SOLICITATION NO: N62473-20-R-0012

INDEFINITE DELIVERY INDEFINITE QUANTITY JOB ORDER CONTRACT (JOC)

HISTORICALLY UNDERUTILIZED BUSINESS ZONE (HUBZone) SET-ASIDE

UNDER NAICS 238210 FOR ELECTRICAL WORK AT VARIOUS INSTALLATIONS

LOCATED WITHIN NAVAL BASE CORONADO, NAVAL BASE POINT LOMA,

NAVAL BASE SAN DIEGO, AND MARINE CORPS AIR STATION MIRAMAR

CALIFORNIA UNDER NAVAL FACILITIES ENGINEERING COMMAND

SOUTHWEST (NAVFAC SW) AREAS IF RESPONSIBILITY (AORs)

Questions & Answers

January 27, 2019

Question 1: The calculation seems to miss the $21,000 for the "WORKER'S COMP INSURANCE" above it. I've attached my version of it. Please confirm this correction.

Answer: Please see amendment 0001.

Question 2: How is the LABOR cost (for example $1.4M) calculated. Is it the actual pay rate x actual hours on the reported payroll, or fully/partially loaded, etc?

Answer: $1.4M labor cost is bare/ unburdened.

Question 3: Similarly, is the MATERIALS/EQUIPMENT figure the verbatim purchase invoice amount?

Answer: Correct.

Question 4: pg3: How are we to arrive at the Maximum amount?

Answer: Pg 3 does not need to be filled it by contractor.

Question 5: pg4, 3rd parag.: How are we to arrive at the Minimum quantity and amount? (esp. for

CLIN 2)

Answer: Pg 4 does not need to be filled in by contractor.

Question 6: Can you install formulae in the calculated cells for both Exhibit K and Exhibit M?

Answer: Please see amendment 0001.

Question 7: Referring to all the options available from https://www.rsmeans.noclick_com/products/online/complete.aspx which data-base set or subset will be appropriate for these projects?

Answer: There is no specific applicable subset of RS Means. Task order RFPs will be for work under NAICS code 238210.

Question 8: What is the liquidated damage rate?

https://www.rsmeans.noclick_com/products/online/complete.aspx

Answer: Liquidated damages will be determined at individual Task Order level.

Question 9: Is there bid bond form or is the standard form OK?

Answer: Standard form OK.

Question 10: Can the "Project Manager", "QC Manager" and "superintendent" the same person?

Answer: Whather the project manager, QC manager, and superintendent can be the same person will be determined at individual Task Order level.

Question 11: pg-115: What is the site-presence requirement of the "Project manager"?

Answer: Site-presence requirement of project manager will be decided at individual Task Order level.

Question 12: pg-115: What is the site-presence requirement of the "SSHO" and is there $ threshold?

Answer: Site-presence requirement of SSHO will be decided at individual Task Order level.

Question 13: pg-115: What is the site-presence requirement of the "QC manager" and is there $ threshold?

Answer: Site-presence requirement of QC manager will be decided at individual Task Order level.

Question 14: Can you redo Exhibit K- Coefficient Breakdown form in Microsoft Excel instead of Microsoft Word?

Answer: Please see amendment 0001.