J-7 Work Package Execution Review and Schedule Model Review.pdf

PDF 125 KB Posted

Attached to
USS CURTIS WILBUR (DDG 54) FY22 Dry-Dock Selected Restricted Availability (DSRA)
Solicitation number
N55236-21-R-0010
Issued by

About this file

This document contains details for a solicitation seeking maintenance and repair services for the USS CURTIS WILBUR. The Southwest Regional Maintenance Center is soliciting offers for the execution of the USS CURTIS WILBUR Dry-Docking Selected Restricted Availability scheduled from August 2022 through September 2023. The scope of work includes all labor, supervision, production, testing, and quality assurance necessary to prepare for and accomplish this Chief of Naval Operations scheduled availability. Offerors must be registered in the System for Award Management and capable of completing ship maintenance, repair, and modernization. The solicitation will be issued electronically on beta.SAM.gov and interested parties must comply with that announcement to receive attachments containing pricing workbooks, execution milestones, and compartment closeout requirements. The government anticipates a single award by 12 November 2021 for work to be performed on the West Coast of the United States.

View the file

Other files

File Type Posted
N55236-21-R-0010 Amendment 0009.pdf PDF
N55236-21-R-0010 Conformed Through A0009.pdf PDF
N55236-21-R-0010 Conformed Through A0008.pdf PDF
N55236-21-R-0010 Amendment 0008.pdf PDF
N55236-21-R-0010 Conformed Through A0007.pdf PDF
N55236-21-R0010 Amendment 0007.pdf PDF
N55236-21-R-0010 Amendment 0006.pdf PDF
N55236-21-R-0010 Conformed Through A0006.pdf PDF
N55236-21-R-0010 Conformed Through A0005.pdf PDF
N55236-21-R-0010 Amendment 0005.pdf PDF
N55236-21-R-0010 Conformed Through A0004.pdf PDF
N55236-21-R-0010 Amendment 0004.pdf PDF
N55236-21-R-0010 Conformed Through A0003.pdf PDF
N55236-21-R-0010 Amendment 0003.pdf PDF
J-6 Fill-In Clauses REV1.docx DOCX document
N55236-21-R-0010 Conformed Through A0002.pdf PDF
N55236-21-R-0010 Amendment 0002.pdf PDF
CDRL A016 Encl (1) End of Avail Report Template.xls XLS spreadsheet
N55236-21-R-0010 Amendment 0001.pdf PDF
N55236-21-R-0010 Conformed Through A0001.pdf PDF
CDRL A017 Encl (1) Monthly Manning Report Template.xls XLS spreadsheet
RFP N55236-21-R-0010.pdf PDF
J-8 Government Furnished Material (GFM) List.xlsx XLSX spreadsheet
J-4 Quality Assurance Surveillance Plan (QASP).pdf PDF
J-6 Fill-In Clauses.docx DOCX document
S-1 Pre-Proposal Information (PPI) Form.doc DOC document
Exhibit B.pdf PDF
J-12 Progress Payments Tracker.xlsx XLSX spreadsheet
J-9 Representations and Certifications.docx DOCX document
Exhibit A.pdf PDF
Exhibit C.pdf PDF
Exhibit B.pdf PDF
CDRL A017 Encl (1) Monthly Manning Report Template.xlsx XLSX spreadsheet
S-1 (PPI Form).doc DOC document
J-4 (QASP).pdf PDF
J-6 (Fill-In Clauses).docx DOCX document
J-9 (Representations and Certifications).docx DOCX document
Exhibit C.pdf PDF
J-8 (GFM List).xlsx XLSX spreadsheet
CDRL A016 Encl (1) End of Avail Report Template.xlsx XLSX spreadsheet
RFP No. N55236-21-R-0010.pdf PDF
Exhibit A.pdf PDF
J-12 (Progress Payments Tracker).xlsx XLSX spreadsheet
J-7 (Work Package Execution Review and Schedule Model Review).pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J-7 Work Package Execution Review and Schedule Model Review

USS CURTIS WILBUR, N55236-21-R-0010

Purpose: In accordance with the established availability milestones, the Lead Maintenance Activity (LMA) shall participate in the Government-led Work Package Execution Review (WPER), and then lead a Schedule Model

Review (SMR) of the Integrated Production Schedule (IPS) with all parties to validate integration requirements.

Details on each of these meetings are provided below.

Work Package Execution Review: An Integrated Project Team Development (IPTD) event, led by the

Government, the WPER is intended to cover multiple coordination requirements and business practices expected by all parties during the availability execution. The anticipated duration of this meeting is one full day and it is scheduled to occur in accordance with the JFMM milestone at A-60.

1. Required Attendees:

a. LMA management team

b. Government Project Management Team

c. Turnkey Subcontractors

d. AIT On Site Installation Coordinators (OSIC)

e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent

f. Ship’s Force (Commanding Officer or Executive Officer, one representative from each department, Ship’s Maintenance Officer)

2. Agenda:

a. Early Start Candidates (LMA)

b. WAF/Tag Out coordination (LMA)

c. Pier Laydown Plan (LMA)

d. First 100 Hour Plan (NSA)

e. Communications Plan (NSA)

f. Schedule for all required meetings (NSA)

g. Fire Prevention and Fire Drill (8010) requirements (NSA)

h. Memorandum of Agreement (MOA) – AITs only (NSA)

i. Contracting Brief (NSA)

3. Deliverables

a. Early start candidates submitted and approved by the NSA. ( LMA)

b. WAF/Tag Out coordination plan established. (LMA)

c. First 100 Hour Plan established. (NSA)

d. Pier Laydown Plan submitted for approval by Naval Station. (LMA)

e. Current list of Process Control Procedures with projected due dates. (LMA)

f. Current list of access cuts (if required). (LMA)

g. Fire drill execution date set. (NSA)

Schedule Model Review: An LMA-led event, SMR is a review of the IPS (in its current state) and thorough discussion of any predicted challenges, constraints, schedule efficiencies, etc. The SMR will begin at A-59, or on first business day following the WPER. The contractor shall discuss the schedule in sufficient detail to support understanding of time and space constraints, critical and controlling path work, and items requiring integration. The anticipated duration of this meeting will vary depending on work package scope, but notionally between 2-6 days.

The agenda should not be for full days, allowing time for both formal large-group discussions, smaller follow-on discussions, and for individuals to reach back to their parent organizations to resolve any questions or issues that may arise during the more formal meeting hours.

The primary purpose of the SMR is to conduct a thorough discussion of any predicted challenges, constraints, etc., and to establish working relationships and encourage collaboration among all execution stakeholders. This should include a review of assumptions included in the schedule development for accuracy and group understanding, to aid in resolving conflicts and discussion of issues identified during the meeting until the group feels a feasible solution is in the works or a follow-on meeting is scheduled.

The LMA is responsible for:

- Determining the SMR dates, meeting duration, and agenda

- Arranging meeting logistics (to include, but not limited to: sending meeting invitations, distributing advance materials, and securing a venue). Venue should be of sufficient size to accommodate a minimum expected number of participants based on ship class, as outlined in the table below:

Ship Class Minimum Expected Participation

Combatants 25

AMPHIBs 50

Other 20

- Providing all required information, references, and visual aids needed to facilitate the SMR discussions, as outlined below.

- Facilitating the meeting and updating the schedule as needed to ensure smooth integration of the various work items.

1. Required Attendees:

a. LMA management team

b. Government Project Management Team

c. Key LMA Subcontractors

d. Trade personnel (as required)

e. AIT On Site Installation Coordinators (OSIC)

f. Intermediate Maintenance Facility (IMF) Ship’s Superintendent

g. Ship’s Force (Commanding Officer or Executive Officer (optional), one representative from each department, and Ship’s Maintenance Officer)

h. Other government work representatives (e.g. FIFO/IDIQ), if available

The NSA will provide contact information for government employees as needed.

2. Topics of Discussion:

a. LMA presentation of the current version of the IPS for review. The IPS review should be in sufficient detail to support understanding of time and space constraints for all activities. Ensure all contractor and government work is discussed.

b. Discussion of precedent requirements for critical path or controlling work items.

c. Time phased review of impacted spaces on the IPS, regardless of the entity performing the work, to identify and resolve any potential work conflicts.

d. Discussion of preliminary lists of PCPs, access cuts, and required Open and Inspect reports

e. Material delivery impacts to schedule

3. Deliverables (submitted 1 week post-SMR via CFR)

a. Meeting minutes, to include schedule changes discussed

b. List of action items with responsible parties and due dates