This is a Price Schedule for a federal demolition contract requiring bidders to provide line item pricing for the complete demolition of Vacant BEQ Building 132H and associated asbestos removal and disposal work.
The contract includes a base price line item (Line 1) for the entire demolition work, with an estimated quantity of one each. Five additional line items specify unit prices for specialized asbestos abatement services: removal and disposal of asbestos-containing mudded pipe fittings (100 each), vibration cloth on HVAC systems (100 linear feet), roofing material (25,000 square feet), fire doors (100 each), and subgrade and utility piping (1,500 each). Bidders must populate all unit price and sub-total fields for each line item and provide a cumulative total price for line items 1-6, which must also be entered on line item 0002 of the SF 1449 form. The pricing structure allows for both comprehensive base pricing and itemized unit pricing for potential change order scenarios related to asbestos removal scope variations.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
Provide line item prices, where indicated by blank underlines, for the following items:
Please provide total price for line items 1-6. $________________________
(This total should also be placed on line item 0002 of SF 1449)
Line Item
Description Quantity Unit Unit Price
Sub-Total
1 BASE PRICE: Total Price for the entire work for
DEMOLISHING VACANT
BEQ BUILDING 132H in accordance with the RFP.
1 EA $_______
2 Unit Price for removal and disposal of asbestos containing mudded pipe fittings.
100 EA $___ $_______
3 Unit Price for removal and disposal of asbestos containing vibration cloth on HVAC.
100 LF $___ $_______
4 Unit Price for removal and disposal of asbestos containing roofing material.
25,000 SF $___ $_______
5 Unit Price for removal and disposal of asbestos containing fire doors.
100 EA $___ $_______
6 $___ $_______ Unit Price for removal and disposal of asbestos containing subgrade and utility piping.
1,500 EEA $___ $_______