUN 2020)

1.3 FAR 52.203-3, GRATUITIES (APR 1984)

1.4 FAR 52.203-5, COVENANT AGAINST CONTINGENT FEES (MAY 2014)

1.5 FAR 52.203-6, RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)

1.6 FAR 52.203-7, ANTI-KICKBACK PROCEDURES (JUN 2020)

1.7 FAR 52.203-8, CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR

IMPROPER ACTIVITY (MAY 2014)

1.8 FAR 52.203-10, PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY

2014)

1.9 FAR 52.203-12, LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL

TRANSACTIONS (JUN 2020)

1.10 FAR 52.203-13, CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (NOV 2021)

1.11 FAR 52.203-17, CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)

1.12 FAR 52.203-19, PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY

AGREEMENTS OR STATEMENTS (JAN 2017)

1.13 FAR 52.204-2, SECURITY REQUIREMENTS (MAR 2021) ALTERNATE II (APR 1984)

1.14 FAR 52.204-4, PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT

PAPER (MAY 2011)

1.15 FAR 52.204-9, PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

1.16 FAR 52.204-10, REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT

AWARDS (JUN 2020)

1.17 FAR 52.204-13, SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)

1.18 FAR 52.204-18, COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)

(a) Definition. As used in this clause–

Commercial and Government Entity (CAGE) code means–

(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or

(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.

DOCUMENT 00 70 00 (ADVERTISE)

(b) Contractors shall ensure that the CAGE code is maintained throughout the life of the contract for each location of contract, including subcontract, performance. For contractors registered in the System for Award Management (SAM), the DLA Commercial and Government Entity (CAGE) Branch shall only modify data received from SAM in the CAGE master file if the contractor initiates those changes via update of its SAM registration. Contractors undergoing a novation or change-of-name agreement shall notify the contracting officer in accordance with subpart

42.12. The contractor shall communicate any change to the CAGE code to the contracting officer within 30 days after the change, so that a modification can be issued to update the CAGE code on the contract.

(c) Contractors located in the United States or its outlying areas that are not registered in SAM shall submit written change requests to the DLA Commercial and Government Entity (CAGE) Branch. Requests for changes shall be provided at https://cage.dla.mil. Change requests to the CAGE master file are accepted from the entity identified by the code.

(d) Contractors located outside the United States and its outlying areas that are not registered in SAM shall contact the appropriate National Codification Bureau (points of contact available at http://www.nato.int/structur/AC/135/main/links/contacts.htm) or NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx to request CAGE changes.

(e) Additional guidance for maintaining CAGE codes is available at https://cage.dla.mil.

(f) If the contract includes Federal Acquisition Regulation clause 52.204-2, Security Requirements, the contractor shall ensure that subcontractors maintain their CAGE code(s) throughout the life of the contract.

1.19 FAR 52.204-19, INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

The Contractor’s representations and certification, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

1.20 FAR 52.204-21, BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS

(NOV 2021)

(a) Definitions. As used in this clause—

Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on

National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

DOCUMENT 00 70 00 (ADVERTISE)

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

DOCUMENT 00 70 00 (ADVERTISE)

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by

Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

1.21 FAR 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND

SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)

1.22 FAR 52.204-25, PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND

VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

1.23 FAR 52.204-27, PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUN 2023)

1.24 FAR 52.204-30, FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS-

PROHIBITION (DEC 2023)

1.25 FAR 52.209-6, PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (NOV 2021)

1.26 FAR 52.209-9, UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING

RESPONSIBILITY MATTERS (OCT 2018)

1.27 FAR 52.209-10, PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS (NOV 2015)

1.28 FAR 52.210-1, MARKET RESEARCH (NOV 2021)

1.29 FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)*

The Contractor shall be required to

(a) Commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed,

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than [to be completed in each task order calendar days after notice to proceed.

The time stated for completion shall include final cleanup of the premises.

A "Notice to Proceed" is deemed to be given by the Government to the Contractor 21 calendar days after the contract award date. No formal written notice will be issued by the Government. Within 21 calendar days following the contract award date, the Contractor is obligated to submit performance and payment bonds in a form acceptable to the Government. The Government shall notify the Contractor of the acceptability of the performance and payment bonds within 5 working days of receipt of these documents. If these documents are not submitted in their proper form acceptable to the Government within 21 calendar days of contract award, any delays resulting thereby will be at the sole expense of the Contractor. The contract completion date will not be extended due to the Government's review of the acceptability of the Contractor's bonds, except where the Government's review of said documents extends beyond 5 working days.

DOCUMENT 00 70 00 (ADVERTISE)

1.30 FAR 52.211-12, LIQUIDATED DAMAGES—CONSTRUCTION (SEP 2000)*

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of [to be completed in each task order] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.31 FAR 52.211-13, TIME EXTENSIONS (SEP 2000)

1.32 FAR 52.211-15, DEFENSE PRIORITY AND ALLOCATION REQUIREMENTS (APR 2008)

1.33 FAR 52.211-18, VARIATION IN ESTIMATED QUANTITY (APR 1984)

1.34 FAR 52.215-2, AUDIT AND RECORDS--NEGOTIATION (JUN 2020)

1.35 FAR 52.215-10, PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA (AUG 2011)

1.36 FAR 52.215-11, PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA--

MODIFICATIONS (DEVIATION 2022-O0001) (OCT 2021)

1.37 FAR 52.215-12, SUBCONTRACTOR CERTIFIED COST OR PRICING DATA (DEVIATION 2022-

O0001) (OCT 2021)

1.38 FAR 52.215-13, SUBCONTRACTOR CERTIFIED COST OR PRICING DATA--MODIFICATIONS

(DEVIATION 2022-O0001) (OCT 2021)

(a) The requirements of paragraphs (b) and (c) of this clause shall—

(1) Become operative only for any modification to this contract involving a pricing adjustment expected to exceed $2 million on the date of execution of the modification; and

(2) Be limited to such modifications.

(b) Before awarding any subcontract expected to exceed $2 million on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed $2 million, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies.

If the $2 million threshold for submission of certified cost or pricing data is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.

(c) The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (b) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.

(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that exceeds $2 million on the date of agreement on price or the date of award, whichever is later.

1.39 FAR 52.215-15, PENSION ADJUSTMENTS AND ASSET REVERSIONS (OCT 2010)

1.40 FAR 52.215-18, REVERSION OR ADJUSTMENT OF PLANS FOR POSTRETIREMENT BENEFITS

(PRB) OTHER THAN PENSIONS (JUL 2005)

1.41 FAR 52.215-19, NOTIFICATION OF OWNERSHIP CHANGES (OCT 1997)

DOCUMENT 00 70 00 (ADVERTISE)

1.42 FAR 52.215-21, REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER

THAN CERTIFIED COST OR PRICING DATA—MODIFICATIONS (NOV 2021)

1.43 FAR 52.215-23, LIMITATIONS ON PASS THROUGH CHARGES (JUN 2020)

1.44 FAR 52.216-18 ORDERING (AUG 2020)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from contract award through a maximum of eight years if all option periods are exercised (five-year base period plus three one-year option periods).

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) A delivery order or task order is considered “issued” when—

(1) If sent by mail (includes transmittal by U.S. mail or private delivery service), the Government deposits the order in the mail;

(2) If sent by fax, the Government transmits the order to the Contractor's fax number; or

(3) If sent electronically, the Government either—

(i) Posts a copy of the delivery order or task order to a Government document access system, and notice is sent to the Contractor; or

(ii) Distributes the delivery order or task order via email to the Contractor's email address.

d) Orders may be issued by methods other than those enumerated in this clause only if authorized in the contract.

1.45 FAR 52.216-19 ORDER LIMITATIONS (OCT 1995)

a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $500,000, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor --

(1) Any order for a single item in excess of $20,000,000;

(2) Any order for a combination of items in excess of $990,000,000; or

(3) A series of orders from the same ordering office within 0 days that together call for quantities exceeding the limitation in subparagraph (b)(1) or (2) of this section.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.

(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 30 days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

1.46 FAR 52.216-22 INDEFINITE QUANTITY (OCT 1995)

DOCUMENT 00 70 00 (ADVERTISE)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after the completion of all task orders.

1.47 FAR 52.216–32 TASK-ORDER AND DELIVERY-ORDER OMBUDSMAN (SEP 2019)

(a) In accordance with 41 U.S.C. 4106(g), the Agency has designated the following task-order and delivery-order Ombudsman for this contract. The Ombudsman must review complaints from the Contractor concerning all task-order and delivery-order actions for this contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract.

The Navy task and delivery order ombudsman is Ms. Cindy Shaver, Deputy Assistant Secretary of the Navy (Procurement), 1000 Navy Pentagon, Washington, DC 20350, phone (703) 614-9600, fax (703) 614-9394, and email NCAG@navy.mil.

(b) Consulting an ombudsman does not alter or postpone the timeline for any other process (e.g., protests).

(c) Before consulting with the Ombudsman, the Contractor is encouraged to first address complaints with the Contracting Officer for resolution. When requested by the Contractor, the Ombudsman may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.

1.48 FAR 52.217-7, OPTION FOR INCREASED QUANTITY-SEPARATELY PRICED LINE ITEM (MAR

1989) [will be included in task orders, as applicable.]

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within [insert in the clause the period of time in which the Contracting Officer has to exercise the option]. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

1.49 FAR 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor prior to the contract expiration date; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 calendar days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

DOCUMENT 00 70 00 (ADVERTISE)

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 96 months.

1.50 FAR 52.222-1, NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)

1.51 FAR 52.222-14, DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

1.52 FAR 52.222-15, CERTIFICATION OF ELIGIBILITY (MAY 2014)

1.53 FAR 52.222-21, PROHIBITION OF SEGREGATED FACILITIES (APR 2015)

1.54 FAR 52.222-26, EQUAL OPPORTUNITY (SEP 2016)

1.55 FAR 52.222-27, AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION

(APR 2015)

1.56 FAR 52.222-29, NOTIFICATION OF VISA DENIAL (APR 2015)

1.57 FAR 52.222-35, EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)

1.58 FAR 52.222-36, EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)

1.59 FAR 52.222-37, EMPLOYMENT REPORTS ON VETERANS (JUN 2020)

1.60 FAR 52.222-50, COMBATING TRAFFICKING IN PERSON (NOV 2021)

1.61 FAR 52.223-2, REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION

CONTRACTS (MAY 2024)*

1.62 FAR 52.223-3, HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (FEB

2021)

1.63 FAR 52.223-5, POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2024)

1.64 FAR 52.223-9, ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-

DESIGNATED ITEMS (MAY 2008)

1.64 FAR 52.223-20, AEROSOLS (JUN 2016)

1.65 FAR 52.223-21, FOAMS (MAY 2024)

1.66 FAR 52.224-1, PRIVACY ACT NOTIFICATION (APR 1984)

1.67 FAR 52.224-2, PRIVACY ACT (APR 1984)

1.68 FAR 52.225-13, RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)

1.69 FAR 52.225-14, INCONSISTENCY BETWEEN ENGLISH VERSION AND TRANSLATION OF

CONTRACT (FEB 2000)

1.70 FAR 52.225-19, CONTRACTOR PERSONNEL IN A DESIGNATED OPERATIONAL AREA OR

SUPPORTING A DIPLOMATIC OR CONSULAR MISSION OUTSIDE THE UNITED STATES (MAY

2020)

1.71 FAR 52.227-4, PATENT INDEMNITY -- CONSTRUCTION CONTRACTS (DEC 2007)

1.72 FAR 52.228-1, BID GUARANTEE (SEP 1996) [if required by task order]

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds,

(1) to unsuccessful bidders as soon as practicable after the opening of bids, and

(2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 21 days after award of the contract, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

1.73 FAR 52.228-2, ADDITIONAL BOND SECURITY (OCT 1997) [if required by task order]

1.74 FAR 52.228-3, WORKERS’ COMPENSATION INSURANCE (DEFENSE BASE ACT) (JUL 2014)

1.75 FAR 52.228-4, WORKER’S COMPENSATION AND WAR HAZARD INSURANCE OVERSEAS (APR

1984)

1.76 FAR 52.228-5, INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)*

1.77 FAR 52.228-11, INDIVIDUAL SURETY—PLEDGE OF ASSETS (FEB 2021)

1.78 FAR 52.228-12, PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022)

1.79 FAR 52.228-14, IRREVOCABLE LETTER OF CREDIT (NOV 2014)*

1.80 FAR 52.228-15, PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (JUN 2020)

(DEVIATION 2020-O0016) [if required by task order]

(a) Definitions. As used in this clause-

Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance bonds (Standard Form 25, except that no seal is required). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25A, except that no seal is required). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, DOCUMENT 00 70 00 (ADVERTISE)

Room 6 F01, Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

1.81 FAR 52.229-6, TAXES – FOREIGN FIXED-PRICE CONTRACTS (FEB 2013)

1.82 FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)*

1.83 FAR 52.232-17, INTEREST (MAY 2014)

1.84 FAR 52.232-23, ASSIGNMENT OF CLAIMS (MAY 2014)

1.85 FAR 52.232-27, PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

1.86 FAR 52.232-33, PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD

MANAGEMENT (OCT 2018)

1.87 FAR 52.232-39, UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)

1.88 FAR 52.233-1, DISPUTES (MAY 2014) ALTERNATE I (DEC 1991)

1.89 FAR 52.233-3, PROTEST AFTER AWARD (AUG 1996)

1.90 FAR 52.233-4, APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

1.91 FAR 52.236-1, PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)*

The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty (20) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

1.92 FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984)

1.93 FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

1.94 FAR 52.236-4, PHYSICAL DATA (APR 1984) [to be completed in each applicable task order]

Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by __________ [insert a description of investigational methods used, such as surveys, auger borings, core borings, test pits, probings, test tunnels].

(b) Weather conditions __________ [insert a summary of weather records and warnings].

(c) Transportation facilities _________ [insert a summary of transportation facilities providing access from the site, including information about their availability and limitations].

(d) ___________ [insert other pertinent information].

1.95 FAR 52.236-5, MATERIAL AND WORKMANSHIP (APR 1984)

1.96 FAR 52.236-6, SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

1.97 FAR 52.236-7, PERMITS AND RESPONSIBILITIES (NOV 1991)

1.98 FAR 52.236-8, OTHER CONTRACTS (APR 1984)

1.99 FAR 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (APR 1984)

1.100 FAR 52.236-10, OPERATIONS AND STORAGE AREAS (APR 1984)

1.101 FAR 52.236-11, USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

DOCUMENT 00 70 00 (ADVERTISE)

1.102 FAR 52.236-12, CLEANING UP (APR 1984)

1.103 FAR 52.236-13, ACCIDENT PREVENTION (NOV 1991) ALTERNATE I (NOV 1991)

1.104 FAR 52.236-14, AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)

1.105 FAR 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

1.106 FAR 52.236-16, QUANTITY SURVEYS (APR 1984)

1.107 FAR 52.236-17, LAYOUT OF WORK (APR 1984)

1.108 FAR 52.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

ALTERNATE I (APR 1984) AND ALTERNATE II (APR 1984)*

1.109 FAR 52.236-23, RESPONSIBILITY OF THE ARCHITECT-ENGINEER CONTRACTOR (APR 1984)

1.110 FAR 52.236-24, WORK OVERSIGHT IN ARCHITECT-ENGINEER CONTRACTS (APR 1984)

1.111 FAR 52.236-25, REQUIREMENTS FOR REGISTRATION OF DESIGNERS (JUN 2003) (not applicable if design is performed outside the United States and its outlying areas but See Document 00 73 00, para 4.10, Professional Registration for Designer-of-Record)

1.112 FAR 52.236-26, PRECONSTRUCTION CONFERENCE (FEB 1995)

1.113 FAR 52.242-13, BANKRUPTCY (JUL 1995)

1.114 FAR 52.242-14, SUSPENSION OF WORK (APR 1984)

1.115 FAR 52.243-4, CHANGES (JUN 2007)

1.116 FAR 52.243-6, CHANGE ORDER ACCOUNTING (APR 1984)

1.117 FAR 52.244-6, SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

(FEB 2024)

1.118 FAR 52.245-1, GOVERNMENT PROPERTY (SEP 2021) ALTERNATE I (APR 2012)

1.119 FAR 52.245-9, USE AND CHARGES (APR 2012)

1.120 FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996)

1.121 FAR 52.246-21, WARRANTY OF CONSTRUCTION (MAR 1994) ALTERNATE I (APR 1984)(see FAR

46.710(e)(2) applicability of alternate I)

1.122 FAR 52.248-3, VALUE ENGINEERING -- CONSTRUCTION (OCT 2020)*

1.123 FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED – PRICE)

(APR 2012) ALTERNATE I (SEP 1996)

1.124 FAR 52.249-10, DEFAULT (FIXED - PRICE CONSTRUCTION) (APR 1984)

1.125 FAR 52.251-1, GOVERNMENT SUPPLY SOURCES (APR 2012)

1.126 FAR 52.253-1, COMPUTER GENERATED FORMS (JAN 1991)

1.127 DFARS 252.201-7000, CONTRACTING OFFICER’S REPRESENTATIVE (DEC 1991)

1.128 DFARS 252.203-7000, REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD

OFFICIALS (SEP 2011)

1.129 DFARS 252.203-7001, PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER

DEFENSE-CONTRACT-RELATED FELONIES (JAN 2023)

1.130 DFARS 252.203-7002, REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (DEC

2022)

1.131 DFARS 252.203-7003, AGENCY OFFICE OF THE INSPECTOR GENERAL (AUG 2019)

1.132 DFARS 252.203-7004, DISPLAY OF HOTLINE POSTERS (JAN 2023)

1.133 DFARS 252.204-7000, DISCLOSURE OF INFORMATION (OCT 2016)

1.134 DFARS 252.204-7003, CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992)

1.135 DFARS 252.204-7004, ANTITERRORISM AWARENESS TRAINING FOR CONTRACTORS (JAN

2023)

1.136 DFARS 252-204-7009, LIMITATIONS ON THE USE OR DISCLOSURE OF THIRD-PARTY

CONTRACTOR REPORTED CYBER INCIDENT INFORMATION (JAN 2023)

1.137 DFARS 252.204-7012, SAFEGUARDING COVERED DEFENSE INFORMATION AND CYBER

INCIDENT REPORTING (DEVIATION 2024-O0013)(MAY 2024)

1.138 DFARS 252.204-7015, NOTICE OF AUTHORIZED DISCLOSURE OF INFORMATION FOR

LITIGATION SUPPORT (JAN 2023)

1.139 DFARS 252.204-7018, PROHIBITION ON THE ACQUISITION OF COVERED DEFENSE

TELECOMMUNICATIONS EQUIPMENT OR SERVICES (JAN 2023)

1.140 DFARS 252.204-7020, NIST SP 800-171 DOD ASSESSMENT REQUIREMENTS (NOV 2023)*

(a) Definitions.

Basic Assessment” means a contractor’s self-assessment of the contractor’s implementation of NIST SP 800-171 that—

(1) Is based on the Contractor’s review of their system security plan(s) associated with covered contractor information system(s);

(2) Is conducted in accordance with the NIST SP 800-171 DoD Assessment Methodology; and

(3) Results in a confidence level of “Low” in the resulting score, because it is a self-generated score.

“Covered contractor information system” has the meaning given in the clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, of this contract.

“High Assessment” means an assessment that is conducted by Government personnel using NIST SP 800-171A, Assessing Security Requirements for Controlled Unclassified Information that—

(1) Consists of—

(i) A review of a contractor’s Basic Assessment;

(ii) A thorough document review;

(iii) Verification, examination, and demonstration of a Contractor’s system security plan to validate that NIST SP 800-171 security requirements have been implemented as described in the contractor’s system security plan; and

(iv) Discussions with the contractor to obtain additional information or clarification, as needed; and

(2) Results in a confidence level of “High” in the resulting score.

“Medium Assessment” means an assessment conducted by the Government that—

(1) Consists of—

(i) A review of a contractor’s Basic Assessment;

(ii) A thorough document review; and

(iii) Discussions with the contractor to obtain additional information or clarification, as needed; and

(2) Results in a confidence level of “Medium” in the resulting score.

(b) Applicability. This clause applies to covered contractor information systems that are required to comply with the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, in accordance with Defense Federal Acquisition Regulation System (DFARS) clause at 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, of this contract.

(c) Requirements. The Contractor shall provide access to its facilities, systems, and personnel necessary for the Government to conduct a Medium or High NIST SP 800–171 DoD Assessment, as described in NIST SP 800–171 DoD Assessment Methodology at https://www.acq.osd.mil/asda/dpc/cp/cyber/docs/safeguarding/NIST-SP-800-171- Assessment-Methodology-Version-1.2.1-6.24.2020.pdf , if necessary.

(d) Procedures. Summary level scores for all assessments will be posted in the Supplier Performance Risk System (SPRS) () to provide DoD Components visibility into the summary level scores of strategic assessments.

(1) Basic Assessments. A contractor may submit, via encrypted email, summary level scores of Basic Assessments conducted in accordance with the NIST SP 800-171 DoD Assessment Methodology to for posting to

SPRS.

(i) The email shall include the following information:

(A) Version of NIST SP 800-171 against which the assessment was conducted.

(B) Organization conducting the assessment (e.g., Contractor self-assessment).

(C) For each system security plan (security requirement 3.12.4) supporting the performance of a DoD contract—

(1) All industry Commercial and Government Entity (CAGE) code(s) associated with the information system(s) addressed by the system security plan; and

(2) A brief description of the system security plan architecture, if more than one plan exists.

(D) Date the assessment was completed.

(E) Summary level score (e.g., 95 out of 110, NOT the individual value for each requirement).

(F) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(ii) If multiple system security plans are addressed in the email described at paragraph (b)(1)(i) of this section, the Contractor shall use the following format for the report:

System Security

Plan

CAGE Codes supported by this plan

Brief description of the plan architecture

Date of assessment

Total Score

Date score of 110 will achieved

(2) Medium and High Assessments. DoD will post the following Medium and/or High Assessment summary level scores to SPRS for each system security plan assessed:

(i) The standard assessed (e.g., NIST SP 800-171 Rev 1).

(ii) Organization conducting the assessment, e.g., DCMA, or a specific organization (identified by Department of Defense Activity Address Code (DoDAAC)).

(iii) All industry CAGE code(s) associated with the information system(s) addressed by the system security plan.

DOCUMENT 00 70 00 (ADVERTISE)

(iv) A brief description of the system security plan architecture, if more than one system security plan exists.

(v) Date and level of the assessment, i.e., medium or high.

(vi) Summary level score (e.g., 105 out of 110, not the individual value assigned for each requirement).

(vii) Date that all requirements are expected to be implemented (i.e., a score of 110 is expected to be achieved) based on information gathered from associated plan(s) of action developed in accordance with NIST SP 800-171.

(e) Rebuttals.

(1) DoD will provide Medium and High Assessment summary level scores to the Contractor and offer the opportunity for rebuttal and adjudication of assessment summary level scores prior to posting the summary level scores to SPRS (see SPRS User’s Guide https://www.sprs.csd.disa.mil/pdf/SPRS_Awardee.pdf).

(2) Upon completion of each assessment, the contractor has 14 business days to provide additional information to demonstrate that they meet any security requirements not observed by the assessment team or to rebut the findings that may be of question.

(f) Accessibility.

(1) Assessment summary level scores posted in SPRS are available to DoD personnel, and are protected, in accordance with the standards set forth in DoD Instruction 5000.79, Defense-wide Sharing and Use of Supplier and Product Performance Information (PI).

(2) Authorized representatives of the Contractor for which the assessment was conducted may access SPRS to view their own summary level scores, in accordance with the SPRS Software User’s Guide for Awardees/Contractors available at.

(3) A High NIST SP 800-171 DoD Assessment may result in documentation in addition to that listed in this clause. DoD will retain and protect any such documentation as “Controlled Unclassified Information (CUI)” and intended for internal DoD use only. The information will be protected against unauthorized use and release, including through the exercise of applicable exemptions under the Freedom of Information Act (e.g., Exemption 4 covers trade secrets and commercial or financial information obtained from a contractor that is privileged or confidential).

(g) Subcontracts.

(1) The Contractor shall insert the substance of this clause, including this paragraph (g), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services (excluding commercially available off-the-shelf).

(2) The Contractor shall not award a subcontract or other contractual instrument, that is subject to the implementation of NIST SP 800–171 security requirements, in accordance with DFARS clause 252.204–7012 of this contract, unless the subcontractor has completed, within the last 3 years, at least a Basic NIST SP 800–171 DoD Assessment, as described in https://www.acq.osd.mil/asda/dpc/cp/cyber/docs/safeguarding/NIST-SP-800-171- Assessment-Methodology-Version-1.2.1-6.24.2020.pdf , for all covered contractor information systems relevant to its offer that are not part of an information technology service or system operated on behalf of the Government.

(3) If a subcontractor does not have summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) posted in SPRS, the subcontractor may conduct and submit a Basic Assessment, in accordance with the NIST SP 800-171 DoD Assessment Methodology, DOCUMENT 00 70 00 (ADVERTISE) to mailto:webptsmh@navy.mil for posting to SPRS along with the information required by paragraph (d) of this clause.

1.141 DFARS 252.205-7000, PROVISION OF INFORMATION TO COOPERATIVE AGREEMENT

HOLDERS (JUN 2023)

1.142 DFARS 252.209-7004, SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED

BY THE GOVERNMENT OF A COUNTRY THAT IS STATE SPONSOR OF TERRORISM (MAY

2019)

1.143 DFARS 252.211-7003, ITEM UNIQUE IDENTIFICATION AND VALUATION (JAN 2023)*

1.144 DFARS 252.215-7002, COST ESTIMATING SYSTEM REQUIREMENTS (DEC 2012)

1.145 DFARS 252.215-7013, SUPPLIES AND SERVICES PROVIDED BY NONTRADITIONAL DEFENSE

CONTRACTORS (JAN 2023)

1.146 DFARS 252.215-7016, NOTIFICATION TO OFFERORS – POSTAWARD DEBRIEFINGS (DEC 2022)

(a) Definition. As used in this provision—

" Nontraditional defense contractor " means an entity that is not currently performing and has not performed any contract or subcontract for DoD that is subject to full coverage under the cost accounting standards prescribed pursuant to 41 U.S.C. 1502 and the regulations implementing such section, for at least the 1-year period preceding the solicitation of sources by DoD for the procurement (10 U.S.C. 3014).

(b) Postaward debriefing.

(1) Upon timely request, the Government will provide a written or oral postaward debriefing to successful or unsuccessful offerors for contract awards valued at $10 million or more, while protecting the confidential and proprietary information of other offerors. The request is considered timely if received within 3 days of notification of contract award.

(2) When required, the minimum postaward debriefing information will include the following:

(i) For contracts in excess of $10 million and not in excess of $100 million with a small business or nontraditional defense contractor, an option for the small business or nontraditional defense contractor to request disclosure of the agency's written source selection decision document, redacted to protect the confidential and proprietary information of other offerors for the contract award.

(ii) For contracts in excess of $100 million, disclosure of the agency's written source selection decision document, redacted to protect the confidential and proprietary information of other offerors for the contract award.

(3) If a required postaward debriefing is provided—

(i) The debriefed Offeror may submit additional written questions related to the debriefing not later than 2 business days after the date of the debriefing;

(ii) The agency will respond in writing to timely submitted additional questions within 5 business days after receipt by the contracting officer; and

(iii) The postaward debriefing will not be considered to be concluded until the later of—

(A) The date that the postaward debriefing is delivered, orally or in writing; or

(B) If additional written questions related to the debriefing are timely received, the date the agency delivers its written response.

DOCUMENT 00 70 00 (ADVERTISE)

(c) Contract performance. The Government may suspend performance of or terminate the awarded contract upon notice from the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .