0502_A_Insulation and Lagging Repairs.pdf

PDF 122 KB Posted

Attached to
USNS EARL WARREN (T-AO 207) ROH/UWILD AMENDMENT 0003
Solicitation number
N6264927RL005
Issued by

About this file

This document is a Statement of Work (SOW) for auxiliary machinery repairs aboard the USNS Earl Warren (TAO 207), issued under Contract No. SSU SN 27-010, Item No. 0502, categorized as "A" priority, with a date of 2026-11-17.

The contractor is required to repair or replace damaged, deteriorated, or missing insulation and lagging throughout the vessel. The work encompasses multiple bulkhead piping systems and ducting locations, including refrigeration tubing and fittings ranging from 5/8" to 2" diameter and various lengths (20–40 feet), condensate drain piping, E-Stream cooling water piping, and AC ducting systems totaling approximately 30 square feet in the pumproom overhead. The contractor must verify all sizes, dimensions, and quantities prior to commencement of repairs, as all provided measurements are approximate. No government-furnished equipment, materials, or services are provided. The contractor shall coordinate with ship's force for lockout/tag-out procedures, install protective barriers to prevent contamination, erect and remove staging as needed, and remove any interferences required to access repair areas. All new and disturbed insulation and lagging must receive lagging sealant and two top coats of paint to match surrounding surfaces. All identification and directional flow markings must be restored to original condition, and all dirt and debris must be removed from the vessel daily. Quality assurance requires that all work be performed to the satisfaction of the Port Engineer and Chief Engineer. No manufacturer's representative or drawing preparation is required for this work item.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS Earl Warren

( TAO 207 )

AUXILIARY MACHINERY CONTRACT NO. SSU SN 27-010

ITEM NO. 0502 CATEGORY "A" 2026-11-17

Insulation and Lagging Repairs Robson, Henry

0502 - 1

1. ABSTRACT

1.1 This item describes the repair or replacement of damaged, deteriorated, or missing insulation and lagging throughout the vessel.

2. REFERENCES/ENCLOSURES

2.1 References:

2.1.1 MSC Drawing 516-8953774 – Refrigeration System Diagram

2.1.2 NAVSEA DWG No. 635-8727027, Insulation Arrangement Shipwide.

2.1.3 NAVSEA DWG No. 635-8727029, Insulation Details

2.1.4 NSTM Chapter 635, Thermal, Fire & Acoustic Insulation.

2.2 Enclosures: None.

3. ITEM LOCATION/DESCRIPTION/QUANTITY

3.1 Location/Description/Quantity:

3.1.1 Bulkhed piping

a) 06 level overhead stbd, 1”copper refrigeration tubing & fittings x 40 ft. long.

b) 01-193-2 condensate drain, 1” copper refrigeration tubing & fittings x 24 ft. long

c) 01-196-1 aft bullhead, 5/8” copper refrigeration tubing & fittings x 26 ft. long.

d) 01-193-1 fwd bulkhead, 5/8” copper refrigeration tubing & fittings x 26 ft. long

e) 1-193-2 condensate drain, 1” copper refrigeration tubing & fittings x 24 ft. long

f) 1-193-1 fwd bulkhead ships general store, 1” copper refrigeration tubing & fittings x 24 ft. long

g) 1-218-1 AC210 ducting in aff room 30sq ft

h) 2-97-0 E-Stream cooling water piping 3/8” copper tubing & fittings x 20 ft. long

i) 2-193-2 condensate drain piping 2” & fittings x 30 ft. long

j) 3-193-2 condensate drain piping from drain funnel 2 & fittings x 30 ft. long

k) 5-97-0 3rd platform AC530 & AC531 condensate drain piping in pumproom overhead 30sq ft

4 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES

4.1 Government Furnished Equipment (GFE): None

4.2 Government Furnished Material (GFM)None

4.3 Government Furnished Services (GFS): None

5 NOTES

USNS Earl Warren

( TAO 207 )

AUXILIARY MACHINERY CONTRACT NO. SSU SN 27-010

ITEM NO. 0502 CATEGORY "A" 2026-11-17

Insulation and Lagging Repairs Robson, Henry

0502 - 2

5.1 MSC Info: VRR 26-088.

5.2 All sizes provided are approximate. The contractor shall verify all sizes, dimensions, and quantities prior to commencement of repairs.

6 QUALITY ASSURANCE REQUIREMENTS

6.1 All work performed shall be to the satisfaction of the Port Engineer and the Chief

Engineer

7.0 STATEMENT OF WORK REQUIRED

7.1 Replace the damaged, deteriorated, or missing insulation and lagging as detailed in paragraph 3.1, using references 2.1.1, 2.1.2, and 2.1.3 for guidance.

7.1.1 Ship’s force shall lock-out and tag-out machinery or piping systems as required, prior to commencement of repairs.

7.1.2 Plastic drop cloths, curtains, or tarps shall be installed and maintained to prevent dust and debris contamination of equipment, machinery, and furnishings.

7.1.3 Erect staging as required to gain access to repairs. Remove upon completion.

7.1.4 Remove interferences as required to gain access to repairs. Reinstall upon completion.

7.2 Apply lagging sealant and two (2) top coats of paint to the new and disturbed insulation and lagging to match surrounding surfaces.

7.3 Restore all identification and directional flow markings as original.

7.4 All dirt and debris resulting from this work item shall be removed from the ship daily and all areas left clean and in good order.

7.5 Preparation of Drawings: None.

7.6 Manufacturer’s Representative: None.

8.0 GENERAL REQUIREMENTS

8.1 None additional.

1. ABSTRACT
2. REFERENCES/ENCLOSURES
2.1 References:
2.1.1 MSC Drawing 516-8953774 – Refrigeration System Diagram
2.1.2 NAVSEA DWG No. 635-8727027, Insulation Arrangement Shipwide.
2.1.3 NAVSEA DWG No. 635-8727029, Insulation Details
2.1.4 NSTM Chapter 635, Thermal, Fire & Acoustic Insulation.
2.2 Enclosures: None.
3. ITEM LOCATION/DESCRIPTION/QUANTITY
5 NOTES
5.1 MSC Info: VRR 26-088.
6 QUALITY ASSURANCE REQUIREMENTS
8.0 GENERAL REQUIREMENTS
8.1 None additional.

File details come from the government source that posted it. Updated .