24R1312 Note 6.docx
DOCX document 54 KB Posted
- Solicitation number
- N6274224R1312
About this file
This document provides answers to questions from potential offerors on solicitation number N6274224R1312 for the FY24 MCON P-406 Recreation Center at the US Naval Support Activity installation on Finegayan, Guam. The solicitation seeks design-bid-build construction services for the new recreation center. Questions and answers clarify that differing site conditions will be evaluated per FAR 52.236-2, fixed furnishings are considered part of construction, and that the contractor is responsible for obtaining necessary permits within the schedule defined in the solicitation despite potential delays in EPA approval. The Navy will not offer self-insurance or economic price adjustments to reduce risks for offerors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24R1312_AMD08.pdf | ||
| 24R1312_AMD07.pdf | ||
| P-406 DRAWINGS AMD06.pdf | ||
| 24R1312_AMD06.pdf | ||
| 24R1312 Note 7.pdf | ||
| P-406 DRAWINGS AMD05.pdf | ||
| 241312_AMD05.pdf | ||
| 24R1312_AMD04.pdf | ||
| 24R1312 Note 5.pdf | ||
| 24R1312 Note 4.pdf | ||
| 24R1312 Note 3.pdf | ||
| 24R1312_AMD0003.pdf | ||
| 24R1312 Note 2.pdf | ||
| 24R1312_AMD02.pdf | ||
| P-406 Site Visit Sign In Sheet.pdf | ||
| 24R1312_AMD01.pdf | ||
| 24R1312 Note 1.pdf | ||
| 3_P406 Drawings_Part2.pdf | ||
| 4_P406 Drawings_Part3.pdf | ||
| 24R1312-JA.ZIP | ZIP file | |
| 2_P406 Drawings_Part1.pdf | ||
| 1_P406 Specs.pdf | ||
| 0_24R1312-RFP.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC
258 MAKALAPA DRIVE, SUITE 100
JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134
Notice No. 6 7 December 2023
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-24-R-1312
FY24 MCON P-406 RECREATION CENTER,
US NAVSUPPACT MCB GUAM, FINEGAYAN, GUAM
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
NOTICE NO. 6
26. Section 01 30 02. 00 20, Page 1 Para. 1.2 General Requirements, 3rd Paragraph states below:
Fixed furnishings (items that are fixed to the structures), such as drying cages, weapon racks, motorized projection screens, window coverings and lockers are not considered FF&E and are part of the construction contract, Structural Interior Design (SID).
Please clarify if the Drying Cages, Weapon Racks and Lockers included as part of Contractor Furnished Contractor Installed (OFOI) Items. If included please provide drawings, specifications, and quantities, on that way we can sort out the material/equipment price for these 3-items.
ANSWER: Section 01 30 02. 00 20, Page 1 Para. 1.2 General Requirements, 3rd Paragraph, provides examples of fixed furnishings. Fixed furnishings such as Drying Cages, Weapon Racks, and Lockers are not part of the project. However, other fixed furnishing are part of the contract and the KTR is responsible for referencing the RFP to identify these items.
27. Sheet B-002 indicates that the soil borings were furnished for the convenience of the bidder and that the bidder is responsible for all assumptions, deductions or conclusions. Please confirm that since this is a design/bid/build project that the Government is ultimately responsible and not the bidder and as a result, unforeseen conditions that are discovered are to be considered a change condition
ANSWER: Confirmed, project is Design-Bid-Build. However, as noted on Sheet B-002, “No assurance is given that the subsurface or groundwater conditions shown on the boring logs are representative of the conditions to be encountered during construction. The bidder is solely responsible for all assumptions, deductions, or conclusions which he may which he may make or derive from his examination of the subsurface information and data furnished herein.” A claim of differing site conditions will comply with RFP Document 007000, FAR 52.236-2 Differing Site Conditions.
28. Please confirm the duration assumed in the schedule for EPA approval. It has been our experience that the process of obtaining an EPA permit has been taking approximately 6 months to obtain. Please confirm that the project duration will be extended as needed based upon delays in obtaining the permit, since this is not in the contractor’s control.
ANSWER: The RFP has been shared with Guam EPA to assist the project in permit approval efficiency. The Contractor is still responsible for obtaining any and all permits related to this project within the duration specified in the RFP Document 007000, FAR 52.211-10 Commencement, Prosecution, and Completion of Work. The RFP remains unchanged.
29. Please confirm if the government will agree to add an economic price adjustment factor for material or other costs, if excessive inflation impacts the costs on the project. This will assist the bidders in providing the most competitive price to the Government.
ANSWER: The RFP remains unchanged.
30. Costs for Builders Risk insurance is becoming more and more costly and harder to acquire. We would like to ask if the government would be interested in self-insuring for a portion or of or for the cost of natural or war-time disasters. This will help bring down the cost of the project for the government.
ANSWER: The Government will not provide a program of self-insurance. The RFP remains unchanged.
End of Notice image1.jpeg