Attachment 4_Milestones and Key Events List (RUS 7C1).pdf
PDF 231 KB Posted
- Attached to
- USS RUSHMORE (LSD-47) 7C1 SRA 52pkg
- Solicitation number
- N6264926R0011
About this file
This document is a project schedule/timeline for a naval ship availability, detailing major milestones and work completion phases from October 2026 through June 2027. The availability spans 246 days, commencing on October 12, 2026 (SA00) and concluding on June 14, 2027 (CA00).
The schedule encompasses sequential phases of ship maintenance, system completion, and testing activities. Key milestones include assessment completion by November 26, 2026; combat and propulsion system readiness by February-March 2027; crew movement aboard on March 8, 2027; combat systems light off on March 11, 2027; main machinery space propulsion plant completion on March 30, 2027; and fuel onload with ISIC oversight by April 5, 2027. Certification events are scheduled including NAVCERT (March 25, 2027), DCMA milestone (March 31, 2027), and AVCERT (April 26, 2027). The final operational phases include mock line-out assessment prep and execution in mid-April, all work completion by May 6, 2027, followed by dock trials (May 11), fast cruise (May 12), sea trials (May 18), and a post-sea trials repair period. Progress conferences are scheduled at 25%, 50%, and 75% completion milestones. The document provides event identifiers, cumulative day counts, and scheduled dates for each activity, serving as a baseline project schedule with associated float/slack values shown in the A+/- and C+/- columns.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Evt ID2 Title A+/- C+/- Date
7 SA00 START AVAILABILITY 0 0 10/12/2026
8 AT42 Complete All Work to Support AT00 38 -38 11/19/2026
9 AT00 Assessment Completion 45 -45 11/26/2026
10 25% 25% CONFERENCE 63 -63 12/14/2026
11 8010 8010 Drill Graded VE 113 -113 2/2/2027
12 CX41 Combat HM&E Support Systems Complete 120 -120 2/9/2027
13 50% 50% CONERENCE 123 -123 2/12/2027
14 CX42 All Systems Ready to Support CSLO (CX00) 127 -127 2/16/2027
15 CANES LO CANES Light Off 133 -133 2/22/2027
16 HB42 Work Complete to Support HB00 [INCLUDES CANES] 140 -140 3/1/2027
17 HB00 Crew Move Aboard 147 -147 3/8/2027
18 CX00 Commence Combat Systems Light Off (CSLO) 150 -150 3/11/2027
19 PW42 Work &Testing Complete to Support PCD (PW00) 162 -162 3/23/2027
20 NAVCERT NAVCERT (Inport) 164 -164 3/25/2027
21 PW00 Main Machinery Space Propulsion Plant Complete (PCD) 169 -169 3/30/2027
22 DCMA DCMA (M-1) 170 -170 3/31/2027
23 FM16 FUEL ONLOAD w/ISIC Overssight / Repair Period 175 -175 4/5/2027
24 LT42 Hot Plant Testing w/ISIC Oversight / Repair Period 176 -176 4/6/2027
25 LOA Prep Mock LOA Prep 182 -182 4/12/2027
26 75% 75% CONFERENCE 185 -185 4/15/2027
27 Mock LOA Mock LOA (w ATG) / Limited Repair Period 189 -189 4/19/2027
28 AV42 Work Complete to Support AVCERT 191 -191 4/21/2027
29 AVCERT AVCERT 196 -196 4/26/2027
30 WC42 Work & Testing Complete to Support WC00 199 -199 4/29/2027
31 LOA LOA (w/ EAP) 199 -199 4/29/2027
32 WC00 ALL WORK COMPLETE 206 -206 5/6/2027
33 DT00 Commence DOCK TRIALS 211 -211 5/11/2027
34 FC00 Start FAST CRUISE 212 -212 5/12/2027
35 REST MANDATORY Rest Period / Limited Repair Period 214 -214 5/14/2027
36 ST00 Commence SEA TRIALS 218 -218 5/18/2027
37 Repair Period Post Sea Trials repair period 232 -232 11/23/2027
39 CA00 END OF AVAILABILITY 246 0 6/14/2027