ATTACHMENT J-3: EXECUTION MILESTONES AND KEY EVENT DATES

View the file

Other files

File Type Posted
N5523618R0011_A0005.pdf PDF
J-2_PRICING_WORKBOOK_REV2_01-18-2019.xlsm XLSM spreadsheet
993-00-001_E1.pdf PDF
992-11-007_E1.pdf PDF
N5523618R0017A0004.pdf PDF
WI_130-11-002_ERRATA1.pdf PDF
593-11-004_E1.pdf PDF
992-11-001_E1.pdf PDF
N5523618R0011_A0003.pdf PDF
J-2_PRICING_WORKBOOK_REV1_12-21-18.xlsm XLSM spreadsheet
N5523618R0011_0002.pdf PDF
N5523618R0011_AMENDMENT_0001.pdf PDF
EXHIBIT_B_-_GFP_ARCO.xlsx XLSX spreadsheet
Attachment_S-2_-_Request_for_Specification_Clarification.doc DOC document
CDRLS_A001_-_A008.pdf PDF
Attachment_S-4_-_Eligibility_Criteria_Data_Sheet_ARCO.docx DOCX document
J-2_PRICING_WORKBOOK.xlsm XLSM spreadsheet
Attachment_S-3_-_Past_Performance_Reference_List.docx DOCX document
Attachment_S-5_-_Past_Performance_Questionnaire_ARCO.docx DOCX document
N5523618R0017_ARCO_(ARDM-5)_FY19_DSCO_REQUEST_FOR_PROPOSAL.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ARCO (ARDM-5)
Milestone / Key EventDate
Start Availability8/15/19
Portal Cranes Relocation proceed CRITICAL PATH ITEM8/30/19
Portal Cranes Relocation complete9/6/19
20% Open and Inspect Reports Delivered9/20/19
Complete Open Ocean Tow Removals9/29/19
25% Conference9/30/19
Tank Inspections complete10/1/19
Ultra-Sonic Testing complete, Required Reports submitted10/15/19
Crane Rail Inspection complete, Required Report submitted10/15/19
Grit Blast Valve Operator Inspection complete, Required Report submitted10/15/19
Electrical Work complete (Auto Dock)11/8/19
50% Conference11/14/19
Spud Moores Reinstalled11/15/19
Portal Wire Rope Install proceed12/16/19
Portal Wire Rope Install complete12/23/19
75% Conference12/30/19
Portal Cranes Complete CRITICAL PATH ITEM1/3/20
Portal Cranes Weight Test; start1/7/20
Commence Open Ocean Tow Reinstallations2/15/20
Tank Close Out complete2/28/20
Ships Force Work complete2/28/20
Dock Basin Repairs complete3/1/20
All Work Complete (Production and Testing complete and certified)3/10/20
Complete Availability3/15/20