This is a Statement of Work (SOW) for auxiliary machinery work on the USNS Earl Warren (TAO 205-207), Contract No. N00000-00-X-0000, Item No. 0521, categorized as "A" with a completion date of November 17, 2026. The work involves the installation of low-temperature fresh water (LTFW) cooling piping for steering gear pump units and a steering gear cooler foundation fitted to the steering gear pump skid, with installations spanning multiple compartments including the Main Machinery Room (MMR), Sewage Treatment Room, Passage, Shaft Alley Access, ERAST Room, and Steering Gear Room on both port and starboard sides.

Government-furnished material (GFM) includes four shell and tube heat exchangers (EKF-1036-6-T), four 7.5 HP motors (00718ET3E213TC-W22), and four hydraulic vane pumps (35V38A 1C22R). The contractor must furnish all additional materials such as fittings, weld material, and pipe hangers not included in the referenced drawings, plus all labor, staging, tools, and services required for completion. Work includes structural installations per Reference 2.1.7, mechanical piping per Reference 2.1.8, joiner modifications, preparation of red-lined and final "As-Built" drawings with Weight Control Data and Electric Plant Distribution Impact Table blocks, comprehensive testing and inspections (including NDT weld inspection), and painting of all new and disturbed areas. The contractor is responsible for coordinating with the Chief Engineer and Principal Port Engineer, managing all interferences and relocations, providing gas-free engineering and fire watch services for hot work, maintaining fire tightness per ABS surveyor requirements, and bearing all costs for regulatory body services (ABS and Coast Guard). Quality assurance includes inspections and acceptance by the Chief Engineer and MSCREP (Military Sealift Command Repair and Modernization Program), with ABS Surveyor attendance provided by the Government. All work must comply with applicable General Technical Requirements (GTRs 1-7, 22-29) and be performed in accordance with Regulatory Body rules and ABS requirements.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS Earl Warren

( TAO 205 207 )

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

(SCSI)

Port Engineer's Name

0521 - 1

1.0 ABSTRACT

This item describes the addition of LTFW Cooling piping installed for the steering gear pump units and a steering gear cooler foundation fitted to the steering gear pump skid.

2.0 REFERENCES/ENCLOSURES

2.1 REFERENCES

2.1.1 803-7081122, Military Sealift Command General Technical Requirements (GTR’s)

2.1.2 MSC Drawing No. 803-7080803, Computer Aided

Designed (CAD) Drawing Standard

2.1.3 NAVSEA Drawing No. 631-8726946, Paint Schedule

2.1.4 NAVSEA Drawing No. 631-8726947, Paint Code

Matrix

2.1.5 NAVSEA Drawing No. 801-8723886, General

Arrangement

2.1.6 NAVSEA Drawing No. 640-8723999, Color

Coordination Manual

2.1.7 MSC Drawing No. 185-XXXXXXX, LTFW Steering

Gear Cooling Modification – Structural

2.1.8 MSC Drawing No. 536-XXXXXXX, LTFW Steering

Gear Cooling Modification – LTFW Cooling Piping

2.1.9 Structural Analysis: Steering Gear Cooler

Assembly

2.1.10 T-AO TALT-205-0134 Steering Gear Modifications

(Mechanical)

2.1.11 T-AO TALT-205-0134 Steering Gear System

Foundations

3.0 ITEM LOCATION/DESCRIPTION

3.1 Locations/Quantity

3.1.1 Port LTFW Steering Gear Cooling

3.1.1.1 MMR (5-193-0)

3.1.1.2 Sewage Treatment Room (3-214-2)

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 2

3.1.1.3 Passage (2-214-2)

3.1.1.4 Shaft Alley Access (6-229-0)

3.1.1.5 ERAST Room (3-244-0)

3.1.1.6 Steering Gear Room (2-253-0)

3.1.2 Starboard LTFW Steering Gear Cooling

3.1.2.1 MMR (5-193-0)

3.1.2.2 Electrical Storeroom (3-224-1)

3.1.2.3 Passage (2-214-1)

3.1.2.4 Shaft Alley Access (6-229-0)

3.1.2.5 Mooring Line Stowage (2-244-1)

3.1.2.6 ERAST Room (3-244-0)

3.1.2.7 Steering Gear Room (2-253-0)

3.2 Item Description/Manufacturer’s Data

3.2.1 Material/Components, including specific quantities

and manufacturer make and model numbers, necessary to accomplish work required by this work item are included in the List of Materials of References

2.1.7 & 2.1.8.

3.2.2 Quantities specified in the List of Materials of

4.2 will be GFM, additional material such as fittings, weld material, pipe hangers, etc., which are not included in the Lists of Materials of References 2.1.7 & 2.1.8 shall be considered CFM, to install fully functional systems that meet the requirements of this specification.

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 3

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Government Furnished Equipment (GFE): None.

4.2 Government Furnished Material (GFM):

QTY

REQD

DESSCRIPTION P/N

4 SHELL & TUBE HEAT EXCHANGER EKF-1036-6-T

4 MOTOR 7.5 HP, 1800 RPM, 230/460, 213/5TC FRAME,

60HZ, 3 PHASE, TEFC, F1 MOUNT, CLOSE-COUPLED

00718ET3E213TC-W22

4 HYDRAULIC VANE PUMP, 35V38A

1C22R, 38 GPM RING CAPACITY, 1- 5/16 SQUARE

35V38A 1C22R

4.3 Government Furnished Services (GFS): None.

4.4 Government Furnished Information (GFI): None.

5.0 NOTES

5.1 The ship’s force will provide access to any required

spaces.

5.2 The contractor shall coordinate all piping and

electrical lock outs/tag outs with the Chief Engineer and Principal Port Engineer.

5.3 The contractor and all subcontractors, regardless of

tier, must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors, regardless of tier, must comply with the requirements of all applicable GTRs, including but not limited to: GTR’s 1 through 7, 22, 23, 24, 27, 28, and 29.

5.4 The contractor and all subcontractors, regardless of

tier, are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

5.5 Existing compartment names and numbers are used for

the removals work. New compartment names and numbers are used for the modification and installation work.

5.6 All material removed and not reinstalled as part of

this work item shall be wrapped in plastic and

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 4 palletized to prevent damage and turned over to the MSCREP via DD1149 prior to work item close out.

5.7 The order of removals and installations are listed by

discipline and not chronologically in the work item.

Contractor to coordinate all removals and installations to align with good engineering practices for desired final result.

5.8 Contractor shall provide gas free engineering/chemist

services and fire watch for all hot work evolutions in this work item.

5.9 The contractor shall be responsible to certify that

all affected spaces are safe for entry, safe for hot work, provide ventilation to the space while people are working in the space and provide the required fire watch personnel.

6.0 QUALITY ASSURANCE REQUIREMENTS:

6.1 Inspection and acceptance of all work shall be by the

Chief Engineer and MSCREP.

6.2 All work performed shall be in accordance with

Regulatory Body rules and regulations.

6.3 Government will furnish ABS Surveyor attendance.

Contractor is responsible for coordinating any or all onsite visits required for ABS representative to witness testing and inspections.

6.4 New cable and/or mounting of equipment that requires

welding or hot work performed in the service areas (from the interior or exterior) shall maintain the fire tightness to the satisfaction of the ABS surveyor and the MSCREP.

7.0 STATEMENT OF WORK REQUIRED

Provide all labor, materials, staging, and tools required to accomplish this specification.

7.1 Arrangements/Outfitting

7.1.1 The Contractor is responsible for the

identification and resolution of all interferences and boundaries affecting the accomplishment of this work item. The Contractor shall temporarily remove, relocate, AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 5 alter, and reroute all interferences, mechanical, electrical, furnishings, insulations, and/or misc. equipment to facilitate the completion of this work item.

All interferences shall be reinstalled using contractor furnished hardware, fasteners, gaskets, seals, O-Rings, etc.

7.1.2 Modifications:

7.1.2.1 Modify joiner work in way of added

piping in accordance with Reference 2.1.8.

7.2 Structural

7.2.1 Installations: Install the low temperature

fresh water steering gear cooler foundation and associated equipment foundations in accordance with Reference 2.1.7.

7.3 Mechanical/Fluids: Install low temperature fresh water

piping in accordance with Reference 2.1.8.

7.4 Preparation of Drawings/Documentation

7.4.1 Maintain red-lined mark ups of References

2.1.5, 2.1.7, 2.1.11 & 2.1.12 to reflect all installations, modifications, and any changes accomplished. Red-lined drawings shall be used for creating the final “As-Built” drawings.

7.4.2 The contractor shall contact the MSCREP in

writing to request MSC drawing number(s) be assigned and provided to the contractor. These drawing number(s) shall be used for the final “As-Built” drawing.

7.4.3 Provide final “As-Built” drawings to reflect

the actual final installation configurations for all efforts accomplished in accordance with this work item.

7.4.4 Final “As-Built” Drawings shall include a

completed and filled-in “Weight Control Data” block using References 2.1.1 thru 2.11 for guidance, accounting for both the removals and the installations as separate line items. The contractor shall perform calculations necessary to populate the data fields on the “Weight Control Data” block.

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 6

7.4.5 Final “As-Built” Drawings shall include a

completed and filled-in “Electric Plant Distribution Impact Table” block using Ref.

2.1.9 as guidance, accounting for both the removals and the installations as separate line items. The contractor shall perform calculations necessary to populate the data fields on the “Electric Plant Distribution Impact Table” block.

7.4.6 All submitted drawings shall be reviewed by

MSCREP prior to final acceptance.

7.4.7 After MSCREP concurrence to the final “As-

Built” drawings, contractor shall submit “As- Built” drawings to American Bureau of Shipping (ABS) for regulatory review and approval, for compliance with all applicable ABS requirements and USCG regulations. Contractor shall receive ABS “stamped” approved drawings, and respective approval letters, and submit deliverables to the MSCREP.

7.5 Contractor Inspection/Test

7.5.1 Inspections:

7.5.1.1 Throughout the work in all areas

affected by this work item, the Contractor shall maintain a listing of each space, with annotations for work performed, inspection points, and acceptances. This listing shall be made available to the MSCREP within 24 hours of request and a final version presented to the MSCREP after final walk-through of all affected compartments.

7.5.1.2 Contractor and MSCREP shall conduct a

joint inspection of areas to be prepared and painted before surface preparation begins to ensure that protective measures are implemented.

7.5.1.3 Contractor shall perform inspections

after completion of each stage of surface preparation, each coat, and each stripe coat, to verify surface condition, DFT and space cleanliness, AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 7 and before securing space. At least 2 DFT readings shall be taken per 100 square feet.

7.5.2 Tests:

7.5.2.1 All tests shall be accomplished in the

presence of and to the satisfaction of the MSCREP and Chief Engineer.

7.5.2.2 All testing shall be accomplished on

all new and modified material, equipment, and systems using Ref. 2.1.1 as guidance.

7.5.2.3 Perform operational tests in the

presence of the ABS Surveyor and MSCREP to verify that:

7.5.2.3.1 All work has been performed

satisfactorily and to the specific instructions and requirements of the work item, manufacturer, and regulatory bodies.

7.5.2.3.2 The equipment, material, machinery, or system including all flows, levels, temperatures, loads, and alarms complies with manufacturer’s parameters.

7.5.2.3.3 The equipment, material, machinery, or system performs its intended purpose.

7.5.2.4 In addition to the requirements of

2.1.12 for electrical Systems:

7.5.2.4.1 Cable Insulation Resistance Test

of all new and modified cabling.

7.5.2.4.2 Accomplish an Enclosure Ground

Test of all new and modified electrical equipment enclosures for continuity and resistance of the grounding path. The resistance of the grounding path between the equipment enclosure and a ship structural member shall not exceed 0.1 ohm.

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 8

7.5.2.4.3 A completion test verifies that

all aspects of the work item have been completed. For compartments, it means all equipment, piping, electrical, HVAC, deck coverings, and overheads are installed and tested. A completion test also verifies the compartment has been wiped down/cleaned and is ready for service.

7.5.2.4.4 The contractor shall prove proper

operation of all re-installed interferences and equipment removed and disturbed in the presence of the MSCREP.

7.5.2.4.5 Perform NDT inspection on new, modified, or repaired welds in accordance with ABS Rule and regulation and contractor’s Quality Assurance Plan. All results of the weld inspection to be reviewed for approval by Port Engineer and ABS surveyor.

7.5.2.4.6 Completion Test in accordance

with GTR 3.

7.6 Insulation and Painting

7.6.1 Insulation: None.

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 9

7.6.2 Painting (General):

7.6.2.1 Prepare prime, and paint all new and

disturbed areas to match the surrounding surfaces using contractor–supplied paint.

This includes any decks, bulkheads, lagging, and all adjacent space coatings that have been damaged by heat from welding. Surface preparation and paint coating application requirements are provided in References 2.1.1, 2.1.3 and 2.1.4.

7.7 Markings

7.7.1 Install label plates, notices, and markings for

all new equipment and systems using References

2.1.1 and 2.1.6 as guidance.

7.8 Manufacturer’s Representative: None

8.0 GENERAL REQUIREMENTS:

8.1 The Contractor shall maintain area of work onboard

ship, clean and free of debris at all times and ensure work area is clean at the end of each day.

8.2 The Contractor shall furnish all labor, staging, ladders, blocking, rigging, cranes, and tools, necessary to accomplish the requirements of this work item.

8.3 The Contractor shall remove and reinstall all

interferences necessary to accomplish this work item.

8.4 The Contractor shall bear the cost for all services of

the Regulatory Bodies, ABS or Coast Guard, necessary to accomplish the requirements of this work item.

8.5 Inspection and acceptance of work shall be obtained

from the Supervisor.

AUXILIARY MACHINERY CONTRACT NO. N00000-00-X-0000

ITEM NO. 0521 CATEGORY "A" 2026-11-17

TAO205-CSI-SALT WATER SPRINKLING SYSTEM (1 YR)

0521 - 10

Structural Analysis: Steering Gear Cooler Assembly

Figure 1. Steering Gear Cooler Assembly

6.3 Government will furnish ABS Surveyor attendance. Contractor is responsible for coordinating any or all onsite visits required for ABS representative to witness testing and inspections.
Structural Analysis: Steering Gear Cooler Assembly