ATTACHMENT A_SCOPE OF WORK.pdf

PDF 6 MB Posted

Attached to
CONVERT INTEL SPACES TO CONTROLLED AREA, BLDG 145, NAS OCEANA, VIRGINIA BEACH, VA
Solicitation number
N4008526R0169
Issued by

About this file

This is a Request for Proposal (RFP) for design-build services to convert approximately 1,830 square feet of Intel space into a Controlled Area with Radio Frequency (RF) protection at Building 145, Naval Air Station Oceana, Virginia Beach, Virginia. The project involves comprehensive renovation of existing office spaces (rooms E205, E223-E227, E229, W205, W223-W226) to comply with "Accreditation Documentation" requirements, including structural, mechanical, electrical, fire protection, and plumbing modifications. The Controlled Area perimeter walls must achieve a minimum Sound Transmission Class (STC) rating of 50 and provide 60 decibel (dB) RF signal mitigation per IEEE 299 standards, with all penetrations grounded unless otherwise noted. Key scope elements include: removal of demising walls to create connecting corridors, installation of new HVAC ductless split systems, conversion of existing vault space (W229) to open storage, new lighting and electrical systems, fire alarm system extensions via fiber optic cable, and comprehensive interior finishes including gypsum board walls, suspended ceiling systems with RF-shielded diffusers, and specific paint and flooring requirements.

The RFP restricts bidding to the MACC GROUP ML-C00081 (small business set-aside) under the Navy's Design-Build/Design-Bid-Build Indefinite Delivery/Indefinite Quantity Multiple Award Construction Contract for Hampton Roads, Virginia. The contract requires a cost-loaded Network Analysis Schedule, comprehensive quality control and safety programs per EM 385-1-1 standards, appointment of qualified personnel including a Designer of Record, Superintendent, Site Safety and Health Officer, and Quality Control Manager, and strict adherence to security requirements including DBIDS access credentials, construction security protocols, and limited photography/disclosure restrictions. The government will provide accreditation documentation separately via DoD Safe; the project must maintain Building 145's operational status throughout construction with scheduled utility outages requiring advance approval. Required submittals include Pre-Award and Pre-Construction Accident Prevention Plans, Activity Hazard Analyses, detailed design packages at 35%, Pre-Final, and Final stages, baseline and monthly Network Analysis Schedules, equipment inventory forms, operation and maintenance information, and record drawings in native CAD format. All work must comply with UFC 1-200-01 (DoD Building Code), Virginia Hazardous Waste Management Regulations, environmental protection requirements, Buy American Act provisions, and Davis-Bacon wage determinations.

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

***UNCLASSIFIED***

eProjects WO#: 1755081

BUILDING 145

CONVERT INTEL SPACES TO CONTROLLED AREA

At the

Naval Air Station Oceana, Virginia Beach, Virginia

PREPARED BY:

NAVFAC MIDLANT, OCEANA ROICC, PDCB PRA21

NAS Oceana, 953 Hornet Drive, Building 820, Suite 210

Virginia Beach, Virginia 23460-2197

REQUEST FOR PROPOSAL (RFP) PREPARED BY:

DM (Design Manager): Alok Anil, R.A.

Architectural: Alok Anil, R.A.

Mechanical: Robert D. Lamb Jr.

Electrical: Christopher T. Olwin, P.E.

Fire Protection: Kevin Kimmel, P.E.

REQUEST FOR PROPOSAL (RFP) APPROVED BY:

Design Engineering Branch Manager: Scott D. McPeek, R.A.

Signature/Date:

Submitted By: Scott D. McPeek, R.A. Date: 29 September 2025

BUILDING 145 – CONVERT INTEL SPACES TO CONTROLLED AREA eProjects WO#: 1755081

NAS OCEANA, VIRGINIA BEACH, VIRGINIA

TABLE OF CONTENTS

PART 2 – GENERAL REQUIREMENTS

PART 3 – STATEMENT OF WORK / PROJECT PROGRAM

PART 4 – MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION

REQUIREMENTS

PART 5 – PRESCRIPTIVE SPECIFICATIONS

(Section 01 31 23.13.20 – ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT

CONTRACT MANAGEMENT SYSTEM)

(Section 01 32 17.00 20 – COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS)

(Section 01 35 26.05 20 – GOVERNMENT REQUIREMENTS FOR DESIGN-BUILD)

PART 6 – ATTACHMENTS

ATTACHMENT 6.01 Record Drawings:P-141U Aircraft Maintenance Hanger 3/3/2000

ATTACHMENT 6.02 Overall Second Floor Plan

ATTACHMENT 6.03 Existing Floor Plan Intel Spaces (Second Floor)

ATTACHMENT 6.04 Concept Floor Plan Intel Spaces (Second Floor)

ATTACHMENT 6.05 NAS OCEANA 145 CONSTRUCTION SECURITY PLAN

ATTACHMENT 6.06 OC-DN-FN-SOP-WA-14 SURFACE PREPARATION AND PAINTING

STANDARD OPERATING PROCEDURE (SOP)

ATTACHMENT 6.07 EV Checklist OC 145

ATTACHMENT 6.08 Proposed Laydown Area OC 145

ATTACHMENT 6.09 Equipment Inventory Form

ATTACHMENT 6.10 Concept Furniture Plan Intel Spaces (Second Floor)

Engineer ing Depar tment eProjects WO#: 1755081

PART 2 – GENERAL REQUIREMENTS

BUILDING 145 – CONVERT INTEL SPACES TO CONTROLLED AREA

NAS OCEANA

VIRGINIA BEACH, VIRGINIA

PART 2 GENERAL REQUIREMENTS - Page 1

Part 2 General Requirements

PART 2

GENERAL REQUIREMENTS

1/20

• 00 00 00 GENERAL REQUIREMENTS

• 01 11 00 SUMMARY OF WORK

• 01 14 00.05 20 WORK RESTRICTIONS

• 01 20 00.05 20 PRICE AND PAYMENT PROCEDURES

• 01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS

• 01 31 19.05 20 POST AWARD MEETINGS

• 01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT

CONTRACT MANAGEMENT SYSTEM

• 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS)

• 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES

• 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

• 01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN BUILD

• 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL

• 01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS

• 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

• 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

• 01 78 00 CLOSEOUT SUBMITTALS

00 00 00 GENERAL REQUIREMENTS

1.1 Definitions

As used throughout the contract, the following terms have the meaning set forth below:

Contracting Officer (KO): The individual designated to administer the contract. Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.

Contracting Officer Representative (COR): The individual designated by the Contracting Officer as

PART 2 GENERAL REQUIREMENTS - Page 2 the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.

Contract: Contract or task order.

Contractor: The term Contractor refers to both the prime Contractor and all subcontractors, whether in contract with the Prime Contractor or other subcontractors at any tier, including the Designer of Record.

Designer of Record (DOR): Licensed architect/engineer working as subcontractor to or partner with prime Contractor who provides design for this contract.

Quality Control (QC): Contractor's system to control the quality of design, material, equipment and construction.

Quality Assurance (QA) Program: Government's program to evaluate the effectiveness of the Contractor's quality control. The Government's QA Program is not a substitute for the Contractor's QC Program.

Federal Holidays: New Year's Day, Martin Luther King Jr. Day, President's Day, Memorial Day, Juneteenth, Independence Day; Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.

1.2 Accessibility

Provide barrier-free design in accordance with UFC 1-200-01, DoD Building Code.

1.3 Changes

No oral statement by any person other than the Contracting Officer, as provided in the Federal Acquisition Regulation (FAR) clause 52.243-5 entitled, "CHANGES AND CHANGED CONDITIONS," will in any manner or degree modify or otherwise affect the terms of this contract.

1.4 No Waiver by the Government

The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred is not to be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.

1.5 Equitable Adjustments

a. Whenever the Contractor submits a claim for equitable adjustment under a clause which provides for equitable adjustment of the contract, such claim must include all types of adjustments in the total amounts to which the clause entitles the Contractor, including, but not limited to, adjustment arising out of delays or disruptions.

b. Except as the parties may otherwise expressly agree, the Contractor must be deemed to have waived: (1) any adjustments to which he otherwise might be entitled under the clause where such claim fails to request such adjustments; and (2) any increase in the amount of equitable adjustments additional to those requested in its claim.

c. If required by the Contracting Officer, the Contractor agrees to execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental

PART 2 GENERAL REQUIREMENTS - Page 3 agreement setting forth the aforesaid equitable adjustment. The Contractor further agrees that such release will discharge the Government, including its officers, agents, and employees, from any further claims, including, but not limited to, further claims arising out of delays or disruptions caused by the aforesaid change.

1.6 Warranty

Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair. For warranted items, furnish the manufacturer’s original written warranty accompanied by a copy of the supplier's receipt showing place of purchase, telephone number of supplier, address, delivery order number if applicable, and ticket number.

1.7 Equipment Inventory Forms

The Contractor must submit an Equipment Inventory Form for existing equipment to be demolished/removed, or for new equipment to be provided under this contract. The Equipment Inventory Form must be completely filled-out and provided for each piece of equipment, for the entire equipment listings. Further clarification on the equipment types will also be discussed at the PAK or Pre-Construction Meetings, or as directed by the Contracting Officer. Submit all Equipment Inventory Forms to the Contracting Officer, prior to demolition of the existing equipment and prior to installation of the new equipment. (See PART 6 – ATTACHMENTS for the Equipment Inventory Form to utilize).

01 11 00 SUMMARY OF WORK

1.0 Protection of Government Property

Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, perform the following:

a. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.

b. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

c. Preserve the natural resources in accordance with the approved environmental protection plan prepared in accordance with UFGS 01 57 19 Temporary Environmental Controls.

1.1 Government Furnished Material and Equipment – NOT APPLICABLE

01 14 00.05 20 WORK RESTRICTIONS

1.1 Existing Underground Utilities – NOT APPLICABLE

PART 2 GENERAL REQUIREMENTS - Page 4

1.2 Work Hours, Access and Passes

All Contractor employees, including subcontractors, subcontractors' employees, suppliers, and suppliers' employees are required to comply with the Installation Security Requirements regarding personnel, vehicle, and equipment security passes and access to the jobsite. Nothing in the contract is to be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station.

Coordinate with the Contracting Officer for specific security and access requirements.

a. Access to Buildings/ Occupied Buildings: The Contractor may work in or around existing occupied buildings. The Contractor is responsible, via the Contracting Officer, to obtain access to building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. Keep the existing buildings and their contents secure at all times. Construction work areas must have complete and secure separation from adjacent occupied areas, as approved and directed by the Contracting Officer and Activity’s Security Officer. Provide temporary closures as required to maintain security. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer.

b. Passes and Badges: Contractor employees and representatives performing work under this contract are required to be either United States citizens or documented legal residents (status verified by prime contractor). All Contractor employees must obtain the required employee and vehicle passes. Each employee is required to wear the Government issued badge over the front of the outer clothing. Failure to obtain security and base access passes must not be a cause for contract performance time extension.

The Contractor is required to immediately turn in all terminated employee's badges to the issuing office.

Obtain access to Navy installations through participation in the Defense Biometrics

Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential. Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation. Registration for DBIDS includes: Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

• Present valid identification, such as a passport or Real ID Act-compliant state driver's license

• Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at <URL>https://www.cnic.navy.mil/om/dbids.html</URL >

• Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments

• Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite

DBIDS Eligibility Requirements: Throughout the length of the contract, the https://www.cnic.navy.mil/om/dbids.html%3c/URL

PART 2 GENERAL REQUIREMENTS - Page 5

Contractor employee must continue to meet background screen standards.

Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible. An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority. DBIDS Notification Requirements: Immediately report instances of lost or stolen badges to the Contracting Officer. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances: (1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials. (2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

c. Contractor Vehicles: All vehicles must display a valid state license plate and safety inspection sticker, if applicable, and must be maintained in good repair. The company name must be displayed in a clearly visible manner and size on each Contractor vehicle used in the course of work. Registration, proof of insurance and driver's licenses are required to obtain a station vehicle pass. Work at Hangar 145 is inside the flightline security fence enclave. All personnel must obtain flight line access from the security officer to access the job site. Only construction vehicles and delivery vehicles will be allowed inside the flightline security enclave. Parking for all personally owned vehicles and non-construction vehicles shall park outside the flightline security enclave. Coordinate with the Contracting Officer. Parking may not be immediately adjacent to the job site. If required, the Contractor shall be responsible for transportation of his employees from the designated parking area to the jobsite.

d. Work Hours: Unless otherwise indicated, work will be located on a Government compound, military installation, or station. Contractor work hours are between 0700 and 1530 Monday through Friday except when utility outages are required. Obtain advance approval from the Contracting Officer for Contractor personnel to remain on site beyond normal working hours. Notify the Contracting Officer at least 48 hours in advance to obtain approval for access to the jobsite or work outside of normal working hours or on Saturday, Sunday, and Federal Holidays.

e. Contractor Personnel: Provide the Contracting Officer the name(s) of the supervisory person(s) authorized to act for the Contractor. Provide, and update as required, a list of the key personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency.

f. Contractor employees must conduct themselves in a proper, efficient, courteous and businesslike manner. Remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of National Security.

1.3 Security Requirements

All security requirements apply to all subcontractors and suppliers associated with this contract.

Special or extraordinary security requirements are identified herein. Comply with the following in addition to special or extraordinary security requirements:

PART 2 GENERAL REQUIREMENTS - Page 6

a. Do not publicly disclose any information concerning any aspect of the materials or services relating to this contract, without prior written approval of the Contracting Officer.

b. Do not disclose or cause to be disseminated any information concerning the operations of the activity's security or interrupt the continuity of its operations.

c. Do not disclose any information to any person not entitled to receive it. Failure to safeguard any classified information that may come to the Contractor or any person under his control, may subject the Contractor, his agents or employees to criminal liability under 18 U.S.C., Sections 793 and 798.

d. Direct to the Contracting Officer and or Installation Security Officer for resolution all inquiries, comments or complaints arising from any matter observed, experienced, or learned as a result of or in connection with the performance of this contract, the resolution of which may require the dissemination of official information.

e. Coordinate photography requirements with the Contracting Officer. All areas restrict or prohibit photographing Government property. Personal photographic equipment of any kind, including but not limited to cameras (Still and Video), film, and cellular telephones are prohibited.

f. Special security requirements apply to this contract. All Contractor personnel associated with this contract must obtain personnel security clearances/badges from the Activity’s Security Officer in order to perform work in Building 145. Strict adherence to the rules and regulations, as set forth by the Activity’s Security Officer, must be complied with at all times.

g. Building 145 is considered Open Secret Storage (OSS) environment and must remain in operation during the entirety at all times while working in the space.

Responsibility for Escorts: The Contractor must be responsible for coordinating escorts with the Building Activity/SSO at all times. The Contracting Officer and other NAVFAC personnel “will not” be responsible for the coordination of escorts for Contractor personnel.

h. Military escorts are required in the following spaces:

Deviations from or violations of any of the provisions of this paragraph, will, in addition to all other criminal and civil remedies provided by law, subject the Contractor to immediate termination for default and withdrawal of the Government's acceptance and approval of employment of the individuals involved.

01 20 00.05 20 PRICE AND PAYMENT PROCEDURES

1.1 Schedule of Prices

Submit a schedule of prices for approval on forms furnished by the Government. The initial schedule of prices may be preliminary for construction activities until the design is developed.

Include a detailed breakdown of the contract price with quantities and unit prices for each work activity or definable feature of work. Include general conditions, profit, and overhead costs within the unit prices. Break down into design and construction is required. The Contractor may invoice for bonds once the Government has approved the bonds, however, no other requests for payment will be processed without an approved schedule of prices and baseline schedule.

PART 2 GENERAL REQUIREMENTS - Page 7

1.2 Contractor Invoices

Contractor requests for payment must conform and will be processed in accordance with the requirements of FAR 52.232-5 and FAR 52.232-27.

a. Content of Invoice: Requests for payment in accordance with the terms of the contract must consist of the following: (If NFAS Clause 5252.232-9301 is present in the contract, documents must be provided as attachments in Wide Area Workflow (WAWF). The maximum size limit per attachment is less than 2 megabytes, but there are no limits on the number of attachments. If a document cannot be attached to WAWF due to system or size restrictions it must be provided as instructed by the contracting officer). If NFAS Clause 5252.232.9301 is not present in the contract, follow the invoicing instructions provided in the contract.

1. Contractor's Invoice on NAVFAC Form 7300/30, must show, in summary form, the basis for arriving at the amount of the invoice.

2. Contractor's Estimate for Voucher/ Contract Performance Statement on NAVFAC

Form 7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC LANT Form 4- 330/110 (New 7/84) on NAVFAC Atlantic contracts when a Monthly Estimate for Voucher is required.

3. Affidavit to accompany invoice (LANTDIV NORVA Form 4-4235/4 (Rev. 5/81)).

4. Updated copy of submittal register.

5. Updated copy of progress schedule. Furnish as specified in "FAR 52.236-15, Schedules for Construction Contracts."

6. Contractor Safety Self Evaluation Checklist (original)

7. Final release (for final payment only). Final invoice must be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release.

b. Payment:

1. Payment will be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments. The Government may withhold payment or reduce payments for the following:

a. Defects in material or workmanship.

b. Claims the Government may have against the Contractor under or in connection with this contract.

c. Contractor's failure to submit an updated schedule.

d. Payroll violations.

e. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.

2. Payments will not be made for materials stored off construction sites

1.3 Budget Management

The Contractor must be responsible for budget management throughout the entire project. It is the intent of the Government to partner with the Contractor to maximize project value while strictly controlling contract modifications and maintaining overall fiscal control. When required, develop a Budget Management System for each phase of the design.

This project requires a Budget Management System be developed and maintained. The Budget Management System must represent major portions of the work such as HVAC, site work, and exterior skin. The purpose of budget management is to balance scope and value during critical project design decisions. Update the budget management status at regular intervals during

PART 2 GENERAL REQUIREMENTS - Page 8 design, at a minimum with design submittals, for review by and discussion with the COR.

01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS

1.1 Supervision

The Contractor must have a superintendent fluent in English on the job site during working hours.

The Superintendent must have a minimum of 5 years of experience as a Superintendent on previous projects of similar size and complexity. The Superintendent may not serve as the Site Safety, Health Officer. Provide a Superintendent Resume for the proposed on-site Project Superintendent describing experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed on-site Project Superintendent at any time in order to verify the submitted qualifications. The Superintendent, Site Safety and Health Officer must be a direct employee of the Prime Contractor.

1.2 Required Insurance

Within 15 calendar days after award, furnish the Contracting Officer a Certificate of Insurance as evidence of the following insurance coverage amounts not less than the amount specified below in accordance with FAR Clause 52.228-5, Insurance Work On A Government Installation:

a. Comprehensive General Liability: $500,000 per occurrence.

b. Automobile Liability: $200,000 per person, $500,000 per occurrence for bodily injury;

$20,000 per occurrence for property damage.

c. Worker's Compensation: As required by Federal and State Worker's compensation and occupational disease and other laws.

d. Employer's Liability Coverage: $100,000, except in states where worker's compensation may not be written by private carriers.

e. Others as required by state law.

f. Above insurance coverages are to extend to Contractor personnel operating Government owned equipment and vehicles.

g. The Certificate of Insurance must provide for 30 calendar days written notice to the Contracting Officer by the insurance company prior to cancellation or material change in policy coverage.

For projects which require removal of asbestos containing materials the Asbestos Contractor or Subcontractor, as the case may be is required to provide occurrence-based liability insurance with asbestos coverages in an amount not less than $1,000,000 and must name the Government and Private Qualified Person (PQP) as additional insureds.

01 31 19.05 20 POST AWARD MEETINGS

1.1 Post Award Kick-off Meeting (PAK)

Prior to commencement of design, and within 21 calendar days of award, meet with representatives of the Contracting Officer, installation and client to present the concept design for discussion and acceptance. The project team will develop a mutual understanding relative to the approved proposal, safety program, environmental permits and requirements, quality control

PART 2 GENERAL REQUIREMENTS - Page 9 procedures, and design and construction schedule. During the meeting, Contractor must propose and gain acceptance for any critical path work activities requiring advance submittal and approval.

If the contract includes work on any fire protection system, including fire alarm and mass notification systems, the Contractor and the appropriate DOR must meet with the NAVFAC Fire Protection Engineer (FPE) to establish clear expectations of fire protection requirements of the project.

The Contractor's key personnel must attend including the Project Manager, Superintendent, Site Safety and Health officer, Construction Quality (CQ) Manager, Design Quality Control (DQC) Manager, Designer of Record (DOR), and major subcontractors.

The Contractor shall take detailed Meeting Minutes/Notes during the PAK meeting, and shall distribute the Meeting Minutes to the Contracting Officer/NAVFAC Team within 3 business days after the PAK Meeting was held.

1.2 Partnering

The Contracting Officer will organize initial and follow-up informal partnering sessions with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session may be a part of the PAK Meeting. The initial partnering session will be conducted and facilitated using electronic media provided by the Contracting Officer. Follow-on partnering sessions will be conducted every 6 months or less frequent as determined by the Contracting Officer.

The Contractor shall take detailed Meeting Minutes/Notes during any Partnering meetings, and shall distribute the Meeting Minutes to the Contracting Officer/NAVFAC Team within 3 business days after the Partnering meetings are held.

1.3 Pre-Construction Conference

Prior to construction or demolition, meet with representatives of the Contracting Officer to discuss and develop mutual understanding relative to administration of the safety programs, environmental issues, safety of building occupants and surrounding area, hazardous materials, waste disposal, construction QC procedures, labor provisions and other construction phase contract procedures.

1.4 NAVFAC Red Zone Meeting (NRZ)

Participate in NAVFAC Red Zone (NRZ) meetings with the Contracting Officer to identify strategies to ensure the project is carried to expeditious closure and turnover to the client. The Contracting Officer will provide a template to the Contractor to use to develop a NRZ Checklist.

Revise the template to include critical work activities and their planned completion dates based on the project scope of work and schedule. Discuss any progress changes with items listed on the NRZ Checklist during regularly scheduled NRZ Meetings beginning approximately at 75% stage of construction prior to project completion.

The Contractor shall take detailed Meeting Minutes/Notes during the PRECON conference, and shall distribute the Meeting Minutes to the Contracting Officer/NAVFAC Team within 3 business days after the PRECON conference was held.

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY

SUPPORT CONTRACT MANAGEMENT SYSTEM

See UFGS Section 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System in Part 5 of this RFP for requirements for the use of eCMS.

PART 2 GENERAL REQUIREMENTS - Page 10

01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES

(NAS)

Develop and implement a design and construction schedule in accordance with UFGS 01 32 17.00 20 in Part 5 of this RFP. (See PART 5 – PRESCRIPTIVE SPECIFICATIONS).

01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES

1.1 Construction submittals are to be Contractor-approved, except those listed below:

a. DOR Approval required for:

1. Fire Protection related submittals

2. All components of the interior doors, hardware, fireproofing/firestopping, paint, finish materials/colors.

3. HVAC Testing, Adjusting, and Balancing.

4. Telecommunications

5. SID submittals.

6. All components of wall construction.

7. All components of RF Shielding.

8. All mechanical HVAC equipment and associated appurtenances.

9. All supply diffusers, return grilles/registers.

10. All mechanical piping, fittings and supports.

11. All ductwork and piping insulation systems.

12. All mechanical equipment controls.

13. Electrical related submittals.

14. All components of roofing.

b. Government Approval required for:

1. Government approved submittals as required by UFGS specification sections edited by the DOR.

2. Electronic Security System

3. HVAC Controls (UFGS 23 09 13 and 23 09 23.02 and associated specifications)

4. HVAC Testing, Adjusting, and Balancing (UFGS 23 05 93)

5. Fire Protection related submittals pertaining to fire alarm & detection systems

1.2 Submit the following construction submittals, approved by the DOR, to the Government for Surveillance (Government Surveillance does not prevent the Contractor from proceeding with construction, but allows the Government an opportunity to confirm the submittals have been approved by the DOR, and are in accordance with the contract documents):

a. Submit doors, frames and hardware.

b. Submit all wall components.

c. Submit Performance Verification and Acceptance Testing required by IBC, UFGS or this

RFP.

d. All components of RF Shielding.

e. All finish materials/colors.

PART 2 GENERAL REQUIREMENTS - Page 11

f. Submit Structural Shop Drawings and structural product data.

1.3 Construction Submittal Process

Provide to the Government submittals as listed. See Section 01 33 10.05 20 "Design Procedures" for specific design and construction submittal format and approval and surveillance requirements.

Design drawings may be prepared more like shop drawings to minimize construction submittals after final designs are approved. Therefore, the Contractor is encouraged to prepare and submit with the design drawings, appropriate connection, fabrication, layout, and product specific drawings.

a. QC Plan, prior to Design/Construction (may be phased).

b. Construction submittals, prior to construction, approved in accordance with QC Plan, the DOR or QC Specialist is the approving authority for submittals unless otherwise indicated.

c. Sustainability Action Plan (and Sustainability Notebook when required) in accordance with 01 33 29.05 20 Sustainability Reporting for Design-Build. – NOT APPLICABLE

d. DOR-approved construction submittals identified for Government surveillance (typically Fire Protection system and Life Safety submittals). Stamp the submittals "FOR SURVEILLANCE ONLY." Submit Surveillance submittals to the Government prior to starting work for that item. Submittals required for surveillance will be returned only if corrective actions are required.

e. Safety Data Sheets (SDS) as applicable.

f. Baseline Schedule: due prior to PAK.

g. Environmental Protection Plan, prior to start of the work.

h. Contractor Safety Self-Evaluation Checklist.

i. Accident Reports - submit if incidence occurs.

j. Accident Prevention Plan and Activity Hazard Analysis: Submit prior to construction.

k. Schedule of Prices, initial due 21 calendar days after award and a detailed due prior to construction.

l. Record Drawings, due at Beneficial Occupancy

m. Operation and Maintenance Information: Due prior to testing as applicable, no later than 30 calendar days before Beneficial Occupancy.

n. Licenses and Permits: Per this section and Part 4.

o. Completed High Performance and Sustainable Building (HPSB) compliance checklists in accordance with UFC 1-200-02, High Performance and Sustainable Building Requirements and UFGS Section 01 33 29.05 20 Sustainability Reporting for Design- Build. Attach completed HPSB Checklist to Interim DD 1354. – NOT APPLICABLE

p. DD Form 1354:

PART 2 GENERAL REQUIREMENTS - Page 12

Prepare a Draft and Interim DD Form 1354, TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY, in accordance with UFC 1-300-08. Coordinate the identification of appropriate asset construction categories with the Contracting Officer and the Real Property Accounting Officer.

1) Draft DD Form 1354. DOR must determine applicable real property assets broken out by construction categories and submit a "Draft DD Form 1354" for Government approval as a part of the Design Analysis included with the Prefinal Design submittal.

"Draft DD Form 1354" must include all quantities and units of measure, but does not require cost breakdown. The Real Property Accountable Officer (RPAO) will provide the first draft of the DD1354 to the contractor with RPUIDs and CCNS on it.

2) Interim DD Form 1354. Contractor must coordinate with the DOR and update the Draft DD Form 1354 submission to include any additional assets, improvements, or alterations that occurred during construction. Use the Draft DD Form 1354 [and the UFGS Section 01 20 00.05 20, Price and Payment Procedures] to identify costs. The costs and quantities must align with the RPUID and unit of measures listed on the RPAO's draft 1354. Submit the final draft Interim DD Form 1354 to the Government for approval 30 days prior to the Beneficial Occupancy Date (BOD). If modifications to the Interim DD Form 1354 are required by the Government, the corrected version must be submitted prior to the BOD.

3) When documenting demolition work, the DD Form 1354 must list the quantitative data associated with this work as a negative value to show the cost should be deleted from the Navy asset data store. Coordinate with the Installation Real Property POC to assist in determining the negative value for demolition work. There are two ways to account for the demolition portion of the project and to document the reduction of real property: (1) attach an Authorization for Demolition form 18 (Service-specific) to the DD Form 1354 to document category codes and quantities of demolished real property. These should be listed separately from constructed/transferred item numbers; or, (2) indicate, as additional DD Form 1354 item numbers, all demolished real property facility numbers and category codes using negative numbers (shown in parenthesis) for units of measure, and in block 18 indicate N/A for costs. Disposal cost within the footprint of the project is added into total construction cost of new facility prompting the demolition.

q. Construction Submittals:

1) In addition to the design submittals noted in Section 01 33 10.05 20, construction submittals will be required. The list of required submittals will be generated from the Contractor-prepared specifications and indicated in the submittal register.

2) Shop drawing submissions will be governed by UFGS 01 33 00.05 20 Construction Submittal Procedures, available on the Whole Building Design website (www.wbdg.org ).

Contractor must assume a 14 day review period, and provide 3 hard copies of all submittals (in addition to electronic submittals) to be submitted to the Construction Manager.

r. Equipment Inventory Form: Prior to demolition of existing or installation of new. (See PART 6 – ATTACHMENTS for the Equipment Inventory Form to utilize).

1.4 Operations and Maintenance Information (OMSI)

Provide operation and maintenance data on all equipment and material installed under this contract due to prior testing as applicable, but no later than Beneficial Occupancy. This data must be incorporated in an operations and maintenance manual.

http://www.wbdg.org/

PART 2 GENERAL REQUIREMENTS - Page 13

Submit Operations and Maintenance data packages, manuals and training according to UFGS 01 78 23 OPERATION AND MAINTENANCE DATA. Quantity and format will also be discussed at the PAK meeting.

Operation and maintenance data information will be furnished by the manufacturer, or the system provider, to the equipment operator and maintenance personnel. Operating and maintenance personnel need this data for the safe and efficient operation, maintenance and repair of the item.

1.5 Licenses and Permits

Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. See "Permits Record of Decision" (PROD) form for list of permits. Comply with all applicable federal, state, and local laws, and base regulations and procedures. Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see FAR 52.236-7, Permits and Responsibilities). Coordinate permit applications with Navy or local environmental office.

The contractor must submit a complete PROD form with the first design submittal package. A blank PROD form can be obtained from the NAVFAC Design-Build website at the following link http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc . Contractor must determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form must be forwarded to the Government's Civil Reviewer and Environmental Reviewer.

Contractor is exclusively responsible for his full compliance with patent laws and must affirm that the company is licensed to use equipment and processes the company employs in this project.

1.6 Record Drawings

The as-built modifications must be accomplished by electronic drafting methods on the Contractor-originated DWG design drawings to create a complete set of record drawings. For each record drawing, provide CAD drawing identical to signed Contractor-originated PDF drawing that incorporate modifications to the as-built conditions. After all as-built conditions are recorded on the DWG files, produce a PDF file of each individual record drawing in conformance with FC 1- 300-09N. Electronic signatures are not required on record drawings.

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

1.1 Summary

This section includes requirements for contractor-originated design documents and design submittals.

1.2 Reference Standards

This RFP references published standards, the titles of which can be found in the Unified Master Reference List (UMRL) on the Whole Building Design Guide at the Unified Facilities Guide Specification (UFGS) Website. The publications referenced form a part of this specification to the extent referenced.

The advisory provisions of all codes, requirements, and standards are mandatory; substitute words such as "must" or "required" for words such as "shall", "should", "may", or "recommended," wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the "authority having jurisdiction" is http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc

PART 2 GENERAL REQUIREMENTS - Page 14 interpreted to mean Contracting Officer or Contracting Officer Representative. Comply with the required and advisory portions of the current edition of the standard at the time of contract solicitation.

Provide work in compliance with the following design standards and codes, as a minimum.

Government standards listed in this RFP take precedence over industry standards. The following list of codes and standards is not comprehensive and is augmented by other codes and standards referenced and cross-referenced in the RFP. Refer to Parts 3 and 4 for specific requirements within other UFC's.

a. U.S. Department of Defense (DoD) Unified Facilities Criteria (UFC)

UFC 1-200-01

DoD Building Code (General Building Requirements)

UFC 1-200-02

High Performance and Sustainable Building Requirements NOT

APPLICABLE

UFC 1-300-08

Criteria for Transfer and Acceptance of DoD Real Property

FC 1-300-09N Navy and Marine Corps Design Procedures

UFC 3-401-01

Mechanical Engineering

UFC 3-560-01

Electrical Safety, O&M

UFC 3-600-01

Fire Protection Engineering

UFC 3-810-01N

Navy and Marine Corps Environmental Engineering for Facility Construction

b. UFC 1-200-01

UFC 1-200-01, DoD Building Code is a hub document that provides general building requirements and references other critical UFCs. A reference to UFC 1-200-01 in the RFP document requires compliance with the Tri-Service Core UFCs. Refer to the UFC 1-200-01 for a complete list of all applicable Tri-Service Core UFCs at website location http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc . Contractor-originated design documents must provide a project design that complies with the Request For Proposal (RFP), FC 1-300-09N, UFC 1-200-01, UFC 3-810-01N, the Core UFCs, and other UFC's listed above.

1.3 Design Requirements

a. Provide design documents that include basis of design, design drawings and design specifications, reports and submittal register in accordance with FC 1-300-09N Navy and Marine Corps Design Procedures.

b. Design is the work necessary to ensure functionality, quality, and safety for critical facets of the project. Special coordination requirements such as for phone, LAN and cable, are included herein.

http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

PART 2 GENERAL REQUIREMENTS - Page 15

c. Provide key plans with North arrow and indicated area of work for all floor plans sheets.

Mechanical and Plumbing

d. The mechanical drawings shall indicate locations of all existing and new equipment to be TAB’d and schedules indicating associated performance for TAB purposes. In addition to the UFC required details, design specific details shall be provided for the following:

• New hot water reheat piping supports.

• Service clearances indicated around each new piece of equipment.

• Secure perimeter penetration details for existing and new piping and ductwork.

• New ductwork fitting/takeoff types and diffuser/grille connections.

• Ductless split system condensing unit roof mounting

• Ductless split system condensing unit refrigerant piping and electrical conduit roof penetrations.

• RF suspended ceiling system diffuser installation.

• RF suspended ceiling system return grille installation.

• RF ceiling penetration for plumbing and mechanical piping.

• RF wall penetration for ductwork, mechanical and plumbing piping installation.

• Ductwork “Manbar” and access door details.

The DDC control drawings shall indicate the existing controllers, control system points, architecture and sequences with integration of any new VAV terminal units. Provide control system legend and abbreviations as part of DDC drawings.

e. The deliverable HVAC load calculation submittal shall include ALL INPUT DATA along with the resulting output data.

f. Part 3 contains the project description, functional and performance requirements, scope items, and expected quality levels that exceed Part 4. Part 4 identifies design criteria, verification requirements, and performance and quality requirements of products.

g. Provide professional registration and design signing and stamping requirements per requirements of FC 1-300-09N, Design Procedures. ***Each design drawing must only be signed, sealed, and dated by the Registered Architect or Professional Engineer who is registered to practice in the particular field involved for work depicted on that drawing, and serves as the Designer of Record for work depicted on that drawing!*** Interior Designers must be NCIDQ certified per UFC 3-120-10 Interior Design. The design effort must be overseen by a Design Quality Control (DQC) Manager who will ensure that the design meets the requirements of this RFP. The DQC Manager will prepare a DQC Plan describing how the design process will ensure conformance to the RFP.

h. Provide a Contractor-originated design specification that in conjunction with the drawings, demonstrates compliance with requirements of the RFP. The specified products, materials, systems, and equipment that are approved by the DOR; submitted to the Government by the Contractor; and reviewed by the Contracting Officer must be used to construct the project. Prescriptive specification sections contained in RFP Part 5 must become a part of the Contractor-originated specification without modification. The Contractor must prepare design specifications that include a UFGS specification for each product, material, or system on the project. Organize the specifications using Construction Specification Institute (CSI) MasterformatTM .

***ON DRAWING SPECIFICATIONS WILL NOT BE ACCEPTED***

PART 2 GENERAL REQUIREMENTS - Page 16

Provide project specifications to include the following:

1. Provide the specification cover sheet with the professional seal and signature of the lead licensed architect or engineer of the project design team. Indicate the Contractor's company name and address on the specification coversheet.

2. Also as “a minimum”, the following “front end” (Division 0 and Division 1) specifications must be provided:

00 01 15 List of Drawings 01 11 00 Summary of Work 01 14 00 Work Restrictions 01 20 00 Price and Payment Procedures 01 30 00 Administrative Requirements 01 31 19 Post Award Meetings 01 32 16 Small Project Construction Progress Schedules 01 33 00 Construction Submittal Procedures 01 35 26 Governmental Safety Requirements for Design Build 01 45 00 Design and Construction Quality Control 01 50 00 Temporary Facilities and Controls 01 57 19 Temporary Environmental Controls 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data

The UFGS Specification sections listed above must be edited to accommodate the requirements of this DB/RFP. Edit only the bracketed items of these Front End Division 0 and Division 1 UFGS Specification Sections. Obtain approval from the Contracting Officer prior to the Prefinal Design Submittal for any edits to these sections other than edits to the bracketed items. Edits to any portion of these front end sections other than to the bracketed items are not permitted without prior approval of the Contracting Officer.

Technical Specifications (Divisions 02 and beyond) must be provided on materials/items that will be provided on the project. As a minimum, projects including DEMOLITION work must include UFGS Specification “02 41 00

DEMOLITION AND DECONSTRUCTION”.

3. Table of contents for entire specification.

4. Individual UFGS specification sections for each product, material, and system required by the RFP. Edit UFGS sections in accordance with RFP Part 3 and 4.

5. If proprietary information is provided or required, include a coversheets for the product, material, or system information that is being proprietarily specified. This information must comply with the related UFGS specification.

6. If proprietary information is provided or required, include highlighted and annotated Catalog Cuts, Manufacturer's Product Data, Tests, Certificates, Manufactures information and letters for each product, material, or system that is being proprietary specified.

7. Coordinated submittal register for all products, materials and systems with each design submittal. Provide a cumulative register that identifies the design and construction submittals required by each design package along with previous design submittals. The DOR must assist in developing the submittal register by determining which submittal items are required to be approved by the DOR.

Complete all fields in the final submittal register in order to obtain Government approval of the final design.

i. Identification of Manufacturer's Product Data Used as Specifications: Provide complete and legible catalog cut sheets, product data, installation instructions, operation and

PART 2 GENERAL REQUIREMENTS - Page 17 maintenance instructions, warranty, and certifications for products and equipment for which final material and equipment choices have been made. Indicate, by prominent notation, each product that is being submitted including optional manufacturer's features, and indicate where the product data shows compliance with the RFP. Attach this product data to the end of the applicable UFGS specification section that specifies the material.

j. Specification Software: Submit the final specification source files in SpecsIntact with a

Submittal Register generated in SpecsIntact.

k. Meet sustainability requirements per UFC 1-200-02 High Performance and Sustainable Building requirements and UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build. UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build must be included in Part 5 of all project RFPs. – NOT APPLICABLE

l. Submit design drawings/specifications, calculations and manufacturer's data to demonstrate compliance with contract requirements.

m. Provide hard and electronic copies of design submittal package(s) to allow the

Government 21 calendar days for reviews. The OnBoard review meeting must take place within 7 calendar days of issuance of Government design review comments. The Contractor must submit their DOR Responses to the Government Review Comments a minimum of 3 business days prior to the OnBoard Review Meeting. OnBoard Review Meetings will occur at the 35% and Pre-Final Review stages.