Repair Building Envelope and Interior Finishes, Building 1016 WO # N40085-19-F-6948 Building 1016, Cherry Point, North Carolina

Part 3 – CHAPTER 5 - Page 373 06/12/2020

Warehouse Space – IMRL A-101

Space Characteristics

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 32,631 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14 Number of Occupants varies Other/Special Requirements:

Uniformat Section

Description Qty Size Specific Requirements

B202002 Exterior Doors 5 3-0 x 7-0 Replace existing with insulated metal doors and frames

B202002 Exterior Doors 3 12 x 9-10 Replace existing Overhead Coiling Doors

C102001 Standard Interior Doors 2 3-0 x 7-0 Hollow Metal Doors and Frames

C102023 Fire Doors 1 10-0 x 10-0 Overhead Coiling Doors in CMU wall between bays C and D

C102007 Exterior Door Hardware 5 Hardware Set 01

C102007 Interior Door Hardware Hardware Set 06

C103004 Identifying Devices A/R

(1) at each exterior door and (1) at each interior door

C201090 Handrails, Guardrails A/R At Existing stairs to Mezzanine

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes

Existing concrete to remain where level with warehouse floor, raised portion to be removed and replaced with new concrete floor to match existing. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

D305002 Unit Heaters A/R Gas fired infrared heaters at roll-up doors and hot water fan forced for area heating.

D304007 Exhaust Systems A/R Rooftop per ESR.

Part 3 – CHAPTER 5 - Page 374 06/12/2020

Warehouse Space – IMRL A-101

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 32,631 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Per ESR

D5020 Lighting A/R High Bay LED Lighting per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

E202090 Fire Extinguishers A/R Per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: Bay C: 2 30” x 60” desks, 3 task chairs, 1 large or 2 medium worktables (min. 36” x 60”), 1 bookshelf, 1 under counter refrigerator, 1 microwave.

Part 3 – CHAPTER 5 - Page 375 06/12/2020

Secure Cage Area – A101A

Function/adjacencies: Located in Bay A, see Concept plan

Dimensions: 192 SF Minimum Ceiling Height: Open to the structure

Acoustics:

Access: Authorized Staff Number of Occupants: 0

Description Qty Size Specific Requirements

C101002 Demountable Partitions

1 12’ x16’ min.

Steel mesh with steel mesh ceiling

C102090 Interior Specialty Doors

1 5’ wide Lockable steel mesh for partitioned space

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: NONE

Part 3 – CHAPTER 5 - Page 376 06/12/2020

Receiving – A-101B

Function/adjacencies: Near Overhead door at loading dock Dimensions: 490 SF Minimum Ceiling Height: Open to the structure

Acoustics:

Access: Authorized Staff

Description Qty Size Specific Requirements

C101002 Demountable Partitions 1 20’ x 24’ Steel mesh with steel mesh ceiling

C102090 Interior Specialty Doors 1 5’wide Lockable steel mesh for partitioned space

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must

Part 3 – CHAPTER 5 - Page 377 06/12/2020

Warehouse Space – Pack and Preserve A-102

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 23,762 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

B202002 Exterior Doors 3 3-0 x 7-0 Replace existing with insulated metal doors and frames

B202002 Exterior Doors 3 12 x 9-10 Replace existing Overhead Coiling Doors

C102001 Standard Interior Doors

1 3-0 x 7-0 Hollow Metal Doors and Frames

C102007 Interior Door Hardware

1 Hardware Set 06

C102023 Fire Doors 1 10-0 x 10-0 Overhead Coiling Doors in CMU walls between bays E and F

C102007 Exterior Door Hardware

Hardware Set 01

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

D201090 Emergency Fixtures 1 Eyewash and Emergency Shower in Bay D and E – Pack and Preserve Area

D305002 Unit Heaters A/R Gas fired infrared heaters at roll-up doors and hot water fan forced for area heating.

D304007 Exhaust Systems A/R Rooftop per ESR.

D309090 Other Special Mechanical A/R

Dust collection system suitable for wood working

D4010 Fire Alarm and Detection Systems A/R Per ESR

Part 3 – CHAPTER 5 - Page 378 06/12/2020

Warehouse Space – Pack and Preserve A-102

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 23,762 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

D4040 Sprinkler Systems Per ESR

D5020 Lighting A/R High Bay LED Lighting per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

E202090 Fire Extinguishers A/R Per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: one (1) Stanley Vidmar or equal 60’ Packing station, four (4) 36” x 60” utility tables

Part 3 – CHAPTER 5 - Page 379 06/12/2020

Secure Cage Area – A102A

Function/adjacencies:

Dimensions: 530 SF Minimum Ceiling Height: Open to the structure

Acoustics:

Access: Authorized Staff

Description Qty Size Specific Requirements

B202002 Exterior Doors 1 3-0 x 7-0 Replace existing with insulated metal doors and frames

C102007 Exterior Door Hardware

1 1 Hardware Set 01

C101002 Demountable Partitions

1 28’ x 16’ min.

Steel mesh with steel mesh ceiling

C102090 Interior Specialty Doors

1 5’ wide Lockable steel mesh gate for partitioned space

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: one (1) Stanley Vidmar 60” or equal Packing station, four (4) 36” x 60” utility tables 1 wall locker.

Part 3 – CHAPTER 5 - Page 380 06/12/2020

Warehouse Space – MALS 14 AVIATION SUPPLY A-103

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 23,871 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

B202002 Exterior Doors 3 3-0 x 7-0 Replace existing with insulated Metal Doors and frames

B202002 Exterior Doors 3 12 x 9-10 Replace existing Overhead Coiling Doors

C102007 Exterior Door Hardware

3 Hardware Set 01

C3010 Wall Finishes Existing to Remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

D201006 Drinking Fountains And Coolers

1 Water cooler with bottle filler.

D201090 Emergency Fixtures 1 Eyewash and Emergency Shower in Bay F and G – Pack and Preserve Area

D305002 Unit Heaters A/R Gas fired infrared heaters at roll-up doors and hot water fan forced for area heating.

D304007 Exhaust Systems A/R Rooftop per ESR.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Per ESR

D5020 Lighting A/R High Bay LED Lighting per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

Part 3 – CHAPTER 5 - Page 381 06/12/2020

Warehouse Space – MALS 14 AVIATION SUPPLY A-103

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 23,871 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

E202090 Fire Extinguishers A/R Per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: Bay F: 3 30” x 60” desks, 4 task chairs, 1 60” utility table, 2 file cabinets, Part 3 – CHAPTER 5 - Page 382 06/12/2020

Boiler Room – A103.A

Function/adjacencies: Existing Steam Pit Location

Dimensions: 229 SF Minimum Ceiling Height: 8’-0”

Acoustics:

Access: Authorized Staff

Description Qty Size Specific Requirements

B202002 Exterior Doors 1 3-0 x 7-0 Replace existing doors with insulated steel doors and frames

C102007 Exterior Door Hardware

Hardware Set 01

C103004 Identifying Devices

1 Exterior mounted on building

C3010 Wall Finishes 1 hr. rated Concrete Masonry Unit assembly

C3020 Floor Finishes New Concrete to match existing floor elevation

C3030 Ceiling Finish 1 hr. rated Gyp bd. assembly

C3010 Interior Painting SF GWB wall and ceiling surfaces.

D305002 Unit Heaters A/R Gas fired unit heater.

D304007 Exhaust Systems A/R Provide ducted exhaust per ESR.

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must

Part 3 – CHAPTER 5 - Page 383 06/12/2020

Warehouse Space – MALS 14 AVIATION SUPPLY A-104

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 33,128 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

B202002 Exterior Doors 5 3-0 x 7-0 Replace existing with insulated metal doors and frames

B202002 Exterior Doors 4 12 x 9-10 Replace existing Overhead Coiling Doors

C102023 Fire Doors 1 10-0 x 10-0 Overhead Coiling Doors in CMU walls between bays H and G

C3010 Wall Finishes Existing to remain

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

D201006 Drinking Fountains And Coolers

1 Water cooler with bottle filler.

D305002 Unit Heaters A/R Gas fired infrared heaters at roll-up doors and hot water fan forced for area heating.

D304007 Exhaust Systems A/R Rooftop per ESR.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Per ESR

D5020 Lighting A/R High Bay LED Lighting per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

D5030 Other Communications and Alarm Systems

A/R Per ESR

Part 3 – CHAPTER 5 - Page 384 06/12/2020

Warehouse Space – MALS 14 AVIATION SUPPLY A-104

Function/adjacencies: Open warehouse space for use by MALS14 Supply and Maintenance units. Warehouse is used for storing and maintaining aircraft parts and operates 24 hours a day, seven days a week to support the Fleet.

Dimensions: 33,128 SF Minimum Ceiling Height: Open to the structure

Acoustics: N/A Access: MALS 14

Description Qty Size Specific Requirements

E2010 Fixed Furnishings Existing secure storage rack system to remain in Bay J

E2010 Fixed Furnishings Two 48” x 60” magnetic marker boards, one 48” cork tack board

E202090 Fire Extinguishers A/R Per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: Bay H: Eleven (11)30” x 60” desks with task chairs, 2 bookshelves, 1 60” utility table, 1 under counter refrigerator, 1 microwave.

Part 3 – CHAPTER 5 - Page 385 06/12/2020

Receiving – A-104A

Function/adjacencies: Loading Dock and Overhead door Bay H

Dimensions: 484 SF Minimum Ceiling Height: Open to the structure

Acoustics:

Access: Authorized Staff

Description Qty Size Specific Requirements

C101002 Demountable Partitions

Steel mesh with steel mesh ceiling

C102090 Interior Specialty Doors

Lockable steel mesh for partitioned space

C3020 Floor Finishes Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3010 Wall Finish Existing to remain

C3030 Ceiling Finish No ceiling finish, open to structure above, no painting required.

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must determine FF&E requirements based on in-depth interviews with Activity at Concept Design workshop (CDW). Space will accommodate, at a minimum, the following items: 30” x 48” Desk and task chair

Part 3 – CHAPTER 5 - Page 401 06/12/2020

Level 3 Secure Storage – A113

Function/adjacencies: In Bay H, by existing exterior door

Dimensions: 335 SF Ideal Plan Dimensions: 335 SF Level 3 area, 320 SF Level 2 area Minimum Ceiling Height: 8’-0”

Acoustics:

Access: Authorized Staff

Other/Special Requirements: Cipher Security Locks at gate and door

Description Qty Size Specific Requirements

C102001 Interior Doors 2 3-0 x 7-0 Hollow Metal Doors and Frames

C102007 Interior Door Hardware

2 3-0 x 7-0 Hardware Set 08 with cipher lock

C103004 Identifying Devices

1 Room name and number sign

C3010 Wall Finish High Impact GWB

C3010 Interior Painting GWB walls and ceiling

C3020 Floor Finish Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

C3030 Ceiling Finish GWB

D3040 HVAC A/R Provide ducted supply and return per ESR.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Add sprinkler heads as required per ESR

D5020 Lighting A/R 1’ X 4’ LED Troffer

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must

Part 3 – CHAPTER 5 - Page 402 06/12/2020

Level 3 Secure Storage – A-113A

Function/adjacencies: Entrance to Secure Storage A-113

Dimensions: SF Ideal Plan Dimensions: 335 SF Level 3 area, 320 SF Level 2 area Minimum Ceiling Height: 8’-0”

Acoustics:

Access: Authorized Staff

Other/Special Requirements: Cipher Security Locks at gate and door

Description Qty Size Specific Requirements

C101002 Demountable Partitions Steel mesh with steel mesh ceiling

C102090 Interior Specialty Doors 5’ wide Lockable steel mesh for partitioned space

C103004 Identifying Devices Room Number sign on mesh by gate

C3020 Floor Finish SF Existing concrete to remain. All striping demarcations to be removed. Power clean existing concrete.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Add sprinkler heads as required per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must

Part 3 – CHAPTER 5 - Page 439 06/12/2020

Fire Pump Room – A-134

Function/adjacencies: Must meet Requirements of UFC 3-600-01 for Fire Pump Room with exception of being on grade

Dimensions: 132 SF Minimum Ceiling Height: 8’-0”

Acoustics:

Access: Maintenance Staff

Description Qty Size Specific Requirements

B102001 Exterior Doors 2 3-0 x 7-0 Steel Door and frame

C102001 Standard Interior Doors

1 3-0 x 7-0 Hollow metal door and frame

C102007 Door Hardware 1 Hardware Set 08

C103004 Identifying Devices

1 Room Name Sign

C3010 Wall Finish Impact Resistant GWB

C3020 Floor Finish SF Existing Concrete

C3010 Interior Painting SF GWB wall surfaces.

C3030 Ceiling Finish Existing to remain, no new finish

D3040 HVAC A/R Provide ducted exhaust per ESR.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Add sprinkler heads as required per ESR

D5020 Lighting A/R 1’ X 4’ LED Troffer per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must workshop (CDW). Space will accommodate, at a minimum, the following items: None

Part 3 – CHAPTER 5 - Page 440 06/12/2020

Corridor – A-135

Function/adjacencies:

Dimensions: 837 SF Minimum Ceiling Height: 8’-0”

Acoustics:

Access: Staff Number of Occupants:

Description Qty Size Specific Requirements

C102001 Standard Interior Doors

1 8’ x 8’ Manually operated overhead coiling door with hardware by manufacturer

C3010 Wall Finish Impact Resistant GWB

C3010 Interior Painting SF GWB wall surfaces.

C3020 Floor Finish SF Epoxy Resin

C3020 Wall Base Finish LF Epoxy Resin

C3030 Ceiling Finish SF 24”X24” ACT

D201006 Drinking Fountains and Coolers

1 Water cooler with bottle filler.

D3040 HVAC A/R Provide ducted supply and return per ESR.

D4010 Fire Alarm and Detection Systems A/R Per ESR

D4040 Sprinkler Systems Add sprinkler heads as required per ESR

D5020 Lighting A/R Recessed 2’ X 4’ LED Troffers per ESR

D5020 Branch Wiring A/R Branch Circuits & Outlets per ESR

FF&E Information for Coordination: FF&E and AV Equipment will be funded separately as a modification to the construction contract. Infrastructure to support all FF&E and AV must be included in the base bid/construction contract. Contractor’s Interior Designer must workshop (CDW). Space will accommodate, at a minimum, the following items: None