PPIs_26DemoProjs- Gov Response 3.20.26.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Demolish Vacant Barracks Buildings 532 and 132H Naval Station Great Lakes
Solicitation number
N4008526R0090
Issued by

About this file

This file is a Pre-Proposal Inquiry (PPI) Response document for the demolition of two vacant barracks buildings at Naval Station Great Lakes, Illinois, solicitation number N4008526R0090. The government provides detailed responses to 21 contractor questions regarding the technical and logistical aspects of the demolition project for Buildings 532 and 132H.

Key technical details clarified in the responses include: foundation thickness specifications referenced in NAVFAC drawings; basement removal requirements limiting demolition to approximately 3 feet below finished grade; utility disconnection and removal procedures per RFP Part 3, Section F2010 1.2; confirmation that no traversable utility tunnels exist, though abandoned steam lines in concrete chases may be present; floor thickness specifications (B532: 10 inches; B132H: 8 inches); and confirmation that seismic monitoring is not required. Operational requirements address dust suppression using fire hydrants (with approved backflow preventers and water meters at $3.47 per 1000 gallons), use of on-site concrete crushers (subject to noise, dust, and permitting approvals), dewatering procedures requiring government review and environmental compliance, and backfill specifications allowing crushed concrete reuse if it meets TACO screening requirements. Environmental and hazmat requirements mandate that contractors perform their own environmental surveys and hazmat assessments for both buildings, with asbestos and lead reports available for B532 but not B132H. Administrative clarifications confirm Microsoft Project is acceptable instead of Primavera, the Period of Performance remains 520 days, the proposal due date was extended to April 7, 2026, and contractors must submit their own NPDES General Permit NOI (ILR10) for stormwater management rather than relying on a master facility permit.

View the file

Other files

File Type Posted
3. 0GRLK_BLDG_533_1968_SERVICE SCHOOL BRKS - BLDG. 533 TYP. BKS .75 W_1206515.pdf PDF
7. GRLK_BLDG_P641_1998_BACHELOR ENLISTED QUARTERS BLDG P641 SECTIONS _99999.pdf PDF
9. GRLK_BLDG_P641A_1998_BACHELOR ENLISTED QRTRS BLDG. P641A FOUNDATION _99999.pdf PDF
8. GRLK_BLDG_P641_1998_BACHELOR ENLISTED QRTRS P641 & P641A EXTERIOR W_99999.pdf PDF
13. NOIsubmittal.pdf PDF
12. IL Urban Manual_Dewatering.pdf PDF
10. GRLK_BLDG_YYYYY_1966_SERVICE SCHOOL BRKS AND MESS HALL 500 BLOCK BK_1120572.pdf PDF
6. GRLK_BLDG_P641_1998_BACHELOR ENLISTED QUARTERS BLDG P641 FOUNDATIO_99999.pdf PDF
14. Water near 132H.pdf PDF
5. GRLK_BLDG_P641_1998_BACHELOR ENLISTED QUARTERS BLDG P641 & P641A S_99999.pdf PDF
11. GRLK_XXXX_YYYYY_1966_TYP BKS 0.75 INCH WALL SECTIONS ARCHITECTURAL_1120522.pdf PDF
15. water near B532.pdf PDF
2. 0GRLK_BLDG_533_1966_SERVICE SCHOOL BRKS AND MESS HALL BKS 533 EXTE_1120520.pdf PDF
1. 0GRLK_BLDG_532_1966_SERVICE SCHOOL BRKS AND MESS HALL (500 BLOCK) _1120565.pdf PDF
N4008526R00900004 SF 30.pdf PDF
4. GRLK_BLDG_P641_1998_BACHELOR ENLISTED QUARTERS BLDG P641 & P641A S_3.pdf PDF
Site Visit Roster 3.10.26.pdf PDF
N4008526R00900003 SF 30.pdf PDF
8. Price Sheet_B532 Add 02_3.5.26.pdf PDF
9. Price Sheet_B132H Add 02_3.5.26.pdf PDF
N4008526R00900002 SF 30.pdf PDF
9. Price Sheet_B132H Add 01_02.27.2026.pdf PDF
1. SCOPE_DB_DEMO_532_Amd 01.pdf PDF
2. SCOPE_DB_DEMO_132H_Amd 01.pdf PDF
10. Offline_Steam Map.pdf PDF
8. Price Sheet_B532 Add 01_02.27.2026.pdf PDF
N4008526R00900001 SF 30.pdf PDF
2a. DRAWINGS DB_DEMO BEQ 132H.pdf PDF
1a. DRAWINGS DB_DEMO BEQ 532.pdf PDF
7. Past Performance Questionnaire.pdf PDF
3. PPI N4008526R0090.xlsx XLSX spreadsheet
5. Construction_Experience_Form.pdf PDF
Solicitation - N4008526R0090.pdf PDF
1. SCOPE-DB_DEMO BEQ_532.pdf PDF
2. SCOPE-DB_DEMO BEQ_132H.pdf PDF
4. Limitations_on_Subcontracting_Certification.pdf PDF
6. Design_Experience_Form.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

N4008526R0090
DEMO VACANT BEQs B532, B132H NSGL. IL
Pre-Proposal Inquires (PPIs) FORM
Question No.RFP Reference (Sect/Para/Page)QUESTIONGOVERNMENT RESPONSE
1What is the foundation thickness of both of the buildings?See attached drawings: B532 = NAVFAC drawing nos 1120565, 1206515, 1120572; B132H = S2.0, S3.0, S3.2
2Can we go 30% below grade on the basement, or do we need to remove the entire basement?Remove foundations to ~3 feet below finished grade, then break up the basement slab for drainage and fill the remainder.
3How far back do we need to cut utilities, or do they need to be completely removed?Utility disconnections and removal shall be per the RFP. For B532 refer to Part 3, Section F2010 1.2 UTILITIES on page 175 of 214. For B132H refer to Part 3, Section F2010 1.2 UTILITIES on page 174 & 175 of 215.
4Are there any underground utility tunnels?There are no traversable utility tunnels in the vicinity of B532 or B132H. However, there may be abandoned steam lines in concrete chase.
5Is there any estimate on the floor thickness of each level of the building?B532 = 10" (see drawing 1120522); B132H = 8" (see drawing S4.0, S6.1)
6Has there been any seismograph done, or is that something that needs to be done prior to removal of the building?No; Seismograph monitoring in not required. Demolition is anticipated to be performed using systematic demolition methods that minimize vibration. KTR is responsible for selecting demolition means and methods that limit vibration and protect adjacent structures/utilities.
7Can we use the fire hydrants for dust suppression during demolition? If yes, can we get a diagram of hydrant locations around the buildings to plan accordingly? Also, will we need backflow preventers on the hydrants if we use them?Yes. See attachments "water near B532" & "Water near 132H." Provide approved backflow preventer equipped with a water meter. Protect any hoses that run over areas of traffic and provide ramps if they run over a sidewalk that is not closed off for use. Water usage will be billed to the KTR at the current fiscal year rate for when water is used (To give an idea the current rate is $3.47 per 1000 gallons).
8Can we get a copy of the engineering drawings?Complete drawings sets are not available; however, individual sheets will be provided as they are found. Availability and completeness cannot be guaranteed.
9Is it possible to get a concrete crusher on location?Use of a concrete crusher is acceptable. KTR must submit noise control and dust suppression plans for review/approval and must comply with all applicable federal, state, and local regulations. KTR is responsible for notifying the IL EPA and obtaining all necessary permits prior to mobilization and operation of crushing equipment.
10Is there access between the two buildings that doesn’t require going off-site and re-entering?Site access logistics will be coordinated during the PAK meeting. Government will make reasonable efforts to accommodate a temporary access opening, subject to approval by base security.
11How and where do we drain water?See attachment "Illinois Urban Manual Practice Standard - Dewatering" Note: Before dewatering, KTR must submit a Dewatering Plan for Government (EV) review/approval. Plan & materials must comply with attachment, Dewatering Practice Standard. Include a map of the dewatering bag and the stormwater drain that it will be draining to. Plan must include the following statements 1) Dewatering will be coordinated with NSGL EV prior to beginning dewatering operations; 2) Dewatering will be stopped immediately if there are signs of contaminants (sheen, film or emulsion) in the basement or signs of contaminants (sheen, film, emulsion, or turbidity) leaving the filter bag.
12Has there been an environmental study done on the buildings?An environmental report is available for B532 and is included in Part 6 for reference. No report is available for B132H. KTR must perform their own environmental survey prior to starting work.
13Has there been an asbestos and lead quantity study done on the buildings?See F2020 - B132H - No survey report available; B532 - report provided in Part 6 Attachments for reference only. HAZMAT Survey is required as a part of this project for each building.
14Can we backfill each location with concrete to a certain depth and then cover with dirt after the concrete?Yes, crushed concrete generated onsite may be reused as fill to a limited depth. Import fill must be clean, certified, and meet applicable screening requirements, including passing a TACO screen. Documentation verifying compliance must be provided prior to placement.
1501_32_17.00 20Is Primavera required or is an alternate (Microsoft Project) acceptable to meet this requirement?Microsoft Project is acceptable.
1601 14 00 1.2.4Will the POP be amended to include the Exclusionary Period?No, POP will remain at 520-days.
17Solicitation, Pg 64Will the owner consider extending the period for PPI's to allow bidders more time to coordinate with their design teams and idenify additional information requests?Proposal due date will be extended to April 7, 2026.
18Solicitation, Pg 65Will the owner consider extending the bid date to allow for reciept of responses for required bid documents, as well as thorough coordination in preparation for execution of the technical requirements?Proposal due date will be extended to April 7, 2026.
19Site VisitCan the owner clarify access to building 132H? Will the contractor be ulilizing the gate that was used for access at the pre-bid? If so, what type of turn around can be expected for the gate to be opened?The Government will try to provide a temporary site access point to avoid using Gate 3; however, this requires base security approval and is not guaranteed. KTR's should plan to use standard entry points unless otherwise approved.
20Site VisitCan the owner clarify the status of the utilities at the time the contractor will take control of both buildings?Utility information is provided in RFP Part 3, F2010 1.2.
21132H Bid SetStormwater management plan, page 3; Is there a master NOI in place for the facility, or is the contractor submitting a whole new permit?KTR must submit their own NOI for a General NPDES Permit ILR10; See attachment "NOIsubmittal"

&"-,Bold"PRE-PROPOSAL INQUIRY FORM &"-,Bold"DEMO VACANT BEQs B532, B132H &"-,Bold"SOLICITATION NUMBER: N4008526R0090

Sheet2

Sheet3

File details come from the government source that posted it. Updated .