WORK ITEM 992-11-001 ERRATA
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523618R0011_A0005.pdf | ||
| J-2_PRICING_WORKBOOK_REV2_01-18-2019.xlsm | XLSM spreadsheet | |
| 993-00-001_E1.pdf | ||
| 992-11-007_E1.pdf | ||
| N5523618R0017A0004.pdf | ||
| WI_130-11-002_ERRATA1.pdf | ||
| 593-11-004_E1.pdf | ||
| N5523618R0011_A0003.pdf | ||
| J-2_PRICING_WORKBOOK_REV1_12-21-18.xlsm | XLSM spreadsheet | |
| N5523618R0011_0002.pdf | ||
| N5523618R0011_AMENDMENT_0001.pdf | ||
| EXHIBIT_B_-_GFP_ARCO.xlsx | XLSX spreadsheet | |
| J-3_Execution_Milestones_and_Key_Events.xlsx | XLSX spreadsheet | |
| Attachment_S-2_-_Request_for_Specification_Clarification.doc | DOC document | |
| CDRLS_A001_-_A008.pdf | ||
| Attachment_S-4_-_Eligibility_Criteria_Data_Sheet_ARCO.docx | DOCX document | |
| J-2_PRICING_WORKBOOK.xlsm | XLSM spreadsheet | |
| Attachment_S-3_-_Past_Performance_Reference_List.docx | DOCX document | |
| Attachment_S-5_-_Past_Performance_Questionnaire_ARCO.docx | DOCX document | |
| N5523618R0017_ARCO_(ARDM-5)_FY19_DSCO_REQUEST_FOR_PROPOSAL.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHIP: ARCO (ARDM 5) ITEM NO: 992-11-001 (E1)
COAR: 28 PCN: EEMC-Q244
ERMC-Q259
EAMC-Q250
EAMC-Q252
CMP: NONE
PLANNER: ALMARIO, DIONISIO
CUSTODIO, DONATO
STOUT, MICHAEL
SSP: SSSD-501-18 1 of 5 ITEM NO: 992-11-001 ERRATA NO. One
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Temporary Service (ARCO); provide
1.2 Location of Work:
1.2.1 Contractor's Facility
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items, (FY19)
2.2 MIL-STD-3007F, Standard Practice for Unified Facilities Criteria and Unified Facilities Guide Specifications.
2.3 S9086-RS-STM-010, NSTM Chapter 512, Vol I, Fans
2.4 S9086-CH-STM-030, NSTM Chapter 074, Vol 3, Gas Free Engineering
3. REQUIREMENTS:
3.1 Make connections, install and maintain temporary services aboard the ARCO on a continuous basis, 24 hours per day, for the entire availability. Location of connections for temporary services shall be provided to the SUPERVISOR.
3.2 Provide a licensed marine pilot and tugboat(s), capable of safely moving the vessel to and from pier side (Naval Base Point Loma) position and in the drydock at the contractors facility.
3.2.1 Schedule the movement of the vessel during high tide.
3.3 Install and maintain marine camels and fenders, conforming to the requirements of 2.2, between vessel and pier and on outboard side of vessel prior to barges or floating cranes coming alongside.
3.4 Install and maintain mooring lines capable of securing the vessel to the pier and drydock equal to those listed in the Heavy Weather Plan.
3.4.1 Provide line handlers.
3.5 Install and maintain an oil spillage/floating sandblasting debris containment booms around the entire perimeter of the vessel during the entire time it is waterborne in the contractors facility.
3.5.1 The containment boom shall have a minimum of four inches in height flotation with at least an eight inch skirt. Connections between each boom shall be oil tight.
SHIP: ARCO (ARDM 5)
SSP: SSSD-501-18 2 of 5 ITEM NO: 992-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.5.2 Ensure that each boom is anchored a minimum of 4 feet and a maximum of 20 feet from craft.
3.5.3 Remove, adjust (by adding or removing sections of boom), and install to accommodate movement of barges, paint floats, camels, diving vessels, drydocking, fueling, berth changes and dock trials.
3.5.4 Remove and dispose of oil spillage, paint residue, sandblasting residue and other debris in accordance with local, state and federal environmental regulations.
3.6 Install and maintain rat guards, conforming to MIL-G-2767, on all mooring lines and on service lines 1-1/2 inches in diameter and larger.
3.6.1 Rat guards shall be placed on mooring lines.
3.7 Install and maintain 2 gangways, one forward and one aft, with handrails. Gangways, platforms (if required), and handrails shall be built and maintained to meet the requirements of 2.2 and the following:
3.7.1 Each gangway and landing platform will be designed and
constructed to support a minimum load of 75 pounds per square foot.
3.7.1.1 Electrically bond and ground metallic gangways and
landing platforms to ships hull. Allowable gangway to ships hull electrical resistance: Zero ohms.
3.7.2 Illuminate the entire length of each gangway and adjacent areas with weatherproof lights, conforming to MIL-F-16377/23, symbol 103, shielded to prevent temporary blinding of personnel.
3.7.3 Install and maintain safety nets under each gangway and platform.
3.7.3.1 Safety nets shall extend 6 feet beyond each side of
gangways and platforms.
3.7.4 Maintain gangways and platforms free of debris, ice, snow and foreign matter.
3.7.5 Inclination of gangways shall not exceed 25 degrees.
3.8 Provide a watch hut with electricity, telephone, heating, and cooling capabilities, at a location designated by the SUPERVISOR while the drydock is in contractor's facility.
3.8.1 Electricity shall be 120 Volt AC, 60 Hz.
3.8.2 Heating and cooling shall be capable of maintaining a
temperature range of 65 to 75 degrees Fahrenheit.
3.8.3 Watch hut shall have windows to permit 360 degree viewing.
3.9 Provide a barricaded area at the foot of the brow with an enclosed covered security checkpoint area.
3.9.1 Security area shall include a portable heater, lights and a 6 foot table suitable for inspection.
3.10 Install and maintain temporary supply and exhaust ventilation to spaces where ventilation has been disrupted due to work being accomplished by the contractor in accordance with 2.3 and 2.4. Temporary
SSP: SSSD-501-18 3 of 5 ITEM NO: 992-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
ventilation shall be capable of providing same air flow as each system disrupted.
(V)(G) "AIR FLOW VERIFICATION"
3.10.1 Verify air flow in accordance with Section 21 of 2.4.
3.11 Provide ungrounded electrical power at 1600 Amps, 450 Volts, 60 HZ, 3 Phase at the ship’s power connection to the switchboard through the duration of the availability. Power shall be ungrounded from a dedicated 450 volt transformer secondary serving only the ship, via facility switchgear and cabling system to terminals onboard ship. The power rating (amps) is not to be demanded or have diversity factor applied.
3.11.1 Voltage shall not exceed the steady state voltage of nominal 450 Volts, plus or minus 5 percent, at ship’s main switchboard.
3.11.2 Current rating requirement shall be achieved via multiple 400 amp shore power cabling circuits.
3.11.3 Install safety devices at dockside capable of automatically maintaining services during power surges and equipped with circuit breakers to de-energize the electrical power during overloads. A 400 amp circuit breaker (100 KAIC rating) shall be provided for each portable shore power cable circuit serving ship. Ensure circuit breaker KAIC rating equals or exceeds 450 volt transformer and cabling system capability.
3.11.4 Portable shore power cabling and connectors serving ship shall have a current carrying capacity equal to or exceeding the specified shore power current requirements.
3.11.4.1 Type and condition of portable cabling and connectors shall be in accordance with DOD-STD-2003.2, figure 2-E-1.
3.11.4.2 Spliced portable cabling shall not to be used.
3.11.4.3 All portable cable circuits shall be of equal lengths (within 10 percent).
3.11.4.4 Cabling shall not be allowed to drop into the water.
3.11.4.5 Route excess lengths of portable cabling along length of pier and not in coils.
3.11.4.6 Post safety barriers at ship and shore connections.
3.11.5 Connect the portable shore power cabling and connectors to the ship.
3.11.5.1 Comply with the ship’s polarity requirements.
3.11.6 Shore power cables shall be wrapped with protective covering at locations where chafing may occur.
3.12 Install and maintain heaters in heated spaces throughout the vessel and maintain an ambient temperature of 65 to 75 degrees Fahrenheit with ventilation system secured, for the entire contract period during the time that the vessel’s heating system is not in operation.
SSP: SSSD-501-18 4 of 5 ITEM NO: 992-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.13 Maintain 3 fire zone boundaries aboard the vessel. The fire zone boundaries shall be the transverse bulkheads, including frame openings to be identified by the SUPERVISOR in conjuction with the Chief Engineer.
3.14 Provide 4 telephone direct trunk lines connected to the municipal telephone system with 24 hour continuous unlimited local service for the duration of the availability in the following locations:
3.14.1 Supply Office (local and long distance)
3.14.2 C.O. Stateroom (local and long distance)
3.14.3 X.O. Stateroom (local and long distance)
3.14.4 Quarterdeck (local)
3.14.5 Operation Office (local)
3.14.6 Telephone systems designated long distance shall be installed in such a manner that the only way long distance calls can be made will be with a long distance calling card (credit card) that shall be obtained by the ship prior to start of availability.
3.15 Provide 3 covered containers for collection of debris and garbage generated by Ship’s Force. Each container shall have a volume capacity of 200 cubic feet, with a minimum covered opening of 3 feet by 3 feet.
3.15.1 Containers shall be placed at suitable locations on the pier, adjacent to the ship service and craft.berthing barge.
(E1)
3.15.2 Garbage containers shall be emptied, steam cleaned and maintained daily in a sanitary condition, free of insects and rodents.
3.15.3 Provide and maintain one additional trash dumpster for medical solid waste with lockable doors, locks and keys. Deliver keys to the SUPERVISOR.
3.16 Provide,DELETED install and maintain a basic Cable Television (CATV) to the ship’s entertainment television panel, located on the berthing barge, on a 24 hour a day basis, throughout the availability, with the following cable channels as a minimum: ABC, CBS, CNN, ESPN, FOX, Headline News, MTV, NBC, PBS, TBS, MSNBC and local channels.
(E1)
3.16.1 If DELETEDCATV service is not available at the contractor’s ship repair facility, a portable satellite Television Receive Only (TVRO) system shall be used and connected to the ship’s entertainment television distribution panel. Mix and selection of available TVRO channels shall be equal to that provided in a basic CATV service.
(E1)
3.17 Disconnect and remove temporary services when directed by the
SUPERVISOR.
3.18 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.
4. NOTES:
4.1 Ship’s Force shall obtain the credit card and billing information for long distance services specified.
4.2 The fire extinguishers provided for Ship’s Force use shall not be
SSP: SSSD-501-18 5 of 5 ITEM NO: 992-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
used to supplement the contractor’s fire watches.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.