This file is a Questions and Answers document for federal contract N6264927RL005, USNS EARL WARREN (T-AO 207), FY27 Repair and Overhaul (ROH) Sustainment Support Unit (SSU) SN 27-010.

The document addresses three specification items with contractor inquiries and government responses. For Specification Item 0159, Deckhouse Preservation (10YR), the contractor requested approval to use SSPC-SP WJ-2 (Waterjet Cleaning) instead of SSPC-SP10 abrasive blasting due to environmental and regulatory constraints in Singapore, citing equivalent cleanliness and coating performance capabilities. The government rejected this request, requiring SSPC-SP10 surface preparation to remain as written because the surface roughness height (RHR) profile must be obtained. For Specification Item 0168, High Profile Non-Skid Weatherdeck Preservation (20PCT) (1YR), the contractor sought confirmation of quoted quantities (HP washing 18,300 ft², blasting 12,850 ft², epoxy painting with 2 coats on blasted areas, non-skid painting on full area with 1 coat, and 100 or 300 tiedown sockets) and asked whether hydroblasting or WJ-2 was acceptable as an alternative surface preparation method. The government similarly rejected the alternative method, requiring SSPC-SP10 surface preparation as written. For Specification Item J-3, Work Items 0021/0568A/0569, the contractor identified discrepancies between the price sheet and received specifications, requesting corrections for Work Item 0021A (should be 0021), Work Item 0568A description, and adding Work Item 0569. The government approved these corrections in a revised J-3 schedule.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6264927RL005 USNS EARL WARREN (T-AO 207)

FY27 ROH SSU SN 27-010

SPECIFICATION ITEM NO.: _____0159____________ PARA. NO.______7.10.5_______

TITLE: Deckhouse Preservation (10YR)

1. QUESTION:

Kindly advise if we can allow to carry-out WJ-2 in lieu of abrasive blasting SSPC-SP10 for the surface preparation of the deckhouse vertical areas.

Due to environmental and regulatory constraints for onboard quay execution in Singapore, dry abrasive blasting is restricted. As such, we have proposed:

- SSPC-SP WJ-2 (Waterjet Cleaning) as an alternative surface preparation method.

- This method is widely accepted and capable of achieving equivalent cleanliness and coating performance where permitted.

We are seeking formal approval/deviation from MSC to use SSPC-SP WJ-2 (Waterjet Cleaning) as an alternative surface preparation method.

1a ANSWER: Item SSPC-SP10 for surface prep must stay as written due to surface RHR profile needs to be obtained

SPECIFICATION ITEM NO.: _____0168____________ PARA. NO._____3.1.2 &7.9____

TITLE: High Profile Non-Skid Weatherdeck Preservation (20PCT) (1YR)

2. QUESTION:

1) Please confirm if below are correct quantities to be considered in the quote:

-HP washing – 18,300ft2 -Blasting – 12,850ft2 -Painting (epoxy) (blasted areas) – 12,850ft2 x 2 coats -Painting (non-skid) (full area?) – 18,300ft2 x 1 coat -Number of tiedown sockets – 100 nos or 300 nos?

2) Please advise if hydroblasting or WJ-2 is acceptable for the blasting method/surface preparation.

Due to environmental and regulatory constraints for onboard quay execution in Singapore, dry abrasive blasting is restricted. As such, we have proposed:

- SSPC-SP WJ-2 (Waterjet Cleaning) as an alternative surface preparation method.

- This method is widely accepted and capable of achieving equivalent cleanliness and coating performance where permitted.

We are seeking formal approval/deviation from MSC to use SSPC-SP WJ-2 (Waterjet Cleaning) as an alternative surface preparation method.

2a ANSWER: SSPC-SP10 for surface prep must stay as written due to surface RHR profile needs to be obtained.

SPECIFICATION ITEM NO.: ____J-3_______ PARA. NO.____________________

TITLE: Work Items 0021/ 0568A/0569

3. QUESTION:

• Price sheet lists Spec 0021A. Spec received is 0021.

• Price sheet lists WI 0568A TAO205-CCSI-FIRE AND SMOKE DETECTION AND

ALARM SYSTEM (1 YR) (SCSI), but spec received is 0568A_A_TAO205-CCSI-

WATER MIST-SPRAY-SPRINKLER INSPECTION AND TEST (1 YR) (SCSI)

• Received spec 0569_A_TAO205-CCSI-FIRE AND SMOKE DETECTION AND ALARM SYSTEM (1 YR) (SCSI) that doesn’t appear on price sheet.

3a ANSWER: See revised J-3:

Correct Work Item 0021A to 0021

Correct 0568A from TAO205-CCSI-FIRE AND SMOKE DETECTION AND ALARM SYSTEM (1 YR) (SCSI) to TAO205-CCSI-WATER MIST-SPRAY-SPRINKLER

INSPECTION AND TEST (1 YR) (SCSI)

Add Work Item 0569 TAO205-CCSI-FIRE AND SMOKE DETECTION AND ALARM

SYSTEM (1 YR) (SCSI)