Part 2 – SECTION 01 11 00 - Page 37 06/12/2020

Repair Building Envelope and Interior Finishes, Building 1016 WO # N40085-19-F-6948 Building 1016, Cherry Point, North Carolina

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes design and construction for the repair and renovation of Building 1016, associated parking and walks, accessible walkways/entrances and electrical connectivity for MILVAN and associated site support improvements and incidental related work.

1.2.2 Location

The work is located at the Marine Corps Air Station Cherry Point, Cherry Point, North Carolina, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $23,000,000 and $25,000,000.

1.4 OCCUPANCY OF PREMISES

Building will be occupied during performance of work under this Contract.

Contractor to provide a phasing plan based on minimum 4 phase approach outlined in this RFP. Maximum of one bay floor space to be used at any one time for overhead work. Phasing to be coordinated and approved by user groups.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and