001_Attachment L - PPI_Responses_27FEB24.pdf
PDF 701 KB Posted
- Solicitation number
- N4008524R2592
About this file
This attachment is related to a solicitation for a Combatant Craft Maintenance Facility project at Joint Expeditionary Base Little Creek - Fort Story in Virginia Beach, Virginia. The solicitation is being issued through the 8(a) Multiple Award Construction Contract (MACC) program primarily for contractors in the Hampton Roads area of Virginia. Only 8(a) MACC Contractors holding certain contract numbers with NAVFAC MID-ATLANTIC may submit a proposal for this P602U MSRON TWO Combatant Craft Maintenance Facility project. The solicitation was issued by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B D E F G H I
Page Section Paragraph
02/20/24 13 2.4.1
This spec section indicates roof, wall and liner panel to be 24 gauge exposed fastener PBR panels. This would create an issue as you cannot provide the requested weathertight warranty for the roof with an exposed fastener roof panel. Would the government prefer an exposed fastener roof panel without weathertight warranty or change it to a standing seam roof panel w/weathertight warranty?
Provide standing seam roof in lieu of exposed fastener system. Provide roof warranty as specified.
02/20/24 S-505
The plans S-101 note 8 indicates the equipment mezzanine columns to be provided by the PEMB manufacturer. Sheet S-505 indicates the mezzanine supported by steel columns with masonry walls with bond beams placed between the columns. The plan provides perimeter beam size (12” ) and joist size (C12 x 3.5), but not the column size. Framing plan B2 on S-505 also indicates structural sections A2/sheet S-401 and C3/sheet S-401. The drawing set does not include a sheet S-401. Could you please confirm if this note is correct in refering to sheet S-401 and, if so, could that sheet be provided? Also, is the mezzanine meant to be free standing, or does it tie into the structural columns on the building?
The mezzanine is intended to be a free standing structure. Sheet S-401 is not included in the bid documents; References to Sheet S- 401 shall be superseded by S-505, which illustrates the framing of the mezzanine. See General Note 2, Sheet S-505 for PEB manufacturer requirements pertaining to mezzanine framing and design.
02/20/24 13 1.2.4.1 / 13 1.2.4.2
These spec sections call for R-19 roof and R-13 wall thermal insulation, however code is been R-30 roof and R-26 wall insulation. This is graphically indicated on the drawings but not specifically called out. Could you please confirm the correct R value for thermal insulation?
Provide R-30 roof and R-26 wall insulation as required by code.
02/22/24 DWGS S-101
& S-505
The plans S-101 note 8 indicates the equipment mezzanine columns to be provided by the PEMB manufacturer. BUT Sheet S-505 indicates the mezzanine supported by masonry walls with bond beams placed between steel columns and specifies perimeter beam size (12” ) and joist size (C12 x 3.5), but not the column size. What size is the columns?
equipment platform is to be designed by the pemb manufacturer per sheet s-001 "delegated design" note 3. Sheet S-100 new work keynote 6. Sheet S-101 new work keynote 8. Sheet S-505 general sheet notes 2. Sheet S-505 shows a platform for bidding purposes not for construction and to illustrate certain column placement and interaction between platform and cmu.
02/22/24 DWG S-505
Framing plan B2 on S-505 also indicates structural sections A2/sheet S- 401 and C3/sheet S-401. There is no drawing S-401. Please provide drawing S-401
References to Sheet S-401 shall be superseded by S-505, which illustrates the framing of the mezzanine. See General Note 2, Sheet S- 505 for PEB manufacturer requirements pertaining to mezzanine framing and design. 001
02/22/24 9/613 1.2.4.1 13 34 19 The specs and A-dwgs general notes call for R-19 roof thermal Insulation, code now has R-30 roof thermal insulation. Do we price the R-19 or the new code R-30?.
Provide R-30 roof and R-26 wall insulation as required by code.
02/22/24 9/613 1.2.4.2 13 34 19 The specs and A-dwgs general notes call for R-13 wall thermal Insulation, code now has R-26 wall thermal insulation. Do we price the R-13 or the new code R-26?.
Provide R-30 roof and R-26 wall insulation as required by code.
02/22/24 21/625 2.4.1 13 34 19
Specs indicate the roof, wall and liner panel to be 24 guage exposed fastener PBR panels. The problem is we can not provide the requested weathertight warranty for the roof with an exposed fastener roof panel, Please indicate which one is required, exposed fastener roof panel w/o weathertight warranty or change to standing seam roof panel w/weathertight warranty?
Provide standing seam roof in lieu of exposed fastener system. Provide roof warranty as specified.
Amend#
Pre-Proposal Inquiry Submission Form N4008524R2592, P602U MSRON TWO Combatant Craft Maintenance Facility
Date Submitted Government Response
Reference Question
RFP N4008524R2592_A001
Attachment L
PPI Submission Form
File details come from the government source that posted it. Updated .