This is an Asbestos Inspection Report for Building HP57 (a Barracks/Enlisted Quarters facility) at MCB Camp Lejeune, dated November 4, 2025. The building was constructed in 1976 and is assigned a Hazard Rank of 3/GREEN as of December 2022.

The report identifies two categories of asbestos-containing materials (ACM): no friable ACM and four instances of non-friable ACM. The non-friable ACM consists of vapor barrier material under hard tiles at shower pans (160 square feet, accessible only in mechanical rooms and presumed to be in all showers) and black roofing sealant at the attic/previous roof perimeter and parapet flashings (2,672 square feet). These materials were documented on March 11, 2010 and October 31, 2019. Extensive sampling conducted from June 2006 through December 2022 across multiple material types (floor tiles, ceiling tiles, caulking, drywall joint compound, pipe insulation, and tar paper) tested negative for asbestos or confirmed non-ACM status. The report emphasizes that intact and undisturbed ACM does not present a significant health hazard to building occupants. Personnel are instructed to avoid disturbance or damage to identified ACM and report any damage, dust, or debris to the Camp Lejeune Asbestos Program Manager at 910-451-5837. ACM will be inspected periodically to monitor condition changes, with the Program Manager maintaining survey records for the building.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASBESTOS INSPECTION REPORT of:

Building # HP57

MCB CAMP LEJEUNE

Tuesday, November 4, 2025

Print Date

Tuesday, November 4, 2025 Page 1 of 10Print Date:

INSPECTION SUMMARY

BLDG #:

OCCUPANT:

YEAR BUILT:

BUILDING COMMENTS:

HP57

BEQ

HAZ RANK 3/GREEN [DEC2022]

ROOFING SEALANT AND TAR PAPER

DEC2022

ACM REMAINS

OCT2019

NO CHANGES

JUL2016

ACM REMAINS

NOV2013

PVS. ACM REMAINS, NO CHANGES

MAR2010

PVS. SAMPLED MATERIALS CONFIRMED NON ACM, ADDL SAMPLING, ACM INCLUDES:

ROOFING SEALANT, BLACK

TAR PAPER, BLACK

VAPOR BARRIER, SHOWER PANS

INSPECT JUN06

NO ASBESTOS CONTAINING MATERIALS WERE IDENTIFIED.

ASBESTOS MANAGER: 910-451-5837

Friable ACM(s) identified

Non-friable ACM(s) identified

NOTICE: The following asbestos-containing materials have been identified in this structure. Refer to survey findings for additional information or contact the Asbestos Program Manager. Please note ACM that is intact and undisturbed is not considered a significant health hazard to building occupants.

DESCRIPTION LOCATION Date Quantity

DESCRIPTION LOCATION Date Quantity

No friable ACM records found in database

NOTIFICATION OF ACM IN BUILDING

VAPOR BARRIER 160 SFUNDER HARD TILES AT SHOWER PANS

(ACCESSIBLE ONLY IN MECHANICAL

ROOMS), PRESUMED ALL SHOWERS

3/11/2010

ROOFING SEALANT, BLACK 2,672 SFATTIC/ PREVIOUS ROOF; PERIMETER

AND PARAPET FLASHINGS

3/11/2010

VAPOR BARRIER 160 SFUNDER HARD TILES AT SHOWER PANS

(ACCESSIBLE ONLY IN MECHANICAL

ROOMS), PRESUMED ALL SHOWERS

10/31/2019

ROOFING SEALANT, BLACK 2,672 SFATTIC/ PREVIOUS ROOF; PERIMETER

AND PARAPET FLASHINGS

10/31/2019

Tuesday, November 4, 2025 Page 2 of 10Print Date:

Tested Non ACM or REMOVED Materials

DESCRIPTION LOCATION Date

VAPOR BARRIER 160 SFUNDER HARD TILES AT SHOWER PANS

(ACCESSIBLE ONLY IN MECHANICAL

ROOMS), PRESUMED ALL SHOWERS

11/5/2013

ROOFING SEALANT, BLACK 2,672 SFATTIC/ PREVIOUS ROOF; PERIMETER

AND PARAPET FLASHINGS

11/5/2013

VAPOR BARRIER 160 SFUNDER HARD TILES AT SHOWER PANS

(ACCESSIBLE ONLY IN MECHANICAL

ROOMS), PRESUMED ALL SHOWERS

7/20/2016

ROOFING SEALANT, BLACK 2,672 SFATTIC/ PREVIOUS ROOF; PERIMETER

AND PARAPET FLASHINGS

7/20/2016

VAPOR BARRIER 160 SFUNDER HARD TILES AT SHOWER PANS

(ACCESSIBLE ONLY IN MECHANICAL

ROOMS), PRESUMED ALL SHOWERS

12/14/2022

ROOFING SEALANT, BLACK 2,672 SFATTIC/ PREVIOUS ROOF; PERIMETER

AND PARAPET FLASHINGS

12/14/2022

DRYWALL AND JOINT MATERIAL DORM ROOMS THROUGHOUT 6/28/2006

12" TAN FLOOR TILE AND ADHESIVE CENTRAL LOUNGES 6/28/2006

PIPE INSULATION SEALANT CENTRAL AREA LAUNDRYS 6/28/2006

MISCELLANEOUS SEALANT CENTRAL LAUNDRIES AT PIPE

PENETRATIONS/ PATCHING

6/28/2006

EXTERIOR CAULKING, THROUGHOUT BUILDING 6/28/2006

TEXTURED CEILING MATERIAL DORM ROOMS THROUGHOUT, ON

CONCRETE

6/28/2006

12" TAN FLOOR TILE AND ADHESIVE DORM ROOMS THROUGHOUT

(PRIMARY TILE, SUPERCEEDED BY

HM01)

6/28/2006

2'x2' CEILING TILE, CENTRAL LOUNGES 6/28/2006

MISCELLANEOUS SEALANT MECHANICAL ROOM PIPE

PENETRATIONS THROUGH BLOCK

WALLS

6/28/2006

BROWN VINYL BASE AND ADHESIVE, 4" CENTRAL LOUNGES AND HALLS 6/28/2006

BROWN VINYL BASE AND ADHESIVE, 4" DORM ROOMS THROUGHOUT 6/28/2006

MISCELLANEOUS SEALANT MECHANICAL ROOM AND CENTRAL

PIPE CHASE DUCTS

6/28/2006

PIPE INSULATION MECHANICAL ROOM SUPPLY AND

RETURN LINES

6/28/2006

INTERIOR CAULKING, ATTIC/ PREVIOUS ROOF; PERIMETER

PARAPET WALL BASE

3/11/2010

LAGGING PAPER ON FIBERGLASS CENTRAL PIPE CHASES 3/11/2010

RESIDUAL MASTIC FIRST FLOOR CENTER HALLWAY 3/11/2010

EXTERIOR CAULKING, BRICK WALL EXPANSION JOINTS 3/11/2010

Tuesday, November 4, 2025 Page 3 of 10Print Date:

ACM only presents a health hazard when asbestos fibers are airborne and inhaled.

Avoid disturbance which will release fibers. The presence of asbestos does not constitute a health hazard.

HEALTH ASPECTS:

Do not disturb or cause damage to ACM. Do not sand, grind or abrade materials or cause damage with any type of equipment.

CONDITIONS TO AVOID:

Report any damage, dust or debris that may come from ACM or suspect ACM, or any change in the condition of materials, or accidental disturbance to the Asbestos

Program Manager.

REPORTS OF DAMAGE:

Corrective action initiated to minimize fiber release and protect personnel. RESPONSE ACTION:

ACM will be inspected periodically to evaluate any changes in condition.INSPECTION:

The Camp Lejeune Asbestos Program Manager maintains a copy of the survey for the building.

RECORDKEEPING:

CAMP LEJEUNE Asbestos Program Manager: Phone: (910) 451-5837

CONCRETE EXPANSION JOINT MATERIAL FIRST FLOOR BRICK/ CONCRETE SLAB

JOINT PERIMETER

3/11/2010

FIBERGLASS INSULATION SEALANT PIPE CHASES AND MECHANICAL ROOMS 3/11/2010

EXTERIOR CAULKING, METAL WINDOWS 3/11/2010

ROOFING MATERIAL, ATTIC/ ROOF, MAIN COVERING

RESIDUAL

3/11/2010

TAR PAPER, BLACK ATTIC/ ROOF, PREVIOUS ROOFING

VAPOR BARRIER THROUGHOUT

3/11/2010

ELECTRICAL WRAPPED WIRING NORTHEAST EXTERIOR GROUND AT

DITCH

3/11/2010

TAR PAPER, BLACK ATTIC/ ROOF, PREVIOUS ROOFING

VAPOR BARRIER THROUGHOUT

10/31/2019

MISCELLANEOUS SEALANT MECHANICAL ROOM AND CENTRAL

PIPE CHASE DUCTS

10/31/2019

12" TAN FLOOR TILE AND ADHESIVE CENTRAL LOUNGES AND OFFICE

AREAS, DORM ROOMS THROUGHOUT

3/11/2010

TEXTURED CEILING MATERIAL DORM ROOMS THROUGHOUT, ON

CONCRETE

3/11/2010

DRYWALL AND JOINT MATERIAL DORM ROOMS THROUGHOUT 3/11/2010

MISCELLANEOUS SEALANT MECHANICAL ROOM AND CENTRAL

PIPE CHASE DUCTS

3/11/2010

MISCELLANEOUS SEALANT MECHANICAL ROOM AND CENTRAL

PIPE CHASE DUCTS

7/20/2016

Tuesday, November 4, 2025 Page 4 of 10Print Date:

SAMPLES COLLECTED

Sample Sample

Date

HA Sample Location Chr

Amo

Oth

Description

HP57-01-01 6/28/200601 1ST FL LOUNGE 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-02 6/28/200601 1ST FL LOUNGE 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-10 3/11/201001 1ST FL CNTR OFFICE 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-11 3/11/201001 1ST FL WEST WING, SOUTH

CNTR RM

0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-11tem 3/11/201001 1ST FL WEST WING, SOUTH

CNTR

0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-12 3/11/201001 1ST FL EAST WING, NW RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-13 3/11/201001 1ST FL EAST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-14 3/11/201001 2ND FL EAST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-14tem 3/11/201001 2ND FL EAST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-15 3/11/201001 2ND FL WEST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-16 3/11/201001 2ND FL EAST WING, SE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-17 3/11/201001 3RD FL CNTR LOUNGE 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-18 3/11/201001 3RD FL WEST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-18tem 3/11/201001 3RD FL WEST WING, NE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-19 3/11/201001 3RD FL WEST WING, SE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-01-20 3/11/201001 3RD FL EAST WING, SE RM 0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/ WHITE

HP57-02-01 6/28/200602 1ST FL LOUNGE 0 0 02'x2' CEILING TILE, HP57-02-02 6/28/200602 1ST FL LOUNGE 0 0 02'x2' CEILING TILE, HP57-03-01 6/28/200603 1ST FL LOUNGE 0 0 0BROWN VINYL BASE

AND ADHESIVE, 4"

Tuesday, November 4, 2025 Page 5 of 10Print Date:

HA Sample Location Chr

Amo

Oth

Description

HP57-03-02 6/28/200603 3RD FL LOUNGE 0 0 0BROWN VINYL BASE

AND ADHESIVE, 4"

HP57-04-01 6/28/200604 1ST FL LAUNDRY 0 0 0PIPE INSULATION

SEALANT

WHITE

HP57-04-02 6/28/200604 2ND FL LAUNDRY 0 0 0PIPE INSULATION

SEALANT

WHITE

HP57-05-01 6/28/200605 1ST FL LAUNDRY 0 0 0MISCELLANEOUS

SEALANT

GREEN

HP57-05-02 6/28/200605 1ST FL LAUNDRY 0 0 0MISCELLANEOUS

SEALANT

GREEN

HP57-06-01 6/28/200606 1ST FL NORTH CNTR ROOM 0 0 0EXTERIOR CAULKING, GRAY

HP57-06-02 6/28/200606 2ND FL NORTH CNTR ROOM 0 0 0EXTERIOR CAULKING, GRAY

HP57-07-01 6/28/200607 1ST FL EAST WING, NW RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-02 6/28/200607 1ST FL WEST WING, NW RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-03 6/28/200607 2ND FL EAST WING, SW RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-04 6/28/200607 2ND FL WEST WING, SE RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-05 6/28/200607 3RD FL WEST WING, SE

RM328

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-06 6/28/200607 3RD FL EAST WING, SE RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-07 6/28/200607 3RD FL EAST WING, SOUTH

CNTR RM 317

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-10 3/11/201007 1ST FL CNTR HALL 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-11 3/11/201007 1ST FL WEST WING, SE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-12 3/11/201007 1ST FL EAST WING, SW RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-13 3/11/201007 1ST FL EAST WING, NORTH

CNTR RM

0 0 0TEXTURED CEILING

MATERIAL

HP57-07-14 3/11/201007 2ND FL EAST WING, NE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-15 3/11/201007 2ND FL WEST WING, NE RM 0 0 0TEXTURED CEILING

MATERIAL

Tuesday, November 4, 2025 Page 6 of 10Print Date:

HA Sample Location Chr

Amo

Oth

Description

HP57-07-16 3/11/201007 2ND FL EAST WING, SE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-17 3/11/201007 3RD FL WEST WING, NE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-18 3/11/201007 3RD FL WEST WING, SE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-07-19 3/11/201007 3RD FL EAST WING, SE RM 0 0 0TEXTURED CEILING

MATERIAL

HP57-08-01 6/28/200608 1ST FL EAST WING, NW RM

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-02 6/28/200608 1ST FL WEST WING, WEST

WING, NW RM 122

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-03 6/28/200608 2ND FL EAST WING, SW RM

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-04 6/28/200608 2ND FL WEST WING, SE RM

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-05 6/28/200608 3RD FL WEST WING, SE RM

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-10 3/11/201008 1ST FL WEST WING, SOUTH

CNTR RM

.1 .1 .1DRYWALL AND JOINT

MATERIAL

HP57-08-11 3/11/201008 1ST FL WEST WING, SE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-12 3/11/201008 1ST FL EAST WING, SW RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-13 3/11/201008 1ST FL WEST WING, NE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-14 3/11/201008 2ND FL EAST WING, NE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-15 3/11/201008 2ND FL WEST WING, NE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-17 3/11/201008 3RD FL WEST WING, NE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-18 3/11/201008 3RD FL WEST WING, SOUTH

CNTR RM

0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-19 3/11/201008 3RD FL WEST WING, SE RM 0 0 0DRYWALL AND JOINT

MATERIAL

HP57-08-20 3/11/201008 3RD FL EAST WING, SE RM 0 0 0DRYWALL AND JOINT

MATERIAL

Tuesday, November 4, 2025 Page 7 of 10Print Date:

HA Sample Location Chr

Amo

Oth

Description

HP57-09-01 6/28/200609 1ST FL EAST WING, NW RM

0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/WHITE

HP57-09-02 6/28/200609 1ST FL WEST WING, NW

RM122

0 0 012" TAN FLOOR TILE

AND ADHESIVE

w/WHITE

HP57-10-02 6/28/200610 1ST FL WEST WING, NW RM

0 0 0BROWN VINYL BASE

AND ADHESIVE, 4"

HP57-11-01 6/28/200611 1ST FL MECH RM 1 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-02 6/28/200611 2ND FL MECH RM 4 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-10 3/11/201011 1ST FL WEST MECH RM,

SOUTH

0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-11 3/11/201011 2ND FL WEST MECH RM,

SOUTH

0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-12 3/11/201011 3RD FL WEST MECH RM,

SOUTH

0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-30 7/20/201611 ATTIC, CNTR DUCT WEST 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-11-40 7/20/201611 ATTIC, CNTR DUCT WEST 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-12-01 6/28/200612 1ST FL MECH RM 1 0 0 0PIPE INSULATION FIBERGLASS

HP57-12-02 6/28/200612 2ND FL MECH RM 2 0 0 0PIPE INSULATION FIBERGLASS

HP57-13-01 6/28/200613 2ND FL MECH RM #3 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-13-02 6/28/200613 3RD FL MECH RM #5 0 0 0MISCELLANEOUS

SEALANT

RED

HP57-20-10 3/11/201020 1ST FL WEST CHASE, EAST

END

0 0 0LAGGING PAPER ON

FIBERGLASS

HP57-20-11 3/11/201020 2ND FL WEST CHASE, EAST

END

0 0 0LAGGING PAPER ON

FIBERGLASS

HP57-20-12 3/11/201020 3RD FL WEST CHASE, EAST

END

0 0 0LAGGING PAPER ON

FIBERGLASS

HP57-21-10 3/11/201021 1ST FL CNTR HALL NORTH 0 0 0RESIDUAL MASTIC BLACK

HP57-22-10 3/11/201022 1ST FL WEST END 0 0 0EXTERIOR CAULKING, GRAY

HP57-22-11 3/11/201022 2ND FL EAST END 0 0 0EXTERIOR CAULKING, GRAY

Tuesday, November 4, 2025 Page 8 of 10Print Date:

HA Sample Location Chr

Amo

Oth

Description

HP57-22-12 3/11/201022 3RD FL WEST END 0 0 0EXTERIOR CAULKING, GRAY

HP57-23-10 3/11/201023 1ST FL WEST END, CNTR 0 0 0CONCRETE EXPANSION

JOINT MATERIAL

BLACK

HP57-24-00ri13 11/5/201324 N/A 9 9 9VAPOR BARRIER BLACK

HP57-24-00ri16 7/20/201624 N/A 9 9 9VAPOR BARRIER BLACK

HP57-24-00ri19 10/31/201924 N/A 9 9 9VAPOR BARRIER BLACK

HP57-24-00ri22 12/14/202224 N/A 9 9 9VAPOR BARRIER BLACK

HP57-24-10 3/11/201024 1ST FL WEST WING, SOUTH

CNTR MECH RM

3 0 0VAPOR BARRIER BLACK

HP57-24-11 3/11/201024 2ND FL WEST WING, SOUTH

CNTR MECH RM

0 0 0VAPOR BARRIER BLACK

HP57-24-12 3/11/201024 3RD FL WEST WING, SOUTH

CNTR MECH RM

0 0 0VAPOR BARRIER BLACK

HP57-25-10 3/11/201025 1ST FL WEST WING, SE RM 0 0 0EXTERIOR CAULKING, GRAY

HP57-25-11 3/11/201025 2ND FL EAST WING, NE RM 0 0 0EXTERIOR CAULKING, GRAY

HP57-25-12 3/11/201025 3RD FL WEST WING, NE RM 0 0 0EXTERIOR CAULKING, GRAY

HP57-26-10 3/11/201026 3RD FL CNTR CHASE WEST 0 0 0FIBERGLASS

INSULATION SEALANT

WHITE

HP57-22-00ri23 12/14/202227 N/A 9 9 9ROOFING SEALANT, BLACK

HP57-27-00ri13 11/5/201327 N/A 9 9 9ROOFING SEALANT, BLACK

HP57-27-00ri16 7/20/201627 N/A 9 9 9ROOFING SEALANT, BLACK

HP57-27-00ri19 10/31/201927 N/A 9 9 9ROOFING SEALANT, BLACK

HP57-27-10 3/11/201027 ATTIC/ ROOF, WEST END 3 0 0ROOFING SEALANT,

BLACK

HP57-27-11 3/11/201027 ATTIC/ ROOF, EAST END 3 0 0ROOFING SEALANT,

BLACK

HP57-27-70 12/14/202227 ATTIC, CNTR MEMBRANE/

VAPOR BARRIER

0 0 0ROOFING SEALANT,

BLACK

HP57-28-10 3/11/201028 ATTIC/ ROOF, WEST END 0 0 0INTERIOR CAULKING, WHITE

Tuesday, November 4, 2025 Page 9 of 10Print Date:

HA Sample Location Chr

Amo

Oth

Description

HP57-28-11 3/11/201028 ATTIC/ ROOF, EAST END 0 0 0INTERIOR CAULKING, WHITE

HP57-29-10 3/11/201029 ATTIC/ ROOF, WEST END 0 0 0ROOFING MATERIAL, BLACK

HP57-29-11 3/11/201029 ATTIC/ ROOF, EAST END 0 0 0ROOFING MATERIAL, BLACK

HP57-30-10 3/11/201030 ATTIC/ ROOF, WEST END 0 0 0TAR PAPER, BLACK

HP57-30-11 3/11/201030 ATTIC/ ROOF, EAST END 0 0 0TAR PAPER, BLACK

HP57-30-40 10/31/201930 ATTIC, WEST CNTR [as HP57-

41-40]

0 0 0TAR PAPER, BLACK

HP57-41-40 10/31/201930 SEE HP57-30-40 0 0 0TAR PAPER, BLACK

HP57-31-10 3/11/201031 NE EXT. GROUND 0 0 0ELECTRICAL WRAPPED

WIRING

BLACK