ATTACHMENT J-3: EXECUTION MILESTONES AND KEY EVENT DATES
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523618R0011_A0005.pdf | ||
| J-2_PRICING_WORKBOOK_REV2_01-18-2019.xlsm | XLSM spreadsheet | |
| 993-00-001_E1.pdf | ||
| 992-11-007_E1.pdf | ||
| N5523618R0017A0004.pdf | ||
| WI_130-11-002_ERRATA1.pdf | ||
| 593-11-004_E1.pdf | ||
| 992-11-001_E1.pdf | ||
| N5523618R0011_A0003.pdf | ||
| J-2_PRICING_WORKBOOK_REV1_12-21-18.xlsm | XLSM spreadsheet | |
| N5523618R0011_0002.pdf | ||
| N5523618R0011_AMENDMENT_0001.pdf | ||
| EXHIBIT_B_-_GFP_ARCO.xlsx | XLSX spreadsheet | |
| Attachment_S-2_-_Request_for_Specification_Clarification.doc | DOC document | |
| CDRLS_A001_-_A008.pdf | ||
| Attachment_S-4_-_Eligibility_Criteria_Data_Sheet_ARCO.docx | DOCX document | |
| J-2_PRICING_WORKBOOK.xlsm | XLSM spreadsheet | |
| Attachment_S-3_-_Past_Performance_Reference_List.docx | DOCX document | |
| Attachment_S-5_-_Past_Performance_Questionnaire_ARCO.docx | DOCX document | |
| N5523618R0017_ARCO_(ARDM-5)_FY19_DSCO_REQUEST_FOR_PROPOSAL.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ARCO (ARDM-5) | |
| Milestone / Key Event | Date |
| Start Availability | 8/15/19 |
| Portal Cranes Relocation proceed CRITICAL PATH ITEM | 8/30/19 |
| Portal Cranes Relocation complete | 9/6/19 |
| 20% Open and Inspect Reports Delivered | 9/20/19 |
| Complete Open Ocean Tow Removals | 9/29/19 |
| 25% Conference | 9/30/19 |
| Tank Inspections complete | 10/1/19 |
| Ultra-Sonic Testing complete, Required Reports submitted | 10/15/19 |
| Crane Rail Inspection complete, Required Report submitted | 10/15/19 |
| Grit Blast Valve Operator Inspection complete, Required Report submitted | 10/15/19 |
| Electrical Work complete (Auto Dock) | 11/8/19 |
| 50% Conference | 11/14/19 |
| Spud Moores Reinstalled | 11/15/19 |
| Portal Wire Rope Install proceed | 12/16/19 |
| Portal Wire Rope Install complete | 12/23/19 |
| 75% Conference | 12/30/19 |
| Portal Cranes Complete CRITICAL PATH ITEM | 1/3/20 |
| Portal Cranes Weight Test; start | 1/7/20 |
| Commence Open Ocean Tow Reinstallations | 2/15/20 |
| Tank Close Out complete | 2/28/20 |
| Ships Force Work complete | 2/28/20 |
| Dock Basin Repairs complete | 3/1/20 |
| All Work Complete (Production and Testing complete and certified) | 3/10/20 |
| Complete Availability | 3/15/20 |
| Attachment J-3 |