About this file

This document is Amendment 0006 to Solicitation N4008524R2536 for a Design-Bid-Build project to renovate and modernize Building 77H at the Philadelphia Navy Yard Annex in Philadelphia, Pennsylvania.

The amendment provides responses to 6 Pre-Proposal Inquiry (PPI) questions related to various requirements, including steel fabricator/erector certifications, electrical equipment studies, voltage drop calculations, and details on the existing environmental chamber. No exterior renderings are available for the building modifications. The proposal due date of August 2, 2024 remains unchanged, but the PPI submission date has closed. This amendment makes no other changes to the solicitation.

The overall project scope includes renovating/modernizing the south bay of Building 77H to provide a 40,000 SF Land Based Engineering Test Site (LBETS) for the FFG-62 Constellation Class Machinery Plant Test and Evaluation Program. Key elements include control rooms, staging areas, shop spaces, demolition of existing test sites, civil/site work, structural modifications, new fire suppression, and complete demolition of Building 480.

View the file

Other files

File Type Posted
Amend0005 - BLDG 77H West Low Bay Labs Redacted.pdf PDF
Amendment 0005 - 1678622 DWG 01of01.pdf PDF
Amend0005 B480 Photos 1of4.pdf PDF
Amend0005 B480 Photos 2of4.pdf PDF
Amend0005 - BLDG 77H East Substation Redacted.pdf PDF
Amend0005 - BLDG 77H General Building Spaces Redacted.pdf PDF
Amend0005 B480 Photos 3of4.pdf PDF
Amend0005 B480 Photos 4of4.pdf PDF
Amend0005 PPI 118 547 Paint B633 High Bay Interior Spec.pdf PDF
Amendment 0005 - AFFF Fire Extinguisher System As Built.pdf PDF
Amend0005 - BLDG 77H Diesel Test Facility Redacted.pdf PDF
Amendment 0005 - DDG51 Test Site Control House Complex Recorded.pdf PDF
Amendment 0005 Phila Naval Business Center Sprinklers -As Built.pdf PDF
AMENDMENT 0005.pdf PDF
Amendment 0005 - Automatic Fire Sprinkler System For Prefab Enclosure.pdf PDF
Amend0005 - BLDG 77H East Low Bay Labs Redacted.pdf PDF
Amend0005 PPI 116 FFG-62 MASW-Report.pdf PDF
Amend0005 - Bldg 77H MEP 77H Site and 480 Photos Redacted.pdf PDF
Amendment 0005 - BLDG 77H 756 Fire Alarm AsBuilts.pdf PDF
Amend0005 - BLDG 77H South Exterior Redacted.pdf PDF
Amendment 0005 - Integrated Ship Control Diagnostic Facility.pdf PDF
Amendment 0005 Small Component Electronic Cooling Water CWAS - As Built.pdf PDF
Amend0005 PPI 115 FFG-62 and Design Mod soil lab reports.pdf PDF
Amend0005 - BLDG 77H East Electrical MDP Redacted.pdf PDF
Amend0005 - BLDG 77H South Sprinkler Risers.pdf PDF
Amendment 0005 14 24 13 - HYDRAULIC FREIGHT ELEVATORS.pdf PDF
Amendment 0005 - DDG-51 Control House Extension 06101997.pdf PDF
Amendment 0004 - Cooling Water System - Controls Hardware.pdf PDF
Amendment 0004 - Fuel Oil System - Modifications to Existing Panel CP-FOPV.pdf PDF
Amendment 0004 - Cooling Tower System - As-Built Drawings.pdf PDF
Amendment 0004 - PPI 84 - NSWC Building 77H Roof Repair record drawings.pdf PDF
Amendment 0004 - Fuel Oil System - Control Panel CP-FOPV As-Built Drawings.pdf PDF
Amendment 0004 - FFG-62 Specifications.pdf PDF
Amendment 0004.pdf PDF
Amendment 0004 - FFG-62 Drawings Signed.pdf PDF
Amend0003 049 - BLDG077H - WEAPONS ELEVATOR - 2078005.pdf PDF
Amend0003 011 - BLDG077H - DIESEL TEST CELLS - 2163659.pdf PDF
Amend0003 010 - BLDG077H - DIESEL TEST CELLS - 2163658.pdf PDF
Amend0003 PPI 46_FFG62 Repair 77H Exterior SWYard Existing Photos DistroA.pdf PDF
Amend0003 7625158 R- D04-10-25_Redacted.pdf PDF
Amend0003 30041555 R- APPROVED 2021-08-11 ZONE 1 GENL ARR_Redacted.pdf PDF
Amend0003 PW-31 5400C246.pdf PDF
AMENDMENT 0003.pdf PDF
Amend0003 052 - BLDG077H - WEAPONS ELEVATOR - 2078009.pdf PDF
Amend0003 PW-30 5400C249.pdf PDF
Amend0003 1705955_DEMO_DWG_FULL SET.pdf PDF
Amend0003 050 - BLDG077H - WEAPONS ELEVATOR - 2078007.pdf PDF
Amend0003 30041586 R1 2021-08-12 SITE EQUIPMENT ARR_Redacted.pdf PDF
Amend0003 051 - BLDG077H - WEAPONS ELEVATOR - 2078008.pdf PDF
Amend0003 PW-32 5400C247.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION NO. N4008524R2536, DESIGN-BID-BUILD, RENOVATE BLDG. 77H, FFG-62 LAND BASED ENGINEERING SITE, PHILADELPHIA

NAVY YARD, PHILADELPHIA, PENNSYLVANIA

The proposal due date of 02 August 2024 NLT 2:00 PM EDT remains unchanged. The PPI submission date has closed.

See Continuation Page(s).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Jul-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008524R2536

X 9B. DATED (SEE ITEM 11)

22-May-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Jul-2024

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008524R2536

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0006

The purpose of this amendment is to provide the following:

1. Pre-Proposal Inquiry (PPI) Responses

Pre-Proposal Inquiry Responses:

Question # Reference

Question Government Response Page Section Paragraph

2A161

2I601

Paragraph states that work must be performed by an AISC Certified Structural Steel Fabricator and Erector. Is an alternate third party (Colliers Engineering & Design) Fabrication and Erection certification acceptable, when AISC Codes of Standard Practices are followed and supplemented by weekly shop and field-testing reports?

No, comply with specification requirements for steel fabricator and erector certifications.

26 28

01.00 10

According to specification 26 28 01.00 10, the contractor owns studies on all the existing electrical equipment along with ARC flash. For bidding purposes, please advise if studies are to be provided on only the new equipment that is tied into the existing or if studies are indeed required on all existing electrical equipment. If studies on all existing electrical equipment are required, please advise as to which work location studies are required on (ex. Bldg. 77H, Bldg. 670, etc.).

There are two substations in B77H where new equipment will be powered from under this project -the East Substation and the Southwest Substation. The Southwest Substation was recently replaced. The East Substation is undergoing replacement as part of a separate project. The idea would be to include the existing sources of power within the power study to ensure that the new equipment is fully coordinated with the existing power distribution system. Information on existing sources will need to be coordinated with the government.

N4008524R2536

28 31 70 & 28 31

For voltage drop calculations, please advise if this is just for the new feeders being implemented or if this includes the branch lines as well.

Voltage drop calculations are required to be performed as part of the power study. These would include feeders and any branch circuits for large pieces of equipment.

Voltage drop calculations for every branch circuit is not required as part of the study. However, voltage drop cannot exceed 5% for each branch circuit from the feeder source to the farthest component of the branch circuit per the NEC.

125 2M102 Please provide weight and dimensions of the salvaged environmental chamber unit.

Environmental Chamber unit is approximately 8 feet wide, 10 feet-6 inches long, and 10 feet high. For bidding purposes, assume unit weight is 50,000 lbs.

126 2S301

If available, please provide an aerial (exterior) rendering of the new design modifications for Bldg. 77H.

No exterior renderings exist.

127 2P602

Please advise how we are to provide integration for the Allen Bradley Fuel Oil Monitoring System to the equipment shown sheet 2P602 as nothing is mentioned.

Refer to attachments in Amendment 0004 for Fuel Oil Control Panel information

(End of Summary of Changes)