20R1310_Notice2-Issued.pdf
PDF 657 KB Posted
- Solicitation number
- N62742-20-R-1310
About this file
This document provides notice of questions and answers related to solicitation N62742-20-R-1310. The solicitation involves the design and construction of a single-story low bay distribution warehouse (P-312) and a low-rise facility with reinforced walls, frame, floor, foundations and roof (P-804) at Joint Region Marianas, Guam for between $100-250 million. The NAICS code is 236220 and small businesses were notified through a sources sought notice and market survey. The completion period is anticipated at 767 calendar days. One question asked for a three-week extension to the March 26th phase one proposal submission date, which was denied, leaving the due date unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20R1310_Notice7_Issued.pdf | ||
| 20R1310_Notice6-Issued.pdf | ||
| 20R1310_Amend0003-Issued.pdf | ||
| 20R1310_Notice5-Issued.pdf | ||
| 20R1310_Notice4-Issued.pdf | ||
| 20R1310_Amend0002-Issued.pdf | ||
| 20R1310_Notice3.pdf | ||
| 20R1310_Amend0001-Issued.pdf | ||
| 20R1310_Notice1-Issued.pdf | ||
| !20R1310-PH1-RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND, PACIFIC
258 MAKALAPA DR., STE. 100
JBPHH, HI 96860-3134
RFP N62742-20-R-1310
Notice No. 1
Notice No. 2 4 Mar 2020
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-20-R-1310
WON 1619739, FY21 MCON P-312 DISTRIBUTION WAREHOUSE &
WON 1590906, FY21 MCON P-804 CENTRAL ISSUE FACILITY,
JOINT REGION MARIANAS, GUAM
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
9. Document 00100 Instruction to Proposers Page 1 of 14 Item 1.2., Request for Time
Extension
Thank you for the recent RFIs, however, we would respectfully request a 3-week extension to the current submission date of March 26 in order to address and develop a comprehensive response to the modified Construction & Design Experience technical elements of the Phase 1 submission.
ANSWER: The date and time set to receive Phase 1 proposals remains unchanged.