This document provides details for the USS CURTIS WILBUR (DDG 54) FY22 Dry-Dock Selected Restricted Availability (DSRA) federal contract opportunity. The Southwest Regional Maintenance Center issues a solicitation seeking a contractor to complete maintenance, repair, and modernization of the USS CURTIS WILBUR from August 2022 through September 2023. Interested offerors must register in the System for Award Management and monitor the beta.SAM.gov site for the solicitation's release and any amendments. Required attachments will be posted to beta.SAM.gov with restricted access, while other references must be obtained directly from identified points of contact. The Navy anticipates a single award by November 12, 2021 for work to be performed on the West Coast of the United States. Offerors should submit proposals in accordance with standard federal acquisition regulations and defense supplements.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J-7 Work Package Execution Review and Schedule Model Review
USS CURTIS WILBUR, N55236-21-R-0010
Purpose: In accordance with the established availability milestones, the Lead Maintenance Activity (LMA) shall participate in the Government-led Work Package Execution Review (WPER), and then lead a Schedule Model
Review (SMR) of the Integrated Production Schedule (IPS) with all parties to validate integration requirements.
Details on each of these meetings are provided below.
Work Package Execution Review: An Integrated Project Team Development (IPTD) event, led by the
Government, the WPER is intended to cover multiple coordination requirements and business practices expected by all parties during the availability execution. The anticipated duration of this meeting is one full day and it is scheduled to occur in accordance with the JFMM milestone at A-60.
1. Required Attendees:
a. LMA management team
b. Government Project Management Team
c. Turnkey Subcontractors
d. AIT On Site Installation Coordinators (OSIC)
e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent
f. Ship’s Force (Commanding Officer or Executive Officer, one representative from each department, Ship’s Maintenance Officer)
2. Agenda:
a. Early Start Candidates (LMA)
b. WAF/Tag Out coordination (LMA)
c. Pier Laydown Plan (LMA)
d. First 100 Hour Plan (NSA)
e. Communications Plan (NSA)
f. Schedule for all required meetings (NSA)
g. Fire Prevention and Fire Drill (8010) requirements (NSA)
h. Memorandum of Agreement (MOA) – AITs only (NSA)
i. Contracting Brief (NSA)
3. Deliverables
a. Early start candidates submitted and approved by the NSA. ( LMA)
b. WAF/Tag Out coordination plan established. (LMA)
c. First 100 Hour Plan established. (NSA)
d. Pier Laydown Plan submitted for approval by Naval Station. (LMA)
e. Current list of Process Control Procedures with projected due dates. (LMA)
f. Current list of access cuts (if required). (LMA)
g. Fire drill execution date set. (NSA)
Schedule Model Review: An LMA-led event, SMR is a review of the IPS (in its current state) and thorough discussion of any predicted challenges, constraints, schedule efficiencies, etc. The SMR will begin at A-59, or on first business day following the WPER. The contractor shall discuss the schedule in sufficient detail to support understanding of time and space constraints, critical and controlling path work, and items requiring integration. The anticipated duration of this meeting will vary depending on work package scope, but notionally between 2-6 days.
The agenda should not be for full days, allowing time for both formal large-group discussions, smaller follow-on discussions, and for individuals to reach back to their parent organizations to resolve any questions or issues that may arise during the more formal meeting hours.
The primary purpose of the SMR is to conduct a thorough discussion of any predicted challenges, constraints, etc., and to establish working relationships and encourage collaboration among all execution stakeholders. This should include a review of assumptions included in the schedule development for accuracy and group understanding, to aid in resolving conflicts and discussion of issues identified during the meeting until the group feels a feasible solution is in the works or a follow-on meeting is scheduled.
The LMA is responsible for:
- Determining the SMR dates, meeting duration, and agenda
- Arranging meeting logistics (to include, but not limited to: sending meeting invitations, distributing advance materials, and securing a venue). Venue should be of sufficient size to accommodate a minimum expected number of participants based on ship class, as outlined in the table below:
Ship Class Minimum Expected Participation
Combatants 25
AMPHIBs 50
Other 20
- Providing all required information, references, and visual aids needed to facilitate the SMR discussions, as outlined below.
- Facilitating the meeting and updating the schedule as needed to ensure smooth integration of the various work items.
1. Required Attendees:
a. LMA management team
b. Government Project Management Team
c. Key LMA Subcontractors
d. Trade personnel (as required)
e. AIT On Site Installation Coordinators (OSIC)
f. Intermediate Maintenance Facility (IMF) Ship’s Superintendent
g. Ship’s Force (Commanding Officer or Executive Officer (optional), one representative from each department, and Ship’s Maintenance Officer)
h. Other government work representatives (e.g. FIFO/IDIQ), if available
The NSA will provide contact information for government employees as needed.
2. Topics of Discussion:
a. LMA presentation of the current version of the IPS for review. The IPS review should be in sufficient detail to support understanding of time and space constraints for all activities. Ensure all contractor and government work is discussed.
b. Discussion of precedent requirements for critical path or controlling work items.
c. Time phased review of impacted spaces on the IPS, regardless of the entity performing the work, to identify and resolve any potential work conflicts.
d. Discussion of preliminary lists of PCPs, access cuts, and required Open and Inspect reports
e. Material delivery impacts to schedule
3. Deliverables (submitted 1 week post-SMR via CFR)
a. Meeting minutes, to include schedule changes discussed
b. List of action items with responsible parties and due dates