992-11-007_E1.pdf
PDF 39 KB Posted
- Solicitation number
- N5523618R0011
About this file
WORK ITEM 992-11-007 ERRATA
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523618R0011_A0005.pdf | ||
| J-2_PRICING_WORKBOOK_REV2_01-18-2019.xlsm | XLSM spreadsheet | |
| 993-00-001_E1.pdf | ||
| N5523618R0017A0004.pdf | ||
| WI_130-11-002_ERRATA1.pdf | ||
| 593-11-004_E1.pdf | ||
| 992-11-001_E1.pdf | ||
| N5523618R0011_A0003.pdf | ||
| J-2_PRICING_WORKBOOK_REV1_12-21-18.xlsm | XLSM spreadsheet | |
| N5523618R0011_0002.pdf | ||
| N5523618R0011_AMENDMENT_0001.pdf | ||
| EXHIBIT_B_-_GFP_ARCO.xlsx | XLSX spreadsheet | |
| J-3_Execution_Milestones_and_Key_Events.xlsx | XLSX spreadsheet | |
| Attachment_S-2_-_Request_for_Specification_Clarification.doc | DOC document | |
| CDRLS_A001_-_A008.pdf | ||
| Attachment_S-4_-_Eligibility_Criteria_Data_Sheet_ARCO.docx | DOCX document | |
| J-2_PRICING_WORKBOOK.xlsm | XLSM spreadsheet | |
| Attachment_S-3_-_Past_Performance_Reference_List.docx | DOCX document | |
| Attachment_S-5_-_Past_Performance_Questionnaire_ARCO.docx | DOCX document | |
| N5523618R0017_ARCO_(ARDM-5)_FY19_DSCO_REQUEST_FOR_PROPOSAL.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHIP: ARCO (ARDM 5) ITEM NO: 992-11-007
COAR: 28 PCN: DAMC-Q814
CMP: NONE
PLANNER: STOUT, MICHAEL
CUSTODIO, DONATO
SSP: SSSD-501-18 1 of 2 ITEM NO: 992-11-007
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Open Ocean Tow Enhancement Removal and Re-installation;
accomplish (OPTION ITEM)
1.2 Location of Work:
1.2.1 Contractor's Facility
1.3 Identification:
1.3.1 Arco (ARDM-5)
2. REFERENCES:
2.1 Standard Items, (FY19)
2.2 SL740-AA-MAN-010 Rev 3, U.S. Navy Towing Manual
2.3 613-4802169 Rev D, ARDM-5 Preparation for Coastal Towing
2.4 613-4802223, ARDM-5 Mooring & Towing Arrangements & Dets
2.5 613-8763593, FWD Outrigger Stowage For Tow Modifications
2.6 613-8763594, Modified Towing Arrangement and Details
2.7 613-8763595, FWD Tow Padeye and Flying Bridge Securing Mods
2.8 613-8763596, Aft Tow Padeye & Chock Modifications
2.9 581-8763597, Modified Anchor & Chain Billboard Install and Stowage
2.10 613-8763598, Fwd and Aft Wavebreak Fabrication & Installation
2.11 631-8763601, Tow Preparation PID
2.12 505-8763218, Towprep - Fr 432 (P/S) Gritblast Drainwell Reach Rod Modifications
2.13 835-8763600, Engineering Calculations Supporting Wavebreak Installation
2.14 581-4802215 Rev C, Anchor Handling Arr & Dets
2.15 631-4802231, Paint and Coating Schedule
2.16 132-4802186 Rev B, ARDM-5 Fwd and Aft Outriggers
2.17 192-7239932, Surface Ship Tightness Requirements
2.18 635-4802234, Thermal Insulation Arrgt & Det
2.19 810-4734309, Vlv Oper Gear & Ext Rods Surf Ships
2.20 S9505-AG-MMM-010, Rigid Rod Valve Remote Control System
3. REQUIREMENTS:
3.1 Accomplish the removal of the installed equipment for open ocean tow of the Service Craft identified in 1.3.1, in accordance with 2.2 through 2.14, using 2.15 through 2.20 as guidance, when directed by the
SHIP: ARCO (ARDM 5)
SSP: SSSD-501-18 2 of 2 ITEM NO: 992-11-007
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
SUPERVISOR.
3.1.1 Submit a report in hard copy or approved transferrable media, of a report listing of each removed equipment in 3.1 to the
SUPERVISOR.
3.1.2 Stow the equipment removed from 3.1 and retain for re-
installation.
3.2 Reinstall the equipment removed in 3.1, in accordance with 2.2 through 2.14, using 2.15 through 2.31 as guidance, when directed by the
SUPERVISOR.
3.2.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.
3.2.2 Re-install flooding alarms, draft indicators, and other alarms in accordance with paragraph 5-7.1.1 of 2.2.
(I)(G) "TOWING INSPECTION"
3.3 Accomplish a tow inspection in accordance with 2.31 para 5-10.1 through 5-10.4.
3.4 Accomplish the requirements of 009-32 of 2.1, for new and disturbed surfaces.
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.