About this file

This document provides answers to questions regarding solicitation number N62742-21-R-1313 for a construction project at Marine Corps Base Guam. The solicitation seeks proposals to complete FY21 MCON Project P-803 for the construction of an Individual Combat Skills Training facility at Finegayan, Guam. A request to extend the bid closing date by four weeks was denied and the closing date remains unchanged. Offerors must have a current Basic NIST SP 800-171 DoD Assessment completed and posted to the Supplier Performance Risk Assessment system prior to award as this is a requirement. The assessment must be no more than three years old unless a lesser time is specified in the solicitation. For offerors who have not yet completed an assessment, conducting and submitting a Basic Assessment is required to meet this pre-award requirement.

The document provides clarification on two questions received regarding the requirements for a current NIST assessment. It confirms the assessment is mandatory for award of the construction contract.

View the file

Other files

File Type Posted
AMD 03 21R1315.pdf PDF
21R1315 Note6-final.pdf PDF
21R1315 Note 5.pdf PDF
21R1315 Note 4.pdf PDF
21R1315 Note 3.pdf PDF
AMD 02 21R1315.pdf PDF
21R1315 Note 2-Final.pdf PDF
AMD 0001 21R1315.pdf PDF
P-803 Final Phase II Specifications.pdf PDF
P-803 Final Phase II Drawings.pdf PDF
N62742-21-R-1315 Front End.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice No. 1 17 May 2021

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-21-R-1315

FY21 MCON PROJECT P-803, INDIVIDUAL COMBAT SKILLS TRAINING, MARINE

CORPS BASE GUAM, FINEGAYAN, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

1. Given the complexity of the project, we are requesting to extend the bid closing date by at least four (4) weeks because of the turn around time from various supplier due to the pandemic.

RESP: The RFP closing date and time remains unchanged.

2. Page 3 of 21, c. Price and Technical Proposals, item g.

“As a part of the pre-award survey, the Contracting Officer will verify that summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old Unless a lesser time is specified in the solicitation are posted in the Supplier Performance Risk Assessment (SPRS) (https://www.sprs.csd.disa.mil/) (see DFARS 252.204-7019, Notice of NIST SP 800 171 DoD Assessment Requirements (Nov 2020)) prior to award. At minimum, a current Basic NIST SP 800-171 DoD Assessment is required prior to award.”

Question:

1) What if the Proposer has never had an assessment at all?

2) Is this assessment A MUST HAVE to meet requirement for the “pre-award survey?

RESP: This is a requirement for award of a contract. A current basic NIST is required. Please see Document 00600, 1.9 DFARS 252.204-7019, NOTICE OF NIST SP 800-171 DOD ASSESSMENT REQUIREMENT (NOV 2020). In particular, please see paragraph (c)(2) for instructions on conducting and submi8tting a Basic Assessment.

End of Notice

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC

258 MAKALAPA DRIVE, SUITE 100

JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134