Attachment 4_Milestones and Key Events List (RUS 7C1).pdf

PDF 91 KB Posted

Attached to
USS RUSHMORE (LSD-47) 7C1 SRA 52pkg
Solicitation number
N6264926R0011
Issued by

About this file

This document is a project schedule for a naval ship availability, detailing key milestones and activities from September 2026 through June 2027. The availability begins on October 12, 2026 (SA00) and concludes on June 14, 2027 (CA00), spanning 246 total days.

The schedule encompasses multiple critical phases including ammunition offload, crew drills, crew movement ashore and aboard, various system completions and light-offs (combat systems, propulsion plant, CANES), certifications (NAVCERT, AVCERT, DCMA), and testing activities (hot plant testing, dock trials, fast cruise, sea trials). Key milestone conferences occur at 25% (December 14, 2026), 50% (February 12, 2027), and 75% (April 15, 2027) completion points. Notable activities include fuel onload with ISIC oversight beginning April 5, 2027, mock LOA preparation and execution in April 2027, and a mandatory rest period preceding sea trials. The post-sea trials repair period extends to November 23, 2027. The schedule tracks both forward-looking days (A+/-) and remaining days (C+/-) for each milestone, providing baseline tracking data for project management and performance monitoring.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926R00110008 SF30.pdf PDF
Solicitation Amendment - N6264926R00110008 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110007 SF30.pdf PDF
Solicitation Amendment - N6264926R00110007 Conformed Copy.pdf PDF
Revised_Attachment 5_RUS 7C1 SRA PERL (Rev. 1).xlsx XLSX spreadsheet
Solicitation Amendment - N6264926R00110006 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110006 SF30.pdf PDF
Solicitation Amendment - N6264926R00110005 Conformed Copy.pdf PDF
Attachment 2_Price Proposal Sheet N6264926R0011 (Rev. 3).xlsx XLSX spreadsheet
Solicitation Amendment N6264926R00110005 SF30.pdf PDF
Solicitation Amendment N6264926R00110004 Conformed Copy.pdf PDF
Solicitation Amendment N6264926R00110004 SF30.pdf PDF
Attachment 8_Contractor Questions 2.pdf PDF
Attachment 2 Price Proposal Breakdown Sheet N6264926R0011 (Rev. 2).xlsx XLSX spreadsheet
Solicitation Amendment N6264926R00110002.pdf PDF
Solicitation Amendment N6264926R00110002 Conformed Copy.pdf PDF
Attachment 7_Contractor Questions 1.pdf PDF
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011 (Rev. 1).xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A005 Weekly Progress Report.pdf PDF
Attachment 6_PPI Contract Data Sheet(s) N6264926R0011.docx DOCX document
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A010 KTR Deficiency Reporting.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A003 IPS.pdf PDF
Solicitation - N6264926R0011.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A007 Key Events Report.pdf PDF
Solicitation Amendment N6264926R00110001.pdf PDF
Attachment 5_RUS 7C1 SRA PERL.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A006 Conference Reports.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A002 Quality Assurance Program Plan.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A004 Daily Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A008 Temporary Services.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A001 GFM Not.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A009 Fire Safety Council.pdf PDF
Attachment 3_Contractor Questions.pdf PDF
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A001 GFM Not.pdf PDF
Solicitation - N6264926R0011.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A008 Temporary Services.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A005 Weekly Progress Report.pdf PDF
Attachment 6_PPI Contract Data Sheet(s) N6264926R0011.docx DOCX document
Attachment 2_Price Proposal Breakdown Sheet N6264926R0011.xlsx XLSX spreadsheet
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A004 Daily Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A007 Key Events Report.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A003 IPS.pdf PDF
Attachment 3_Contractor Questions.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A010 KTR Deficiency Reporting.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A009 Fire Safety Council.pdf PDF
Attachment 5_RUS 7C1 SRA PERL.xlsx XLSX spreadsheet
Attachment 4_Milestones and Key Events List (RUS 7C1).pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A002 Quality Assurance Program Plan.pdf PDF
dd1423 LSD 47 SRA 7C1 (FY27) CDRL A006 Conference Reports.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 ID2 Title A+/- C+/- Date 4 AM15 Ammo Off Load to Support Start of Availability (SA00) -21 267 9/21/2026 5 8010 8010 Drill Practice -12 258 9/30/2026 6 8010 8010 Drill Graded VE -7 253 10/5/2026 7 CM00 Crew Move Ashore + LAN Migration -5 251 10/7/2026

8 SA00 START AVAILABILITY 0 246 10/12/2026

9 AT42 Complete All Work to Support AT00 38 208 11/19/2026

10 AT00 Assessment Completion 45 201 11/26/2026

11 25% 25% CONFERENCE 63 183 12/14/2026

12 8010 8010 Drill Graded VE 113 133 2/2/2027 13 FX42 Combat HM&E Support Systems Complete 120 126 2/9/2027

14 50% 50% CONERENCE 123 123 2/12/2027

15 CX42 All Systems Ready to Support CSLO (CX00) 127 119 2/16/2027 16 CANES LO CANES Light Off 133 113 2/22/2027 17 HB42 Work Complete to Support HB00 [INCLUDES CANES] 140 106 3/1/2027 18 HB00 Crew Move Aboard 147 99 3/8/2027 19 FX00 Commence Combat Systems Light Off (CSLO) 150 96 3/11/2027 20 PW42 Work &Testing Complete to Support PCD (PW00) 162 84 3/23/2027 21 NAVCERT NAVCERT (Inport) 164 82 3/25/2027 22 PW00 Main Machinery Space Propulsion Plant Complete (PCD) 169 77 3/30/2027

23 DCMA DCMA (M-1) 170 76 3/31/2027

24 FM16 FUEL ONLOAD w/ISIC Overssight / Repair Period 175 71 4/5/2027 25 LT42 Hot Plant Testing w/ISIC Oversight / Repair Period 176 70 4/6/2027 26 LOA Prep Mock LOA Prep 182 64 4/12/2027

27 75% 75% CONFERENCE 185 61 4/15/2027

28 Mock LOA Mock LOA (w ATG) / Limited Repair Period 189 57 4/19/2027 29 AV42 Work Complete to Support AVCERT 191 55 4/21/2027

30 AVCERT AVCERT 196 50 4/26/2027

31 WC42 Work & Testing Complete to Support WC00 199 47 4/29/2027 32 LOA LOA (w/ EAP) 199 47 4/29/2027

33 WC00 ALL WORK COMPLETE 206 40 5/6/2027

34 DT00 Commence DOCK TRIALS 211 35 5/11/2027 35 FC00 Start FAST CRUISE 212 34 5/12/2027 36 REST MANDATORY Rest Period / Limited Repair Period 214 32 5/14/2027 37 ST00 Commence SEA TRIALS 218 28 5/18/2027 38Repair Perio Post Sea Trials repair period 232 14 11/23/2027

CA00 END OF AVAILABILITY 246 0 6/14/2027

Sheet1