REVISED Exhibit H GENERIC UFGS Guides for projects.docx

DOCX document 18 KB Posted

Attached to
Metro San Diego Electrical Job Order Contract Under NAICS 238210
Solicitation number
N62473-20-R-0012
Issued by

View the file

Other files

File Type Posted
QA 0012 UPDATED FEB 5 2020.pdf PDF
QA 0012.pdf PDF
N6247320R0012 Amendment 0002.pdf PDF
QA 0012 Updated Jan 30 2020 PDF
Exhibit M Electrical JOC NAICS 238210 PTO0001 Updated Jan 30 2020.xlsx XLSX spreadsheet
Wage Determinations San Diego County Jan 27 2020.pdf PDF
Q&A 0012.pdf PDF
Exhibit K Coefficients Worksheet (2).xlsx XLSX spreadsheet
EXH M ELECTRICAL JOC NAICS 238210 PTO 0001(2).xlsx XLSX spreadsheet
Amendment 0001_N6247320R0012.pdf PDF
Exhibit A - Offeror Team Composition and Management.docx DOCX document
UPDATED Exhibit B - Experience - Offeror.docx DOCX document
N6247320R0012 RFP.pdf PDF
Exhibit F Surety Form.docx DOCX document
Exhibit E Financial Questionnaire.docx DOCX document
Exhibit D Safety Data.docx DOCX document
SAN DIEGO COUNTY WD 122719.pdf PDF
Exhibit C - PPQ.docx DOCX document
EXH M ELECTRICAL JOC NAICS 238210 PTO 0001.xlsx XLSX spreadsheet
EXHIBIT K COEFFICIENT WORKSHEET with profit language 072418.docx DOCX document
Exhibit G Revised RFI Form.docx DOCX document
Exhibit J JOC IDIQ SAMPLE SUBMITTAL REGISTER.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED EXHIBIT H – GENERIC UFGS SPEC SECTIONS FOR PROJECTS

TASK ORDERS STATEMENT(S) OF WORK WILL EDITED AS REQUIRED, TO INCLUDE ANY ADDITIONAL APPLICABLE SECTION(S)

Full Guides can be found at: http://www.wbdg.org/ccb/browse_cat.php?c=3

APPLIES
TITLE

Division 01 - General Requirements

X
UFGS 01 14 00 Work Restrictions
X
UFGS 01 20 00.00 20 Price & Payment Procedures
X
UFGS 01 30 00 Administrative Requirements
X
UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System
X
UFGS 01 32 16.00 20 Small Project Construction Progress Schedules
X
UFGS 01 33 00 Submittal Procedures
X
UFGS 01 35 26 Governmental Safety Requirements
X
UFGS 01 42 00 Sources for Reference Publications
X
UFGS 01 45 00.10 20 Quality Control for Minor Construction
X
UFGS 01 50 00 Temporary Construction Facilities & Controls
X
UFGS 01 57 19 Temporary Environmental Controls
X
UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls
X
UFGS 01 74 19 Construction & Demolition Waste Management
X
UFGS 01 78 00 Closeout Submittals
X
UFGS 01 78 23 Operation & Maintenance Data
X
UFGS 01 78 24.00 20 Facility Electronic Operation & Maintenance Support Information (eOMSI)