Revised_Attachment 5_RUS 7C1 SRA PERL (Rev. 1).xlsx

XLSX spreadsheet 65 KB Posted

Attached to
USS RUSHMORE (LSD-47) 7C1 SRA 52pkg
Solicitation number
N6264926R0011
Issued by

About this file

This is a Production and Event Readiness List (PERL) scheduling attachment for the USS RUSHMORE (LSD-47) 7C1 Ship Repair Availability (SRA) contract. The spreadsheet details 52 Item Control Numbers (ICNs) representing specific repair and maintenance work items required during the vessel's availability period from October 12, 2026, through July 31, 2027, at Commander Fleet Activities Sasebo (CFAS), India Basin. Work items encompass structural repairs, preservation work, equipment overhauls, and system testing across multiple vessel systems including ballast tanks, main propulsion diesel engines (MPDE), oily waste and bilge systems, ventilation ducts, and auxiliary machinery. Each ICN is tracked against multiple completion milestones designated by event codes (PW42, WC42, WC00, etc.), with Production Completion Dates (PCD) and key operational readiness events such as Main Machinery Space Propulsion Plant completion (PW00), Crew Move Aboard (HB00), Commence Combat Systems Light Off (CX00), Dock Trials (DT00), Fast Cruise (FC00), and Sea Trials (ST00), with final availability end targeted for March 30, 2027.

The PERL establishes strict scheduling requirements with work categorized by completion status codes (I for Open & Inspect per CFR, P for Production Complete, T for Testing Complete, C for Certification Complete). Multiple ICNs have been revised through various contract amendments, with Production Completion Dates adjusted to accommodate schedule changes. The solicitation (N6264926R0011) is limited to firms holding active Master Ship Repair Agreements (MSRA) or Agreements for Boat Repair (ABR) with the U.S. Navy in the Japan Region as Prime Contractors, or firms meeting Navy requirements for MSRA/ABR certification. Proposals are due July 29, 2026, at 10:00 AM Japan Standard Time, with this work being performed under firm fixed-price job order terms. The contractor must report progress against milestone PW42 and maintain compliance with schedule management requirements outlined in the specification documents.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926R00110008 SF30.pdf PDF
Solicitation Amendment - N6264926R00110008 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110007 SF30.pdf PDF
Solicitation Amendment - N6264926R00110007 Conformed Copy.pdf PDF
Solicitation Amendment - N6264926R00110006 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110006 SF30.pdf PDF
Solicitation Amendment - N6264926R00110005 Conformed Copy.pdf PDF
Attachment 2_Price Proposal Sheet N6264926R0011 (Rev. 3).xlsx XLSX spreadsheet
Solicitation Amendment N6264926R00110005 SF30.pdf PDF
Solicitation Amendment N6264926R00110004 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110004 SF30.pdf PDF
Attachment 8_Contractor Questions 2.pdf PDF
Attachment 2 Price Proposal Breakdown Sheet N6264926R0011 (Rev. 2).xlsx XLSX spreadsheet
Solicitation Amendment N6264926R00110002.pdf PDF
Solicitation Amendment N6264926R00110002 Conformed Copy.pdf PDF
Attachment 7_Contractor Questions 1.pdf PDF
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011 (Rev. 1).xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A005 Weekly Progress Report.pdf PDF
Attachment 6_PPI Contract Data Sheet(s) N6264926R0011.docx DOCX document
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A010 KTR Deficiency Reporting.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A003 IPS.pdf PDF
Solicitation - N6264926R0011.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A007 Key Events Report.pdf PDF
Solicitation Amendment N6264926R00110001.pdf PDF
Attachment 5_RUS 7C1 SRA PERL.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A006 Conference Reports.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A002 Quality Assurance Program Plan.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A004 Daily Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A008 Temporary Services.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A001 GFM Not.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A009 Fire Safety Council.pdf PDF
Attachment 3_Contractor Questions.pdf PDF
Attachment 4_Milestones and Key Events List (RUS 7C1).pdf PDF
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A001 GFM Not.pdf PDF
Solicitation - N6264926R0011.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A008 Temporary Services.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A005 Weekly Progress Report.pdf PDF
Attachment 6_PPI Contract Data Sheet(s) N6264926R0011.docx DOCX document
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A004 Daily Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A007 Key Events Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A003 IPS.pdf PDF
Attachment 3_Contractor Questions.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A010 KTR Deficiency Reporting.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A009 Fire Safety Council.pdf PDF
Attachment 5_RUS 7C1 SRA PERL.xlsx XLSX spreadsheet
Attachment 4_Milestones and Key Events List (RUS 7C1).pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A002 Quality Assurance Program Plan.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A006 Conference Reports.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

NOICNKOIJSNTITLESuggest KE/MSSuggest PCDPS00PF00AM15
(Ammo Off Load to support(SA00))SA00

(Start Availability)

AT42

(Complete All Work to Support AT00)

AT00
(Assessment Completion)CX41

(Combat HM&E Support Systems Complete)

CX42

(All Systems Ready to Support (CX00))

HB42

(Work Complete to Support HB00 [INCLUDES CANES])

HB00

(Crew Move Aboard)

CX00

(Commence Combat Systems Light Off (CSLO))

PW42

(Work &Testing Complete to Support (PW00))

PW00
(Main Machinery Space Propulsion Plant Complete (PCD))FM16
(Fuel Onload w/ISIC Oversight/Repair Period)LT42

(Hot Plant Testing w/ISIC Oversight / Repair Period)

AV42

(Work Complete to Support AVCERT)

WC42

(Work & Testing Complete to Support (WC00))

WC00

(All Work COmplete)

DT00 (Commence Dock Trials)
FC00

(Start Fast Cruise)

ST00 (Commence Sea Trials)
CA00 (End of Availability)
EG00 (End Guarantee Period)
COMMENTSEvent Readiness List (Work Item Title)

Legend: "I" = Open & Inspect (CFR), "P" = Production Complete, "T" = Testing Complete, "C" = Certification Complete.

138E9312306RA01ER01-ZJP6
ER01-ZJP7ACCESSIBLE VOID 6-56-4-V; REPAIRPW423/30/271/8/273/30/27PC
238E9312315RA01EM01-6720, ES01-NP9A

ES01-NPA9, ES01-NPAA

ES01-NPABDECK PLATING ON MMR NO.ONE UPPER LEVEL; REPAIR
PW423/30/271/8/273/30/27PC
338E9312317RA01EM01-ZEC0BILGE AREA IN FWD SHAFT ALLEY; PRESERVEPW423/30/271/8/273/30/27IPC
438E9312318A01EM01-ZEC1WASTE WATER DRAIN COLLECTING TANK 6-61-2-W; REPAIRPW423/30/271/8/273/30/27IPC
538E9312319RA01ES01-NP4T, EM02-ZE07BILGE AREA IN MAIN MACHINERY ROOM NUMBER 2; PRESERVEPW423/30/271/8/273/30/27IPC
638E9312324RA01ES01-NP4V
DECK SURFACE IN 3-74-1-E; PRESERVEPW423/30/2710/12/263/30/27CFWD A/C Plant
738E9312326RA01EA02-ZA72, EA02-ZA74JP-5 SERVICE TANK 6-98-5-J; REPAIRPW423/30/271/8/273/30/27IPC
838E9312327A01ER01-ZJL2, ER01-ZJQ5WASTE WATER DRAIN COLLECTING TANK 6-83-1-W; REPAIRPW423/30/2710/12/263/30/27IPC
938E9312328A01ER01-ZJQ1, ER01-ZJU0, ER01-ZJM5BALLAST TANK 6-81-3-W; REPAIR AND PRESERVEWC423/30/2710/12/263/30/27IPC
1038E9312329A01ER01-ZJN0, ER01-ZJP3BALLAST TANK 6-89-1-W; REPAIRWC423/30/2710/12/263/30/27IPC
1138E9312330RA01ER01-ZJN1, ER01-ZJO6BALLAST TANK 6-74-0-W; REPAIRPW423/30/271/8/273/30/27IPC
1238E9312331RA01ER01-ZJM8, ER01-ZJP1BALLAST TANK 6-83-0-W; REPAIRPW423/30/271/8/273/30/27IPC
1338E9312334RA01ER01-ZJM2, ER01-ZJQ0
ER01-ZJT7BALLAST TANK 6-85-1-W; REPAIR AND PRESERVEWC423/30/271/8/273/30/27IPC
1438E9312341A01EB14-ZH27, EB14-ZH28WASTE OIL TANK 6-59-1-F; REPAIRPW423/30/271/8/273/30/27IPC
1538E9312342A01EB14-ZH30, EB14-ZH29OILY WASTE HOLDING TANK 6-59-2-F; REPAIRPW423/30/271/8/273/30/27IPC
1638E9312343A01EB14-ZH33, EB14-ZH34OILY WATER DRAIN COLLECTING TANK 6-65-2-W; REPAIRPW423/30/271/8/273/30/27IPC
1738E9312344A01EB14-ZH35, EB14-ZH36OILY WASTE HOLDING TANK 6-81-1-F; REPAIRPW423/30/2710/12/263/30/27IPC
1838E9312345A01EB14-ZH37, EB14-ZH38WASTE OIL TANK 6-81-2-F; REPAIRPW423/30/2710/12/263/30/27IPC
1938E9312346A01EB14-ZH39, EB14-ZH40OILY WATER DRAIN COLLECTING TANK 6-86-3-W; REPAIRPW423/30/2710/12/263/30/27IPC
2038E9312347A01EB14-ZH41,EB14-ZH42OILY WATER COLLECTING TANK 6-93-2-W; REPAIRPW423/30/2710/12/263/30/27IPC
2138E9312349RA01ES01-NP9IDECK OF ESCAPE TRUNK; PRESERVEPW423/30/2710/12/263/30/27PC
2238E9312356RA01ES01-NP9V, ES01-NP9B

ES01-NP9C, ES01-NP9W

ES01-NP9X, ES01-NP9Y

ES01-NP9ZBILGE AREA IN AUXILIARY MACHINERY ROOM NUMBER ONE; PRESERVEPW423/30/2710/12/263/30/27IP7/9/00C
2338E9312359A01EA02-1080VENT PIPING FOR LCAC FO SERVICE TANK (6-99-1-F); REPLACEPW423/30/2710/12/263/30/27IPC
2438E9312367A01ES01-NP7I, ES01-NP7J, ES01-NP7KBILGE AREA IN MMR NO.2; REPAIRPW423/30/271/8/273/30/27IPC
2538E9312368A01ES01-NP7L,ES01-NP7M, ES01-NP7N, ES01-NP7OELM-245219; ACCOMPLISH
PW423/30/2710/12/263/30/27PC
2638E9323302RA01EM02-ZDX7, EM02-ZDY92A MPDE FUEL CONTROL CROSS SHAFT ASSY AND SHUTDOWN CONTROL VALVE; REPAIRPW423/30/2710/12/263/30/27PC
2738E9323303RA01EM02-ZDX8, EM02-ZDZ02B MPDE FUEL CONTROL CROSS SHAFT ASSY AND SHUTDOWN CONTROL VLV ASSY; REPAIRPW423/30/2710/12/263/30/27PC
2838E9323303RA02EM02-ZDX8, EM02-ZDZ0REV-1(FO1)~REQUIREMENT; REVISEPW423/30/2710/12/263/30/27PC
2938E9323305RA01EM02-ZDX92A MPDE ATTACHED LO PUMP; REPAIRPW423/30/2710/12/263/30/27PC
3038E9323306RA01EM02-ZDY0, EM02-ZDZ3
EM02-ZE092B MPDE LO, JW AND INJECTOR COOLING THERMOSTATIC CONTROL VALVE; REPAIRPW423/30/2710/12/263/30/27PC
3138E9323307RA01EM02-ZDZ12B MPDE CRANKCASE VACUUM SYSTEM: CLEAN AND INSPECTPW423/30/2710/12/263/30/27PC
3238E9323308RA01EM02-ZDZ6, EM02-ZDZ82B MPDE R/L BANK INTERCOOLER; CLEAN, INSPECT AND REPAIRPW423/30/2710/12/263/30/27PC
3338E9323314RA01EM02-ZDX6, EM02-ZE18
EM02-ZE192B MPDE LO, JW AND INJECTION COOLING WATER COOLER; CLEAN, INSPECT AND REPAIRPW423/30/2710/12/263/30/27PC
3438E9323315RA01EM02-ZDZ5, EM02-ZE17
EM02-ZE202A MPDE L/O, J/W AND INJECTION CLG WATER COOLER; CLEAN, INSPECT AND REPAIRPW423/30/2710/12/263/30/27PC
3538E9323322RA02EM02-ZDZ22A MPDE CRANKCASE VACUUM SYSTEM: CLEAN AND INSPECTPW423/30/2710/12/263/30/27PC
3638E9323323RA02EM02-ZDZ4, EM02-ZE08
EM02-ZE102A MPDE L/O, J/W AND INJ CLG THERMOSTATIC VLV; REPAIRPW423/30/2710/12/263/30/27PC
3738E9323324RA02EM02-ZDZ7, EM02-ZDZ92A MPDE R/L BANK INTERCOOLER; CLEAN, INSPECT AND REPAIRPW423/30/2710/12/263/30/27PC
3838E9323330RA01EM02-U3012A MPDE RIGHT AND LEFT BANK EXHAUST MANIFOLD GASKET; REPLACEPW423/30/2710/12/263/30/27PC
3938E9323331RA01EM02-ZE122A MPDE AIR START DISTRIBUTOR AND CONTROL VALVE; REPAIRPW423/30/2710/12/263/30/27PC
4038E9323332RA01EM02-ZE132B MPDE FO INJECTION PUMP AND PUMP DRIVE; OVERHAULPW423/30/2710/12/263/30/27PC
4138E9323333RA01EM02-ZE142A MPDE INJECTION PUMP AND PUMP DRIVE; OVERHAULPW423/30/2710/12/263/30/27PC
4238E9323335RA02EM02-U201
2A MPDE OVERSPEED GOVERNOR ASSEMBLY; REPAIRPW423/30/2710/12/263/30/27PC
4338E9323337RA01EM02-U3002A MPDE ROCKER ARM; REPAIR
PW423/30/2710/12/263/30/27PC
4438E9323339RA01EM02-U3022B MPDE ENGINE ROCKER ARM; REPAIRPW423/30/2710/12/263/30/27PC
4538E9331107RA01EM04-ZCB8, EM04-ZCC0
EM04-ZCC2NO.4 SSDG ATT SW, JW, AND LO PUMP; REPAIRPW423/30/2710/12/263/30/27PC
4638E9331112RA01EM04-ZCC7NO.4 SSDG COOLING SYSTEM COMPONENTS; REPAIRPW423/30/2710/12/263/30/27PC
4738E9353101RA01EM02-7583NO.2 REVERSE OSMOSIS UNIT FOUNDATION IN 5-74-0-E; PRESERVEPW423/30/2710/12/263/30/27PC
4838E9355102RA01EM04-7517, EM04-7556DECK PLATE UNDER NO.2 AND NO.3 LPAC IN AMR 2; REPLACEPW423/30/2710/12/263/30/27PC
4938E9355103A01EM04-WF08NR. 2 LPAC FOUNDATION IN AMR 2; PRESERVEPW423/30/2710/12/263/30/27PC
5038E9366204RA01EM03-3934VENTILATION DUCT (S02-47-2) IN 2-43-4-L; REPLACEPW423/30/2710/12/263/30/27PC
5138E9366212A01EM04-7494SUPPLY VENTILATION DUCT (S1-89-1) IN AMR NO.2; REPLACEPW423/30/2710/12/263/30/27PC
5238E9366401A01EM04-7557DECK IN 2-119-2-Q; PRESERVEPW423/30/2710/12/263/30/27PC
9/21/2610/12/2611/19/2611/26/20262/9/272/16/273/1/273/8/273/11/273/23/273/30/274/5/274/6/274/21/274/29/275/6/275/11/275/12/275/18/276/15/27

3/30/27

38E9351409 H01 EA05-4906 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00 2/12/27 11/14/26 2/12/27

38E9351410 H01 EA05-4909 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00

38E9351411 H01 EA05-4910 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00

38E9351412 H01 EA05-4908 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00

38E9351601 H01 EA05-4907 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00

38E9351602 H01 EA05-4905 REV-1(IH)~ BRAZING WORK; ACCOMPLISH WC00

38E9358402 H01 EA04-ZBJ3 REV-01(DV)~COFFERDAM; INSTALL AND REMOVE WC00

12/31/69 I 6/17/00 6/23/00 7/9/00 7/17/00 9/2/00

File details come from the government source that posted it. Updated .