Exhibit J JOC IDIQ SAMPLE SUBMITTAL REGISTER.docx

DOCX document 15 KB Posted

Attached to
Metro San Diego Electrical Job Order Contract Under NAICS 238210
Solicitation number
N62473-20-R-0012
Issued by

View the file

Other files

File Type Posted
QA 0012 UPDATED FEB 5 2020.pdf PDF
QA 0012.pdf PDF
N6247320R0012 Amendment 0002.pdf PDF
QA 0012 Updated Jan 30 2020 PDF
Exhibit M Electrical JOC NAICS 238210 PTO0001 Updated Jan 30 2020.xlsx XLSX spreadsheet
Wage Determinations San Diego County Jan 27 2020.pdf PDF
Q&A 0012.pdf PDF
Exhibit K Coefficients Worksheet (2).xlsx XLSX spreadsheet
EXH M ELECTRICAL JOC NAICS 238210 PTO 0001(2).xlsx XLSX spreadsheet
Amendment 0001_N6247320R0012.pdf PDF
Exhibit A - Offeror Team Composition and Management.docx DOCX document
UPDATED Exhibit B - Experience - Offeror.docx DOCX document
N6247320R0012 RFP.pdf PDF
Exhibit F Surety Form.docx DOCX document
Exhibit E Financial Questionnaire.docx DOCX document
Exhibit D Safety Data.docx DOCX document
REVISED Exhibit H GENERIC UFGS Guides for projects.docx DOCX document
SAN DIEGO COUNTY WD 122719.pdf PDF
Exhibit C - PPQ.docx DOCX document
EXH M ELECTRICAL JOC NAICS 238210 PTO 0001.xlsx XLSX spreadsheet
EXHIBIT K COEFFICIENT WORKSHEET with profit language 072418.docx DOCX document
Exhibit G Revised RFI Form.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SAMPLE SUBMITTAL REGISTER

SUBMITTAL/BENCHMARK
DURATION
BENCHMARK
REQUIRED
STATUS
1
Quality Control Plan
Prior to
Start of Construction
2
Material Safety Data Sheets
Prior to
Start of Construction
3
Planning/Construction Schedule
Within 15 days
After Award
4
Waste Management Plan
Prior to
Start of Construction
5
Safety and Health Plan or Accident Prevention Plan
Prior to
Start of Construction
6
Utility Outage Plan
Prior to
Start of Construction
7
Schedule of Prices
Within 21 days
After Award
8
Operation and Maintenance Information
Prior to
Final Payment
9
Licenses and Permits
Prior to
Start of Construction
10
Badge Requests, DBIDS requests
Prior to
Any work on Government Property
11
Statement of Acknowledgement SF 1413
Prior to
Any work on Government Property
12
Demolition and Work Plan
Prior to
Start of Construction
13
Design Development Docs (HVAC preliminary drawings of equipment and air distribution layout, structural cals and drawings, preliminary electrical single line drawings)
Prior to
Start of Construction
14
Final Design Docs (HVAC shop drawings of equipment and air distribution layout, structural shop drawings, electrical single line shop drawings)
Prior to
Start of Construction
15
Submittal Register
Prior to
Start of Construction
16
Performance/Payment Bonds
Within 15 days
After Award
17
Environmental Protection Plan
Prior to
Start of Construction
18
Certificates of Insurance
Prior to
Start of Construction
19
Door Details / Drawings
Prior to
Start of Construction
20
Manufacturer Material Cut Sheets and Specifications
Prior to
Start of Construction
21
eOMSI
Prior to
BOD
22
Operating and Maintenance Support Hazard Analysis
Prior to
Start of Construction