26R0131 P1476U Amendment 0004.pdf
PDF 851 KB Posted
- Attached to
- DESIGN-BUILD (DB), P-1476U NEW FIRE APPARATUS BAY CHEATHAM ANNEX, NAVAL WEAPONS STATION YORKTOWN, VIRGINIA
- Solicitation number
- N40085-26-R-0131
About this file
This is Amendment 0004 to a Design-Build (DB) Request for Proposals (RFP) for a new fire apparatus addition (P-1476U Fire Station Addition) at Naval Weapons Station Yorktown, Virginia. The amendment extends the proposal due date from May 27, 2026 to June 8, 2026 by 2:00 PM ET and clarifies that no additional pre-proposal inquiries will be accepted after this amendment.
The amendment provides updated technical documents including revised Site Concept Plans (REV 1), Government Baseline Building Performance Report Guide (REV 1), Life Cycle Cost Analysis (LCCA) for the P1476U Fire Station Addition, and NAVFAC High Performance and Sustainable Building Checklist Goals (REV 1). It modifies specifications addressing working hours (7:00 AM to 3:30 PM Monday through Friday only), Quality Control Manager duties (clarifying the QCM cannot serve as Site Safety and Health Officer or Superintendent), building commissioning responsibility (assigned to government-hired independent commissioning firm), and room requirements including apparatus bay fall protection hardpoints, drinking fountain with bottle filling station (ABA compliant), secure storage with linoleum tile flooring and acoustical ceiling panels, and emergency fixtures at 85°F. The amendment adds new plumbing specifications for drinking fountains and coolers, modifies floor finish requirements in storage areas, and provides 223 pre-proposal inquiry responses addressing sustainability requirements, LCCA methodology, fire station design criteria per UFC 4-730-10, HVAC systems, electrical infrastructure, hazardous materials handling, FF&E funding (Option Item 0004 funded through O&M as a separate modification), and various technical clarifications on building systems, site logistics, and construction scope.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
N40085-26-R-0131
SECTION SF30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0004
This amendment is issued to incorporate the following:
1. Extend the proposal due date from 27 May 2026 to 08 June 2026
2. Provide continuation sheet for drawings and specifications (Enclosed)
3. Provide updated ATT(04) Site Concept Plans - REV 1 (attached separately)
4. Provide updated ATT(07) Government_Baseline_Building_Performance_Report_Guide-REV 1
(attached separately)
5. Provide ATT (18) LCCA P1476U Fire Station Addition (attached separately)
6. Provide ATT (19) NAVFAC HIGH PERFORMANCE AND SUSTAINABLE BUILDING
CHECKLIST – GOALS- REV 1 (attached separately)
7. Provide additional PPI Responses and updated PPI Responses
1. The proposal due date is extended from 27 May 2026 to 08 June 2026 by 2pm ET.
PLEASE NOTE: NO ADDITIONAL PRE-PROPOSAL INQUIRIES WILL BE
ACCEPTED.
2. Continuation Sheet for Drawings and Specifications (Enclosed)
DRAWINGS:
RFP - PART 6, ATTACHMENTS
DELETE: ATT (04) Site Concept Plans
ADD: ATT (04) Site Concept Plans – REV 1
DELETE: ATT (07) Government_Baseline_Building_Performance_Report_Guide
ADD: ATT (07) Government_Baseline_Building_Performance_Report_Guide- REV 1
Includes: Hourly Schedule Input
Yorktown Weather Data
Design Load Space Summary Report
Baseline Air System Inputs
ADD: Attachment:
ATT (18) LCCA P1476U Fire Station Addition
ATT (19) NAVFAC HIGH PERFORMANCE AND SUSTAINABLE BUILDING
CHECKLIST – GOALS- REV 1
SPECIFICATIONS:
Section 01 14 00 1.4.2 Working Hours
DELETE “between , and 7 a.m. to 3:30 p.m. on Saturday.” and REPLACE with: “between 7 a.m. to
3:30 p.m., Monday through Friday.”
Section 01 45 00 1.6.1.1 Duties
DELETE “and to serve as the Level three Site Safety and Health Officer (SSHO) as detailed in Section
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.” and REPLACE with: “QCM cannot be the
Superintendent or SSHO”
SECTION 01 35 261.8.3 Additional Requirements
DELETE “The Level Three SSHO must not serve as the Quality Control Manager. The Three SSHO must not serve as the Superintendent.”
and REPLACE with: “The SSHO must not serve as the Quality Control Manager. The SSHO must not serve as the Superintendent.”
SECTION 01 33 29 NAVFAC HIGH PERFORMANCE AND SUSTAINABLE BUILDING
CHECKLIST – GOALS
DELETE attached NAVFAC HIGH PERFORMANCE AND SUSTAINABLE BUILDING
CHECKLIST – GOALS (pages 129-133) and REPLACE with: “ATT (19) NAVFAC HIGH PERFORMANCE AND SUSTAINABLE
BUILDING CHECKLIST – GOALS- REV 1”
RFP:
Part Three: Project Program Combined
2.0 PROJECT OBJECTIVES
Paragraph 2.3.4 Building Commissioning
DELETE “Provide commissioning to meet requirements identified in Section 01 91 00.22 Total
Building Commissioning, and UFC 1-200-02 High Performance and Sustainable Building
Requirements.”
REPLACE with: “The government will provide 3rd party commissioning to meet requirements identified in Section 01 91 00.22 Total Building Commissioning, and UFC 1-200-02 High
Performance and Sustainable Building Requirements.”
5.0 Room Requirement Forms
ADD the following to 5_Room_Requirements_Forms_FS -FINAL
100 - APPARATUS BAY
Other/special requirements: ADD “Contractor to provide 2 fall protection hardpoints attached to metal building structure roof structure. Structure must be designed for these anchors.”
“D201006” Drinking Fountain. Quantity:1 Description: Drinking fountain with bottle filing station. Must be ABA compliance.
106 - SECURE STORAGE
“E20” Furnishings. ADD “freestanding” in front of “shelf”.
“C3020” Flooring. DELETE “Sealed concrete with resilient base” and REPLACE with “Low-maintenance resilient linoleum tile flooring with resilient rubber base.”
“C3030” Ceilings. DELETE “painted GWB” and REPLACE with “ACP”.
6.0 ENGINEERING SYSTEMS REQUIREMENTS
C103006 Shelving:
DELETE from Section “C10 Interior Construction”
ADD the following section to C3020 FLOOR FINISHES:
Provide resilient linoleum tile flooring in storage areas for floors with high durability, low to moderate maintenance, anti-static and antimicrobial requirements. This product is made from readily renewable, natural raw materials including linseed oil, flour and resin binders double calendared onto natural jute backing. Pattern and color must extend throughout thickness of material. Seal linoleum using manufacturer's recommended sealer for commercial application. A manufacturer's 5-year warranty is required.
D201090 Emergency Fixtures:
DELETE “Provide tepid water (60°F to 100°F) with water tempering valve assembly.” and
REPLACE with: “Provide tepid water 85°F with water tempering valve assembly. The DOR is instructed to use 40°F as the entering domestic water temperature.
ADD the following section to 6_ESR_D20 Plumbing
“D201006 Drinking Fountains and Coolers
Provide drinking fountain with bottle filling station. Refer to Room Requirement Section for number and type.”
3. Updated ATT(04) Site Concept Plans - REV 1 is provided with this amendment (attached separately).
4. Updated ATT(07) Government_Baseline_Building_Performance_Report_Guide-REV 1 is provided with this amendment (attached separately).
5. ATT (18) LCCA P1476U Fire Station Addition is provided with this amendment (attached separately).
6. ATT (19) NAVFAC HIGH PERFORMANCE AND SUSTAINABLE BUILDING CHECKLIST
– GOALS- REV 1 is provided with this amendment (attached separately).
7. Pre-Proposal Inquiry Responses
PPI
Page Section Paragraph Question Response
3 (updated response)
Site plans appear to show gas service around the area of work. Can gas be utilized for heating and water heating? Everything in the RFP appears to be direct to 100% electric.
Baseline LCCA was designed to be 100%
Electric. Per UFC 1-200-
02 Change 03, Section 4-2, while the initial baseline
LCCA is prepared during
RFP development, the
UFC explicitly mandates:
"refining the LCCA at each design submittal, as well as during construction if there are significant changes to the system."
If AE-2 submitted building systems that are different from those prescribed in the RFP, AE-2 must submit a detailed proposed alternative, with supporting LCCA data, for
Government evaluation during submittal process. If the AE-2 needs to resubmit an LCCA, follow the D-B-
B procedures.
If AE-2 chooses to propose an alternative system that increases first costs, supporting documents must be submitted in accordance with the above paragraph. However, the contractor is required to provide the systems prescribed in the RFP.
Deviations are at the
Government’s discretion, and no change orders for increased first costs will be issued to the Contractor-elected deviations unless formally accepted by the
Contracting Officer.
9 Is PV solar to be excluded?
Please see the Initial HPSB
Checklist and the Initial
LCCAs for the energy systems, renewable energy, and Solar Hot Water provided with Amendment
0004.
10 (updated response)
Typically for new buildings, UFC1-200-02 requires an LCCA to be performed in order to select an HVAC system type. Since the system types are spelled out in the RFP, will an LCCA be required?
Yes, an LCCA is required.
The system outlined in
ESR_D30 serves as a representative model to demonstrate a viable solution for the project's scope.
11 483 sustainability
This paragraph requires
30% energy use reduction over baseline building. With HVAC systems spelled out in the
RFP, in order to achieve those savings, the use of
Solar PV array may be required, but those appear to be omitted in the RFP.
Solar PV is required to be provided in accordance with the annual production rate referenced by UFC 1-
200-02 (refer to IgCC
2018) when LCCE as a standalone system. When considering the 30% reduction below baseline, PV may be employed to reach the 30% requirement if the whole building strategy is found to be
LCCE. Note that the system analysis must be provided for the min.
amount required by UFC, but the whole building amount of PV is not limited to the min. amount, a larger array may be provided to improve the cost/kW which may prove beneficial to the whole building LCCA. In accordance with ASHRAE
90.1-2019, PV may not be used to achieve more than
5% of the energy savings
(see ASHRAE 90.1 for specifics) to meet the requirements of ASHRAE
90.1, but this 5% limit is not applied to the required
30% savings below baseline.
16 (updated
511-
100 Apparatus Bay does not indicate any requirements for SCBA
(self-contained breathing apparatus) equipment or maintenance. UFC 4-
730-10, Table 4-1 requires SCBA connections. Will SCBA equipment and facilities
No SCBA equipment or facilities are required. Only
SCBA connections are needed for the new bay.
17 (updated
100 Apparatus Bay has a requirement for 3" water line with 2-1/2" ball valves in each truck bay.
Ball valves can be closed quickly resulting in severe water hammer.
Will multi-turn gate valves be acceptable or will industrial style water hammer arrestors be required?
Must follow UFC 4-730-
10 Table 4-1 Plumbing requirement. Use 1/4 turn ball valves with water hammer arrestors or multi-turn gate valves.
18 (updated
100 Apparatus Bay requires an eyewash station. UFC 4-730-10 requires a combination eye/face wash and drench shower. Which type is
Both. Follow UFC 4-730-
10 including, but not limited to, Table 4-1, 4-11, 4-12, 4-13, 4-33, Plumbing requirement.
19 (updated
100 Apparatus Bay - The eyewash station requires tepid water which is defined by ANSI Z358.1 as 60dF to 100dF. The ground water temperature is 62F.5dF as determined from the Williamsburg
Design Data. What water temperature is required for tepid water applications to emergency safety equipment?
Provide 85°F for emergency fixture temperature. The DOR is instructed to use 40F as the entering domestic water temperature.
30 (updated
UFC 4-730-10
3-6.2
Is a drinking fountain with bottle filling station
Drinking fountain with bottle filling station is required and must meet
ABA standard. Please see
Continuation Sheet
32 (updated
D202003
Para. D202003 requires a heat pump domestic water heater. Are other types of water heaters as listed in Part 4, PTS_Section _D20 para.
D202003 1.2 acceptable as an alternative?
Yes. Systems listed in Part
4 is acceptable if it is more
LCCE.
39 573 &
585-
D50 & F10
Engineering
Requirements D50 and
F10, Metal Building require seismic protection for Importance Factor
Cumulative weight of the hanger supported utility lines/equipment must be accounted when verifying seismic resistance for the
IV. Do all systems, including fire sprinkler require seismic protection?
structure as whole as well as for the supports. Lateral supports must be able to provide adequate resistance to the supported elements to prevent damages of the pipe fittings during earthquake events. Similarly vertical supports stiffness must be assured to support potential vertical movement of the pipelines during earthquake, to prevent damage of the supported systems. These requirements apply to the electrical conduits and their connections.
Design of the utility lines/equipment support must account maximum local deflections as well as in building as whole under extreme load conditions, to prevent fittings and connections damages under such conditions.
41 (updated
100 Apparatus Bay will be heated with electric infrared heaters. Will they operate 24/7 so that the bay can be considered heated, or will they only operate when occupied and therefore the apparatus bay might freeze, which will require a dry-pipe sprinkler system.
Electric infrared heaters must be thermostatically controlled to prevent the bay from ever dropping below freezing.
49 512
Table 100
C3020
Apparatus Bay - Floors call for Resinous floor with integral base. UFC
Please see RFP Part 4 -
C302009 1.2 that provides the tech specs.
4-730-10 Table 4-1
Finishes calls for 1-part or 2-part water-based epoxy concrete paint, in a slip-resistant, semi-gloss, light color finish. Please confirm a resinous floor is preferred and if any fuel resistive properties are required.
50 513
E20
Apparatus Bay furnishings call for Hose storage rack and drying rack. UFC 4-730-10
Table 4-1 Furnishings
Fixtures & Equipment
(FF&E) calls for Ice
Machine (with fresh water dispenser) and a storage cabinet near mop sink for cleaning supplies. Please confirm required furnishings and provide data, including size requirements for all required FF&E.
All requirements within the UFC are mandatory and include the FFE indicated on the room requirement sheets.
Technical Specifications for FFE and construction should be gathered from
User during design process.
51 515
Table 102
D2010
Protective Equipment
Laundry - Plumbing fixtures calls for a drip dryer rack. Provide data for rack.
Technical Specifications should be gathered from
52 516
Table 102
Protective Equipment
Laundry - Furnishings calls for a stainless-steel folding table. Please provide size requirements. UFC 4-
730-10 Table 4-5 calls for a wall-mounted hanging rack. Confirm if this is required and provide data if required.
All requirements within the UFC are mandatory and include the FFE indicated on the room requirement sheets.
Technical Specifications for FFE and construction should be gathered from
53 518
Table 103
PPE Gear
Storage/Maintenance -
Furnishings call for
Mobile PPE gear lockers.
UFC 4-730-10 Table 4-2 calls for 24 inch by 24 inch by 6 ft high wire mesh metal lockers. It also calls for a work bench surface for self-inspection of gear. Please confirm required furnishings and provide data for all.
and include the FFE indicated on the room requirement sheets.
Technical Specifications for FFE and construction should be gathered from
54 519
Table 103A
Function/ adjacencies
UFC 4-730-10 Table 4-
11 Casework/built-in
Equipment calls for a bench and lockers. Please confirm that these are not required for this project.
and the FFE indicated on the room requirement sheets. Technical
Specifications for FFE and construction should be gathered from User during design process.
56 524
Table 106
Furnishings call for a shelf and locking drug storage cabinet. Please provide data for both.
UFC 4-730-10 Table 4-7 calls for a lockable medical refrigerator.
Please confirm this is not required.
and the FFE indicated on the room requirement sheets. Technical
Specifications for FFE and construction should be gathered from User during design process.
57 525
C3020
Floors call for sealed concrete with resilient base. UFC 4-730-10
Table 4-7 calls for low-maintenance resilient sheet or tile flooring with rubber base. Please confirm which finish is preferred.
Comply with UFC by providing low-maintenance resilient tile flooring with rubber base.
See Continuation Sheet
58 (updated
C3030
Ceilings call for Painted
GWB. UFC 4-730-10
Table 4-7 calls for suspended acoustical ceiling panels. Please confirm which finish is preferred.
Bid per RFP on room requirement sheets. Please see Continuation Sheet provided with Amendment
0004 which replaces painted GWB with ACP.
61 27
3.2.3
UFC 4-730-
Is Fall Protection required in each stall of the Apparatus Bay?
An active fall protection system selected by the Fire
Chief is required. Provide
2 fall protection hard points attached to the metal building structure. The structure must be designed for these anchors.
Technical Specifications should be gathered from
User during design process. Please see
Continuation Sheet
62 483
Sustainability
The 5th Paragraph in
"Sustainability" states:
The Navy will hire an outside contractor to perform 3rd party commissioning to meet requirements identified in
Section 01 91 00.15 20
Total Building
Commissioning, and
UFC 1-200-02 High
Performance and
Sustainable Building
Requirements."
However, Paragraph
2.3.4 Building
Commissioning states:
Provide commissioning to meet requirements identified in Section 01
The Government has hired an Independent
Commissioning Firm.
They will be responsible for commissioning services. Please see
Continuation Sheet
91 00.22 Total Building
Commissioning, and
UFC 1-200-02 High
Performance and
Sustainable Building
Requirements. Please confirm who is responsible for providing commissioning services.
63 614
Part 3 - Chapter
G4010
G4010 states "Install a new 45’ Class 2 pole with a 75kVA transformer twenty feet closer to the road.
Connect the existing
120/240 volt, single phase, three wire, 60
Hertz electrical system service drop feeding the fire station power to the new transformer and transfer meter to the new pole. Install a new riser fed from the new transformer overhead at
Pole 912-1 and extend to the project site underground to a service entrance rated disconnect and meter." Please confirm that you want a
120/240 volt, single-phase service. Where is
Pole 912-1 located?
Confirm that service to the new building is from a new pole and service to existing building is from existing pole 912-1. Can we just use the existing pad-mounted transformer on the site for power? If so, do you have any existing loads available?
Provided per section G40.
Existing loads can be provided after award.
64 576
Part 3 - Chapter
D509002
D509002 for the emergency generator states "Provide with a full subbase fuel tank." How many hours/days of fuel is required for this facility?
EPSS is a Level 2, Class
72, Type 60.
Please identify the approved contractor trailer location, laydown area, employee parking area, dumpster location, crane setup areas, material delivery route, and haul route. Confirm whether off-site laydown will be required due to limited space around
CAD119.
Refer to revised site diagram for laydown area.
Additional areas are needed and final project limits to be determined during design.
68 Please identify the approved contractor trailer location, laydown area, employee parking area, dumpster location, crane setup areas, material delivery route, and haul route. Confirm whether off-site laydown will be required due to limited space around
CAD119.
Refer to revised site diagram for laydown area.
Additional areas needed and final project limits to be determined during design.
74 Line Item 0001 states the
Base Price is the subtotal of Line Items 0001A through 0001E. However, Line Item 0001A appears to cover only Supporting
Facilities to the 5-foot line outside the building, while 0001B through
0001E are unit-priced
Please see Amendment
0003 for revised Price
Proposal Form- REV1, Primary Facilities are covered under Line Item
0001A.
site/soil/debris items.
Please confirm whether the contractor is to include the Primary
Facility/building cost, including PEMB, building foundations, slab, interior construction, MEP, fire protection, overhead doors, finishes, and all work inside the 5-foot line.
75 Please confirm whether the 1,500-ton estimated quantity in Line Item
0001B includes only contaminated/impacted soil media or also includes surplus non-contaminated soil media from planned excavations. The bid note states that removal and disposal of all surplus non-contaminated soil media encountered within planned excavations is covered under Line Items
0001B and 0001C. Please clarify how non-contaminated soil is to be measured, paid, and distinguished from impacted soil.
Base bids on the assumption that all surplus soil media is contaminated.
The quantity in the Price
Schedule is revised in
Amendment 0003 to 4,000
TONS.
76 For Line Item 0001B, please confirm the required disposal facility classification for impacted soil media:
Subtitle D facility accepting
PFAS/petroleum/metals-
Bid per the RFP: Part 3, 3.2.13.1 impacted material, Subtitle C hazardous waste landfill, thermal treatment facility, or contractor-determined based on sampling and receiving-facility approval.
77 For Line Item 0001B, please define the minimum Government-required sampling frequency, analyte list, laboratory method, turnaround time, and approval process before impacted soil may be transported off site. If the receiving facility requires additional analytes, confirm whether those costs are included in the unit price and whether delays waiting on facility-specific approval are compensable.
Bid per the RFP.
78 For Line Item 0001C, please confirm the required treatment standard, discharge criteria, definition of
“non-detect,” approved discharge/disposal location, required sampling frequency, and whether treated water may be discharged on site after approval or must be hauled off site.
80 Please confirm whether
Line Item 0001D applies to unsuitable soils encountered below building footings only, or also applies to proof-rolled subgrades for slabs, concrete aprons, heavy-duty asphalt pavement, LID features, utility trenches, and other site improvements.
81 For Line Item 0001E, please confirm how the
1/2 CY threshold will be determined in the field, whether reinforced concrete, abandoned pipe, asphalt, creosote-treated timber, and mixed debris are all paid under this line item, and whether replacement backfill is included in the unit price.
82 Please confirm whether buried debris encountered outside planned excavation limits, but requiring removal to complete the work, will be compensated under
Line Item 0001E or handled as a differing site condition.
85 For Option Item 0003, please clarify the required wall assembly when using the 10-foot-high CMU exterior wall backup system in lieu of insulated metal panels.
Confirm whether this option includes changes to foundations, PEMB
1.0 PROJECT
DESCRIPTION states
"provide 10’ High
Concrete Masonry Unit
(CMU) Exterior Cavity wall composed of split face
CMU exterior veneer, veneer anchors, foam board insulation, vapor barrier, and CMU backup girts/framing, exterior veneer/panel attachment, insulation, air/vapor barrier, interior finishes, lintels, bond beams, reinforcing, control joints, and MEP penetrations.
wall construction." PEMB and Foundation design loads in the base bid must support the bid option. All other items must be included in the bid option.
88 For Option Item 0004, please provide the FF&E list, design responsibility, procurement responsibility, installation requirements, storage requirements, and whether the contractor is responsible for field verification, blocking/backing, electrical/data coordination, anchorage, and final placement.
GC must provide a complete, functional building. For bidding purposes, GC will only provide a HAR percentage which will be based on the final cost of the FFE package. Reference E20 for FFE details. It is the responsibility of the GC's
Professional Interior
Designer to provide the
FF&E design/layout, technical specifications, as per User's requirements, and provide the completed design process with an
RFQ bidding package.
Including technical specs, government estimate, release the RFQ and prepare the Best Value
Determination. It is the
GC's responsibility to procure FFE once bid option has been awarded, installation requirements, store as needed but work to align delivery with building construction date, and field verification is the
GCs responsibility.
Blocking/backing for all
FFE items will be included in the construction cost and indicated by the GC's
Interior Designer during design. Electrical/data coordination is the responsibility of the GC and their subs. Anchorage is the responsibility of the
GC and should be included in the construction cost.
Final placement of the FFE is the responsibility of the
GC's hired furniture dealership.
92 Because the RFP states indirect costs such as meetings, submittals, surveys, haul-road/storage-yard maintenance, dust control, security, overhead, profit, and field office salaries are not to be cost-loaded as individual pay items.
Please confirm how the
Government wants bidders to structure mobilization, general conditions, and environmental controls in the proposal/payment breakdown.
The contractor cannot be paid anything other than bond and insurance until we have an approved
Schedule and associated
EVR/SOV. Regarding indirect costs, they should be distributed among all other line items. No exceptions.
93 Please confirm whether any limited early procurement, survey, potholing, or environmental planning work may proceed before acceptance of the complete cost-loaded
NAS and Earned Value
Report.
Efforts may proceed, but if they need to accomplish early procurement, survey, potholing, or environmental planning, they need to submit that portion of the NAS and
EVR for Government approval.
94 Please confirm whether
Season II TAB, endurance testing, post-occupancy testing, or commissioning activities are required after beneficial occupancy, and whether these activities extend the contractor’s required supervision, warranty, or closeout duration.
Endurance testing must be completed prior to BOD, while Season II TAB is a deferred requirement to be performed after BOD.
Commissioning for
Functional performance testing activities must be completed prior to BOD;
any deferred testing must be explicitly documented and approved in the commissioning Plan.
These activities do not extend the requirement for full-time site supervision or delay the start of the facility.
98 Please confirm the hazardous-material assumptions for bidding:
asbestos, lead, cadmium, chromium, PCB-containing coatings/sealants, mercury-containing equipment, contaminated soil, and groundwater.
Are bidders to assume all impacted paints are lead/cadmium/chromium-containing and all impacted sealants/coatings are
PCB-containing until proven otherwise?
Bid per RFP. See ESR F20 and Hazmat Report in Part
6.
99 Please confirm the required scope and duration for the Private
Qualified Person, including whether the
PQP must be onsite full-time during all
The PQP is only required to be on-site for hazardous building component abatement. See Hazmat
Specs in Part 5 for requirements for specific demolition/excavation activities or only during hazardous-component work.
hazardous building materials. Bid per the RFP.
100 Section 02 41 00 states storage of removed materials on the project site is prohibited. Please clarify whether temporary roll-off containers, covered dumpsters, regulated waste containers, and soil stockpiles awaiting test results are permitted within the approved laydown area.
These are permitted to be stored within the approved laydown area.
103 Please confirm whether
PPE gear lockers, wire-mesh lockers, composite plastic lockers, locker shelving, hooks, and related storage systems are Base Bid construction contract scope or FF&E
Option Item 0004 scope.
Affixed items such as wire-mesh lockers, composite plastic lockers, locker shelving, hooks and related storage systems would be considered part of the base bid contract.
Items such as mobile PPE gear storage lockers, equipment, and shelving units would be considered the FF&E package.
105 Please provide the
FF&E/equipment list for
Option Item 0004 and confirm whether PPE extractor, PPE drying cabinet, stainless-steel folding table, drying racks, gear lockers, shelving, and specialty fire station equipment are
Base Bid construction
Refer to Space Tabulation chart. [See RFP pg. 507]
Construction Items: Hose storage rack, recessed entrance mat, PPE drying cabinet, locking drug storage cabinet.
FF&E Items: PPE extractor, dryer, drying rack, stainless-steel scope or FF&E Option
Item 0004 scope.
laundry folding table, mobile PPE gear storage lockers, shelving, and equipment.
107 The room requirements identify sealed concrete and slip-resistant sealed concrete as floor finishes.
Please confirm whether any resinous epoxy flooring system is required, or whether sealed/slip-resistant concrete is acceptable for all listed rooms.
See PPI #49 referencing
Apparatus Bay floor finish.
113 Please provide or confirm the planned excavation limits used for Line Items
0001B, 0001D, and
0001E. Do planned excavation limits include building foundations, slab subgrade, apron subgrade, utility trenches, LID/stormwater features, pavement replacement areas, and sidewalk areas?
Bid per RFP.
116 For Line Item 0001B, required disposal facility classification for impacted soil media:
Subtitle D facility accepting
PFAS/petroleum/metals-impacted material, Subtitle C hazardous waste landfill, thermal treatment, or contractor-determined based on
Bid per RFP: Part 3, 3.2.13.1.
sampling and receiving facility approval.
118 For Line Item 0001C, required treatment standard, sampling frequency, definition of
“non-detect,” approved discharge location, and whether treated water may be discharged onsite or must be hauled offsite.
119 If soil or dewatering effluent cannot be hauled, discharged, or disposed until test results and
Government approval are received, will resulting standby, storage, tank rental, or schedule impacts be compensable?
123 For Bid Option 1, please confirm whether
“required power and data connections” for the two additional overhead doors include empty raceways only, full conductors/cabling, controls integration, fire alarm/security interface, door operators, and testing.
Confirmed. PEMB framing, wall panels, structural reinforcing, power/data rough-ins, controls rough-ins, fire alarm rough-ins, and future rear overhead door openings are to be framed but infilled and are part of the base bid.
127 Please confirm all slab areas required to slope to drains, including apparatus bay, PPE laundry, decontamination, mechanical room, and fire riser room.
Room requirement sheets lists which slab on grade must slope to drain. Bid per RFP.
133 Please confirm whether roof drainage discharges to grade, connects to storm piping, or ties into
LID/stormwater facilities.
Provide roof drainage in accordance with UFC 3-
201-01.
141 Please provide required coefficient of friction, texture standard, and product performance criteria for slip-resistant sealed concrete in wet/service areas.
In accordance with DOT, standard regulations and codes are referenced in
Part 4, performance spec section.
142 Please confirm required coating systems for abuse-resistant GWB, moisture-resistant GWB, CMU, hollow metal, exposed steel, and wet-room ceilings.
Refer to Part 4 sections
C1010, C3010, C101003 and in accordance with
Gypsum Association GA
214, GA216, and GA224.
144 Please confirm whether a tempered combination eye/face wash and drench shower, foot-operated mop sink, mop rack, hose bibs, and hose reel are required in the final project scope.
Confirmed.
149 Please confirm whether
Season II TAB is required and whether it may occur after beneficial occupancy without delaying final payment or closeout.
Season II TAB is required.
Please refer to Part Two
General Requirement specification section 01 20
00 1.3.3 Schedule
Requirements for HVAC
TAB for payment or closeout.
150 Please confirm sprinkler hazard classification, design density, water supply/flow test basis, See D4020 for Water
Supply and Backflow
Assembly criteria. See
D4040 for Sprinkler backflow requirements, and whether a fire pump is required.
system design criteria.
Based upon preliminary flow test data, a fire pump is not anticipated but should be confirmed by contractor flow test and hydraulic calculations.
151 Please confirm whether the new fire alarm system must tie into the existing
CAD119 panel, a base-wide reporting system, or a new standalone panel.
See D4010 for Existing
Building FACP interface.
Base-wide reporting is required per D4010.
Provide DACT over campus phone system to communicate to Norfolk
Naval Station Regional
Dispatch Center.
152 Please identify required interfaces between fire alarm, HVAC shutdown, CO/NO₂ detection, overhead doors, security contacts, mass notification, and sprinkler flow/tamper monitoring.
Provide required interfaces per UFC 3-600-01 for fire related systems. Monitor
Emergency generator with fire alarm system per UFC requirements.
153 Please confirm whether an emergency generator is required for this project, which loads must be connected, and whether the generator is
Base Bid construction scope.
Provide and install new generator and Automatic transfer switch per Part 3
Chapter 1 Electrical
Requirements. Generator is part of the base bid construction scope.
Generator loads must meet
UFC requirements.
154 Please confirm whether the new pole-mounted transformer is
Government/utility-furnished or contractor-furnished, and define contractor responsibility for primary/secondary
Provide all equipment and infrastructure as required in ESR G40. The contractor is responsible for all construction and appurtenances for a complete and usable system.
conduits, conductors, trenching, grounding, and coordination.
155 Please confirm whether a complete lightning protection system is required on the PEMB and covered walkway and whether UL Master
Label certification is required.
Lightning protection system is not required.
156 Please identify the telecom demarcation point, cabling pathway, telecom room/equipment requirements, NMCI coordination requirements, and whether fiber splicing/testing is included.
Telecom infrastructure plans is CUI and will be given only to the awarded bidder during the design phase. Provide telecom
&NMCI coordination as required for a fully functional building. There are existing fiber lines going into CAD119. Fiber splicing and testing are only required if the lines are rerouted due to the new building. Bid per RFP.
159 Please clarify whether the
Government or contractor provides the
Commissioning
Authority, and define contractor trade support required for pre-functional checklists, functional testing, issue resolution, retesting, and training.
The government has hired an Independent
Commissioning Firm.
They will be responsible for commissioning services. Please see
Continuation Sheet provided with Amendment
0004. Refer to SECTION
01 91 00.15 22 TOTAL
BUILDING
COMMISSIONING for trade support required.
161 6
1.8.3
Page 9 section 01 35 00 paragraph 1.6.1.1 states that the QC Manager can
QC Manager cannot be the
SSHO. Please see
Continuation Sheet be the SSHO - Please see question below:
Page 6 Paragraph 1.8.3 states that the SSHO cannot be the
Superintendent or the QC
Manager. Please confirm that the QC Manager can be the SSHO.
168 Size of domestic water service is artificially enlarged to accommodate
2.5" tanker fill valves.
Can tanker fill valves be piped from the fire sprinkler service, downstream of backflow but upstream of alarm valve? This would prevent the fire alarm from activating during tanker fill and prevent oversizing of domestic water and resultant stagnation of domestic water from low velocity.
Permissible with appropriate valving and fire alarm monitoring.
170 14 and
Part 2, Section
01 33 10.05 20
2.2.2
Required
Design
Submittals
Per the latest UFC 1-200-
2 Change 03, section 4-2, for Design Build (DB)
Projects, the Life Cycle
Cost Analysis (LCCA) is required to be prepared during the development of the solicitation package, or Request for
Proposal (RFP), typically by the RFP preparation team ("AE-1"). The lowest life cycle cost building systems are incorporated as requirements in the DB
RFP. The DB RFP must
Please see initial LCCA created during RFP development with
Amendment 0004.
Per UFC 1-200-02 Change
03, Section 4-2, while the initial baseline LCCA is prepared during RFP development, the UFC explicitly mandates:
"refining the LCCA at each design submittal, as well as during construction if there are significant changes to the system."
require that any deviation provided by the offeror that increases energy efficiency be supported by an energy optimization and LCCA.
That said, on a recent DB project, MIDLANT has required an LCCA also be performed by the AE-
2 during the design phase, despite the fact that an LCCA was already performed by the
AE-1 that yielded the building systems prescribed by the RFP and the building systems are being designed in strict accordance (no deviations) with the RFP.
Considering the above and the fact that this RFP prescribes the building systems to be provided under this contract, will an LCCA be required on this project? If the answer is, "yes," since this goes against the requirements of UFC 1-
200-02 for DB projects, please describe the process in detail. For example, should we follow the UFC 1-200-02 requirements for Design
Bid Build (DBB) projects and provide an updated
LCCA with each design submission? What will the process be if our
LCCA yields building
If AE-2 submitted building systems that are different from those prescribed in the RFP, AE-2 must submit a detailed proposed alternative, with supporting LCCA data, for
Government evaluation during submittal process. If the AE-2 needs to resubmit an LCCA, follow the D-B-
B procedures.
If AE-2 choose to propose an alternative system that increases first costs, supporting documents must be submitted in accordance with the above paragraph. However, contractor is required to provide the systems prescribed in the RFP.
Deviations are at the
Government’s discretion, and no change orders for increased first costs will be issued for Contractor-elected deviations unless formally accepted by the
Contracting Officer.
systems that are different from the systems that are prescribed by the RFP?
If the LCCA results in the lowest life cycle cost, systems having a higher first cost than the systems prescribed by the RFP, will a change order be issued?
171 Pgs
1303-
(of pg.
RFP)
Part 6, Attachment 7
Entire
Several pages of
Attachment 7 include the editing instructions to the
RFP preparer, "Note to
DM: The Mechanical
Team Member responsible for editing and developing the mechanical content of this RFP will remove this guide before RFP release and replace it with the Government
Baseline Building
Performance Report.
Do not include this guide in the RFP release. "
Will the government provide the fully edited
"Government Baseline
Building Performance
Report"?
Please see fully edited
"Government Baseline
Building Performance
Report" provided with
172 Pgs
129-
133 (of
Part 2, Section
01 33 29 HPSB
Checklist
HPSB
Checklist
The HPSB checklist provided after section 01
33 29 is incomplete.
Please refer to editing instructions for UFGS section 01 33 29 (Design-
Build projects) which require a completed
HPSB Checklist be
Please see fully edited
"Government Baseline
Building Performance
Report" and the preliminary LCCA provided with Amendment
0004. The LCCA is required to be updated by the DOR. (Items listed on provided with this section in the RFP.
Per UFC 1-200-2 Change
03, section 4-2, for
Design Build (DB)
Projects, the Life Cycle
Cost Analysis (LCCA) is required to be prepared during the development of the solicitation package, or Request for
Proposal (RFP).
Please confirm which, if any, of the "renewable energy technology types" listed in the HPSB checklist were deemed to be life cycle cost effective and should be included in the contract.
the HPSB checklist as "not
LCCE" should not be included in the base bid unless the offeror is using them in a whole building strategy that they expect to be LCCE.
173 Pgs
1303-
(of
Part 6, Entire
The "Government
Baseline Building
Performance Report
Guide" appears to be an older document that no longer applies to this project.
(1) It references an outdated version of 90.1.
(2) It indicates, "The
Energy Design Reduction
Technical Evaluation
Factor in the DB selection process requires the prospective offerors to perform an HVAC simulation of their proposed building and submit their results with a comparative analysis to the Government Baseline
Building Performance
Please see fully edited
"Government Baseline
Building Performance
Report" and the preliminary LCCA
Report." We cannot find any other references to a
"The Energy Design
Reduction Technical
Evaluation Factor" in the
RFP.
Considering all building systems are required to be determined by an
LCCA prior to issuance of the RFP (UFC 1-200-2
Change 03, section 4-2) and those building systems are incorporated as requirements in the
RFP, please confirm if the "Government
Baseline Building
Performance Report
Guide"/"Government
Baseline Building
Performance Report" will not be utilized in this
RFP. If they will be used, please provide specific details for how offerors and the future awardee are to use the
"Government Baseline
Building Performance
Report" considering the various building systems have already been selected and prescribed by the government.
175 There is a conflict between 01 35 26 and 10
45 00. Please confirm that the QCM can also be the SSHO.
QC Manager cannot be the
SSHO. Please see
Continuation Sheet provided with
179 The RFP states "All members of the field
40-hour HAZWOPER training is required for crew must have received prior training per 29 CFR
1910.120€ (40-hour
HAZWOPER) and annual 8 hour
HAZWOPER refresher".
Please define "all members of field crew".
Is this only for workers exposed to the soil?
personnel coming into contact with contaminated soil or groundwater, as stated in the RFP.
180 Please confirm the government will allow 14 calendar days between the amendment answering PPIs and the proposal due date. This period will allow any revisions that become necessary to the pre-proposal design docs and subsequent distribution to the market for pricing.
The proposal due date has been extended with
184 For CLIN 0001C, can on-site filtration be utilized to support groundwater remediation or is this unit price intended to capture containerization, transport, and disposal at a licensed facility?
187 Please confirm if SSHO can be the superintendent.
SSHO must not serve as the Superintendent. Please see Continuation Sheet
188 549
C103006
Shelving
This section indicates to provide built-in steel fixed utility shelving as part of the construction contract. Room
Requirements for 106
The Activity is requesting standalone shelving, and linear footage and will be further discussed during the CDW. Please see
Continuation Sheet
Secure Storage indicate
E20 Furnishings Shelf, locking drug storage cabinet. Is this shelf the indicated built-in steel utility shelf? What is the required linear feet of storage needed for the shelving?
0004 that removes reference to built-in shelving.
189 583
E201090
Other fixed furnishings indicates furnishings such as - drying racks, equipment safety cages, safes, and miscellaneous types of "fixed" racks are part of the project. Pg
579 E20 Indicates fixed furnishings are part of the
SID package and in contract. Please verify which Items listed under
E20 on the Room
Requirements sheets are considered "fixed" and part of the SID in the construction contract and which items are considered part of the
FF&E Contract
Refer to WBDG, Collateral
Equipment Classification and Funding Matrix.
Construction Items are generally items that are permanently attached to the facility. These include but are not limited to Hose storage rack, entrance mat, PPE drying cabinet, locking drug storage cabinet, permanently attached shelving, fire extinguisher cabinets.
FF&E Items are items that are separate from the facility and "placed" within the building. These include but are not limited to desks, files, chairs, fire extinguishers, PPE extractor, dryer, drying rack and stainless-steel laundry folding table, PPE
Gear Storage Lockers, freestanding shelving and equipment, mobile PPE gear lockers.
190 579
E20 System Description indicates the purchase and installation of moveable furniture and furnishings (FF&E) will
FFE is an option to the construction contract. It will be funded with O&M funding, not MILCON.
The GC will bid a HAR be funded separately as part of Collateral
Equipment. Page 478 indicates Furniture, Fixtures, and Equipment
(FF&E) will be part of
Bid Option 3. Page 511
100 - Apparatus Bay indicates FF&E will be funded separately as a modification to the construction contract.
Please clarify how FF&E will be funded and if it will be a modification or
Bid option to the construction contract.
percentage (not to exceed
5%) on the bid schedule.
The final dollar amount will be based on final FFE and all necessary costs.
The 5% HAR is based on the FFE cost only. Once
O&M funding is secured, the option for the FFE will be awarded and the construction bond will increase due to the overall project cost increasing.
E20, general system requirements, state timeline for FFE award.
See Bid Schedule notes for additional information.
192 561
Part 3
Chapter 6
D209005
a. Is air compressor required to be oil-free?
b. Is an air dryer or filters required?
c. Are pressure regulators and quick-connect fittings required at air drops?
a. Yes.
b. Air dryer is required.
c. Yes, all are required.
Please refer to Part Four
Performance Technical
Specifications D209005
1.3 Compressed Air Piping
System.
193 511-
Chapter 5
Room
Requirements
Do sinks in Decontam, PPE Laundry, and
Apparatus Bay and the
PPE Extractor need to go to the oil/water separator?
Follow UFC 4-730-10 Fire
Station Chapter 4 Specific
Design Criteria.
194 512
Is the FAVERS vehicle exhaust system an automatic system with rail assembly, trolley with balancer, vertical hose, nozzle, end stop, fan auto-start and centrifugal fan or a stationary manually operated hose-type
The direct vent system can be either an automatic-type
Fire Apparatus Vehicle
Exhaust Removal System
(FAVERS) or a manually operated hose-type exhaust system operating whenever equipment is running in the bay.
exhaust system? Re: UFC
4-730-10, page 31.
195 512
OSHA generally limits the travel time to emergency safety showers and eye washes to 10 seconds (55 feet).
Assuming trucks are parked in both bays that impede the path, will multiple safety showers
Must comply with UFC 4-
730-10 and ANSI Z358.1.
196 563-
D30 HVAC
All support spaces (PPE
Laundry, PPE Storage, Decon, Restroom and
Vestibule) are required to have negative pressure.
UFC 4-730-10 requires the Apparatus Bay to be negative pressure. Since the facility is a stand-alone structure:
a. Will neutral pressure/air balance in the support spaces be acceptable?
b. Is the Apparatus Bay required to be negative pressure in relation to the support spaces?
a. Please refer to
Performance Requirement of the RFP, utilizing the appropriate climate design data per UFC 3-400-01 to determine the necessary design solutions.
b. Please refer to the UFC
4-730-10 Green Zone, Yellow Zone, Red Zone spaces. Design per section
3-6.2 HVAC requirement.
197 563-
D30 HVAC
Based on the project being located near the coast, will dehumidification be required to maintain 30 to
50% RH in support spaces?
Please refer to
Performance Requirement of the RFP, utilizing the appropriate climate design data per UFC 3-400-01 to determine the necessary design solutions.
200 1305
Appendix 7
Government
Baseline
Building
Can the government provide the HVAC
LCCA? It is indicated it is required to be
Please see fully edited
"Government Baseline
Building Performance
Report" and preliminary
Performance
Report Guide produced IAW UFC 1-
200-02 HIGH
PERFORMANCE AND
SUSTAINABLE
BUILDING
REQUIREMENTS.
According to the guide the HVAC LCCA best value selection is to be done before RFP release.
LCCA provided with
201 IAW UFC 1-200-02,
Paragraph 4-2 - Design
Build Projects, please provide copies of the
LCCAs that should have been produced during the development of the RFP solicitation package. As noted in the UFC "The resulting system and feature selections are incorporated as requirements in the DB
RFP."
Building Performance
Report" and the preliminary LCCA
202 29
01 31 19.05 20
1.3.2.b.(6).(g)
Please confirm that it is not required to include
Life-Cycle Cost Analysis for relevant plumbing, mechanical, and electrical systems with the Final Concept (CDW)
Report. Or please provide copies of the LCCAs that we can include in the report since they should have been completed as part of the development of the solicitation package IAW UFC 1-
200-02, Paragraph 4-2 -
Design Build Projects.
Building Performance
Report" and preliminary
LCCA provided with
Amendment 0004. Per
UFC 1-200-02 Change 03, Section…