About this file

This document is Amendment 0004 to Solicitation N4008524R2536 for a Design-Bid-Build project to renovate and modernize Building 77H at the Philadelphia Navy Yard. The amendment provides responses to 111 pre-proposal inquiries, revises drawings and specifications, and extends the proposal due date to August 2, 2024. Key changes include extending refrigerant and cold-water piping for an existing environmental chamber, providing details on the temporary fire pump requirements, and clarifying grounding and bonding for the fuel oil system. The overall project scope involves renovating the south bay of Building 77H to establish a 40,000 SF Land Based Engineering Test Site for the FFG-62 Constellation Class Machinery Plant Test and Evaluation Program. This includes a control room, industrial staging area, shop, and support spaces, as well as civil site work, fire protection, and utility upgrades.

View the file

Other files

File Type Posted
AMENDMENT 0006.pdf PDF
Amend0005 - BLDG 77H West Low Bay Labs Redacted.pdf PDF
Amendment 0005 - 1678622 DWG 01of01.pdf PDF
Amend0005 B480 Photos 1of4.pdf PDF
Amend0005 B480 Photos 2of4.pdf PDF
Amend0005 - BLDG 77H East Substation Redacted.pdf PDF
Amend0005 - BLDG 77H General Building Spaces Redacted.pdf PDF
Amend0005 B480 Photos 3of4.pdf PDF
Amend0005 B480 Photos 4of4.pdf PDF
Amend0005 PPI 118 547 Paint B633 High Bay Interior Spec.pdf PDF
Amendment 0005 - AFFF Fire Extinguisher System As Built.pdf PDF
Amend0005 - BLDG 77H Diesel Test Facility Redacted.pdf PDF
Amendment 0005 - DDG51 Test Site Control House Complex Recorded.pdf PDF
Amendment 0005 Phila Naval Business Center Sprinklers -As Built.pdf PDF
AMENDMENT 0005.pdf PDF
Amendment 0005 - Automatic Fire Sprinkler System For Prefab Enclosure.pdf PDF
Amend0005 - BLDG 77H East Low Bay Labs Redacted.pdf PDF
Amend0005 PPI 116 FFG-62 MASW-Report.pdf PDF
Amend0005 - Bldg 77H MEP 77H Site and 480 Photos Redacted.pdf PDF
Amendment 0005 - BLDG 77H 756 Fire Alarm AsBuilts.pdf PDF
Amend0005 - BLDG 77H South Exterior Redacted.pdf PDF
Amendment 0005 - Integrated Ship Control Diagnostic Facility.pdf PDF
Amendment 0005 Small Component Electronic Cooling Water CWAS - As Built.pdf PDF
Amend0005 PPI 115 FFG-62 and Design Mod soil lab reports.pdf PDF
Amend0005 - BLDG 77H East Electrical MDP Redacted.pdf PDF
Amend0005 - BLDG 77H South Sprinkler Risers.pdf PDF
Amendment 0005 14 24 13 - HYDRAULIC FREIGHT ELEVATORS.pdf PDF
Amendment 0005 - DDG-51 Control House Extension 06101997.pdf PDF
Amendment 0004 - Cooling Water System - Controls Hardware.pdf PDF
Amendment 0004 - Fuel Oil System - Modifications to Existing Panel CP-FOPV.pdf PDF
Amendment 0004 - Cooling Tower System - As-Built Drawings.pdf PDF
Amendment 0004 - PPI 84 - NSWC Building 77H Roof Repair record drawings.pdf PDF
Amendment 0004 - Fuel Oil System - Control Panel CP-FOPV As-Built Drawings.pdf PDF
Amendment 0004 - FFG-62 Specifications.pdf PDF
Amendment 0004 - FFG-62 Drawings Signed.pdf PDF
Amend0003 049 - BLDG077H - WEAPONS ELEVATOR - 2078005.pdf PDF
Amend0003 011 - BLDG077H - DIESEL TEST CELLS - 2163659.pdf PDF
Amend0003 010 - BLDG077H - DIESEL TEST CELLS - 2163658.pdf PDF
Amend0003 PPI 46_FFG62 Repair 77H Exterior SWYard Existing Photos DistroA.pdf PDF
Amend0003 7625158 R- D04-10-25_Redacted.pdf PDF
Amend0003 30041555 R- APPROVED 2021-08-11 ZONE 1 GENL ARR_Redacted.pdf PDF
Amend0003 PW-31 5400C246.pdf PDF
AMENDMENT 0003.pdf PDF
Amend0003 052 - BLDG077H - WEAPONS ELEVATOR - 2078009.pdf PDF
Amend0003 PW-30 5400C249.pdf PDF
Amend0003 1705955_DEMO_DWG_FULL SET.pdf PDF
Amend0003 050 - BLDG077H - WEAPONS ELEVATOR - 2078007.pdf PDF
Amend0003 30041586 R1 2021-08-12 SITE EQUIPMENT ARR_Redacted.pdf PDF
Amend0003 051 - BLDG077H - WEAPONS ELEVATOR - 2078008.pdf PDF
Amend0003 PW-32 5400C247.pdf PDF
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0004 15-Jun-2024

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N4008524R2536

9B. DATED (SEE ITEM 11)

22-May-2024

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION N4008524R2536, DESIGN-BID-BUILD, DESIGN-BID-BUILD, RENOVATE BLDG. 77H, FFG-62 LAND

BASED ENGINEERING SITE, PHILADELPHIA NAVY YARD, PHILADELPHIA, PENNSYLVANIA

The proposal due date has been extended to 02 August 2024 NLT than 1400 (EDT).

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil

N40085-24-R-2536

SF 30 BLOCK 14 CONTINUATION PAGE

The purpose of this amendment is to provide the following:

1. PPI Responses

2. Revised Drawings & Specifications

3. Reference Drawings

4. Extend proposal due date to 02 August 2024 NLT 2:00PM EDT.

Pre-Proposal Inquiry Responses:

Question # Reference

Question Government Response Page Section Paragraph

Can photos of the exterior work areas on the west side of Building 77H please be provided? The Government did not grant access to this area during the pre-bid site walk.

Pictures cannot be provided due to content and the level of review required.

Can photos of the interior (high bay area and lean-to) column lines 1-12 of Bldg

77H be provided? Photos of the existing condition would be useful to bidding subcontractors unable to attend the pre-bid visit.

Pictures cannot be provided due to content and the level of review required.

Has the exisiting roof steel in Building

77H, and other any other existing steel locations, been analyzed as adequate to support suspended scaffolding? Or alternatively, please provide the hanging load capacity of the roof structure.

No. Temporary loading is the responsibility of the contractor. See Structural sheets for load information.

67 2PD401

Please clarify access points to the Fuel

Oil Purifier Room as there are no doors shown on the drawings. This could affect if/how the equipment required to be removed from this room can be removed in whole or needs to be done in parts and/or if an opening needs to be created in a wall. If the designer has an intent please indicate.

The lines that appear to be enclosing the existing fuel oil purifier represent an 8" concrete curb, not wall. There should be no issue with the removal or replacement of equipment in this space.

Can someone confirm the exact location of the existing Lenel ACP Intelligent

Control Panel with the Star Multiplexer

(LNL-8000) that the Control House new

Card Reader Modules (LNL-1320) will connect to via a RS-485 (2-wire)? Does the Security Contractor need to confirm that the existing ACP and Star

Multiplexer has the capacity for the additional LNL 1320 Dual Reader

Modules?

Refer to 2TY101 for location of existing Lenel ACP with

Star Multiplexer. It is WRA's understanding that the lenel panel has capacity to incorporate Control House

Lenel Dual Reader Interface

Modules.

69 2TY103

Based on the specifications and drawings, please confirm the security cable is required to be in conduit, except for the cable run between the Mezz

Confirmed. Security cable will be installed in conduit except as noted between Mezzanine

Telecom Room 203 and

Telecom (Room 203) and perimeter wall of the Control House that utilizes a cable tray below raised access floor as indicated on drawing 2TY103. It is assumed that the cable run between the

Control House to the existing ACP with the Star Multiplex ACP is in conduit.

perimeter wall of the Control

House.

It is assumed that the security cable supporting the card reader doors to the junction box above the door is in conduit. Please confirm that conduit is required between the card reader door junction box to the ACP is in conduit.

Correct. Security cable from card reader to above door junction box must be in conduit. Conduit from card reader junction boxes to ACP is required.

71 2A001 10 26 00

2.3 , 2.3.1 , 2.4

Please clarify location of wall covering and panels. It is listed under the spec section and 2A001 but not shown in any drawings.

Provide Wall Covering in Jan

202 at back and side walls of

Janitor's Sink. Refer to amended drawing.

2S101, 2S103 31 62 00

Please confirm there is a pile located at

Column 3.7, Section 'D', DWG #2S103

If the referenced location is under the 12'-0" dimension annotation, then yes there is a pile. If not, then clarify referenced location.

2S101, 2S103, 2S104

31 62 00

Please confirm there is a proof load test pile at Column 8.9, Section 'B', DWG

#2S103

Yes, see 2S104 for specific pile at referenced area.

74 31 62 00 Please confirm the load capacities of the micropiles. (Dead and Live Load)

Refer to Deep Foundations notes on 2S001.

75 31 62 00

Please confirm what the PID was measuring so we have a better understanding of the methane amount and other possible hazards.

A PID was used to screen samples for volatile organic compounds. The PID does not detect methane gas.

Can the roof or portions of the roof be demolished and remain open through the course of interior earthwork and foundation construction to aid in ventilation?

Sequence of construction is up to the contractor, however, there are restrictions on openings. Refer to general sheets and division 1 specifications for building enclosure requirements during construction.

77 21 30 00 2.3

Please confirm that any/all packaged fire pump houses will be classified as COTS

(Commercial Off The Shelf) items and the Buy American Act will apply as such.

Comply with the Buy

American Act

78 26 08 00 3.1.a

Specification 26 08 00 indicates that acceptance tests and inspections shall be performed on applicable equipment and systems specified in specification section

26 24 13 for Switchboards, however, this specification section has not been made available. Please provide.

Specification section 26 24 13 was not included as part of the

CD package. There is not a new switchboard in the scope of this project.

79 2M102

For the existing environmental chamber, please confirm that no warranties of this existing Government furnished equipment will be expected.

No warranties of this existing

Government furnished equipment are expected.

80 2M102

For the existing environmental chamber, please provide photos to distinguish the condition of the equipment to be installed by us.

Photos are not available.

81 E115

Please provide details of the 16-way and

8-way ductbank connection with stub-up at column B3.

Ductbank details are shown at sheet 2E610. It should be noted that the 16-way 6"-inch conduit ductbank is shown correctly for the medium voltage ductbank that is called out on 2E115 as 5"-conduit.

Where conduit is called to stub up above grade, it should transition from PVC conduit to RGS conduit above grade.

Cap and seal conduit as required to prevent entrance of moisture and debris.

82 09 97 13.27 2.1

Can the primer coat of the high performance coating system be shop-applied to avoid removal of specified steel shop primer in the field prior to application of the high performance primer? See paragraph 2.1 stating

"Apply the entire coating system in the field. Remove all shop-applied primer prior to final field surface preparation and coating system application."

The requirement was pulled directly from the DOD UFC specifications and should be provided as specified.

83 21 13 13 3.4.10

Please confirm that there is no requirement for drain/test connections for the wet sprinkler system to be located on remote branchlines, only that there be a drain/test connection for each waterflow switch.

Confirmed.

84 09 90 00

Please provide details for existing structural steel sizes and framing plans to be coated with lead encapsulating paint.

Refer to excerpts from the

NSWC Building 77H Roof

Repair record drawings accompanying this amendment for additional information about the existing structure.

85 33 52 40

Please clarify if high performance coating is be to applied to both existing and new fuel system piping or only new fuel system piping. If applying to existing piping what is the state of the coatings on the existing piping.

The high performance coating is required only on the new fuel system piping.

Can a construction joint in the new SOG be included at the approximate location of the existing drive aisle? This is to facilitate continuity of drive aisle access while excavation, foundation, concrete work occurs elsewhere.

Refer to Section 03 30 00, paragraph 2.2.5 for construction joint location requirements. Submit a construction and movement joints shop drawing for review as noted in the amended spec section.

33 52 40, 33

56 10, 33 57

2.1.2, 2.1.1, 2.3.1

Specifications 33 52 40 (2.1.2), 33 56 10

(2.1.1), and 33 57 55 (2.3.1) mentions that grounding and bonding are required for the fuel oil piping as indicated on the

Refer to NEC 250.104(B) for methods by which to bond the fuel oil piping system. The fuel oil piping system should drawings, however, there are no locations found on the drawing set provided. Please show where this will be required on the drawing set.

be bonded to the existing building grounding grid unless it is within the area of the new interior grounding grid that is established in the major areas of the project scope. In addition, refer to specification

26 20 00 Section 3.1.18 for further requirements for grounding and bonding practices.

88 2A401 What are the finish requirements for the stainless steel handrails?

No. 4 - Brushed Finish

89 2M102

For the environmental chamber, kindly specify the location from where the equipment has to be picked from with the dimensions and weight of the environmental chamber. If there is a specific route required to move the equipment along, please advise where that route would be.

The camber is being removed/salvaged under the

Early Demolition project which is currently in construction. It will be located within 5 miles of B77H (exact location is unknown).

90 2M102

The drawings state the following:

"Extend refrigerant and cold-water piping as required per manufacturer's recommendations. Charge system with the appropriate refrigerant." Kindly provide the details, valves, etc. as required for accurate pricing.

The re-installation of the environmental chamber should require extension of the piping only with no new valves or other components.

91 2M102

For the environmental chamber, please advise how much charge will be needed and if there is any special requirements for re-charging the equipment.

Additionally, please confirm what type of refrigerant is to be used.

Approximately 50 LBS of R-

507 Refrigerant is required for re-charging the equipment.

Assume there are no special requirements for re-charging the equipment.

92 2I402

Since no details are available and the nature, size, complexity of it is unknown, please advise if a $2,500 allowance will be sufficient to provide the laser cut brushed aluminum sign with a backlight on drawing 2I402. If so, this will be built into our price proposal.

Please assume a $10,000 allowance.

93 31 62 00

Will the overhead bay doors be able to stay open, to allow for ventilation, while diesel equipment is running inside the the buidling?

Typically doors cannot remain open as a means of ventilation.

Refer to general sheets and division 1 specifications for building enclosure requirements during construction. If nessary for work execution, overhead bay doors may be left open for a limited duration, but must be coordinated with the

Contracting Officer a minimum of ten (10) working days in advance and approved by NSWCPD.

94 31 62 00

Were there any monitoring wells installed for the purpose of long term montitoring of the methane gas? If so, can this data be made available?

Monitoring wells have not been installed.

For bidding purposes, please indicate how much fuel (in gallons) should be included for the temporary fire pump throughout the duration of the project.

Contractor is responsible for fuel required to perform pump commissioning, initial startup, and to top off of the tank. For bidding purposes, assume 500 gallons. Contractor is responsible for removal/disposal of excess fuel when the temporary pump assembly and house is removed after B485 is renovated.

What is the expected completion date for the perimeter security fence project that is indicated as out of contract on the drawings, such that access to exterior

B77H areas will be controlled/restricted to badged personnel?

The expected completion date is unknown. For bidding purposes, assume that access to exterior B77H areas will be controlled/restricted to badged personnel for the project duration.

97 2M604

Regarding the CRAC units on drawing

2M604 detail C1, there are packaged controls included. However, some points are marked in the schedule of this detail without 'Note 1' which states: "Obtain input through a BACnet connection to packaged unit controller." Are the points marked without 'Note 1' to be controlled directly by the Controls Subcontractor?

The points that are referenced with Note 1 are analog and digital inputs for monitoring only. There are no controls commands associated with these points.

98 2M606

In reference to drawing 2M606 detail

A1, are the only points to be controlled by the controls contractor the points described in the 'Cooling Tower Pump

System Points List' table with the remaining 'Process Cooling Water' points remaining existing.

The only points to be provided by the controls contractor are those points indicated in the points list.

99 2M606

On drawing 2M606 detail A1, 'Note 1' states "Refer to reference drawings

"Cooling Water System - As-Build

Drawings" and "Cooling Water System -

Controls Hardware" for supplemental information regarding the existing conditions and controls components required for integration to the existing cooling water controls system." Can these documents be provided?

Drawings provided as part of this Amendment.

100 31 62 00

Was there a Health and Safety Plan completed for this site? If so, can the report be made available? If not, can a

HASP be requested?

No hazards have been identified above and beyond what can be controlled/mitigated through design and construction.

CLIN0010- option 9: Is the intent of this solely for branch line/circuit replacement, or are mains and risers to be excluded from the base price CLIN and included here?

The intent is solely for branch line / circuit replacement.

Mains, risers, and other services passing through space and serving other areas of the building should not be included in this CLIN.

Can photos of the interior (existing flooring) of Building 485 please be provided?

No. There are photos, but they are not approved for public release. The existing floor is concrete with an epoxy coating

103 2E601

Keynote #2 on drawing 2E601 refers you to the grounding plans for quantity and location of the 'DLO' cables, however, there is no location indicated on the grounding plans. Please provide.

Provide DLO cables at each column of the equipment platforms. The length of each cable should be the height of the equipment platform plus

12'-0" as identified on sheet

2E601. Refer to amended grounding plan sheets 2E151 and 2E155.

2.00E+11

Keynotes #5 and #7 on drawing 2E111 are related to the environmental chamber which states to extend the existing circuits and to provide a NFSS, however, the circuits are not sized nor is the NFSS.

The closest panels are L-5D and L-7D, but neither of those indicate circuits for this chamber. Please advise.

Assume that the branch circuit for the environmental chamber originates inside of the Lab.

We were not able to very the exact size of the branch circuit requirements for the environmental chamber.

Assume a maximum circuit size of 70A, 208V or 480V, three-phase.

2.00E+11

Keynote #6 on drawing 2E111 are related to the environmental chamber which states to extend and reconnect existing control conduit, however, no size is indicated nor number/size of conductors. Please advise.

For control wiring, assume a maximum of (12) #14 AWG conductors.

01 91 00.15

22; 23 08

00.00 20

1.7.1; 1.1

Is the CxA (Summers Consultants) also assuming the role of CxC as described in these references? Can the terms CxA and

CxC be used interchangeably? In other words, please confirm that the ktrs are responsible for only the Lead Cx

Representative (para 1.7.4) (Prime

Contractor) and the Cx

Specialists/Representatives

(subcontractors).

"Section 01 91 00.15 22, paragraph 1.1 states that the

Government is hiring an independent Commissioning

Firm. Paragraph 1.7.1 defines the CxC as the entity that performs all commissioning responsibilities.

2E404 &

2E709

Panel FF-Heater is a 500A Class 1 Div 1

Panel (keynote #8 on sheet 2E404), however, Square D does not make a panel that size in Class 1 Div 1. The providing subcontractor can provide (2)

225A panels in Class 1 Div 1, please advise.

Eaton Crouse-Hinds appears to have a series of panelboards rated for the proposed hazardous location with ratings available up to a 600A main bus.

108 1C107 Key notes

24, 25.

Both of these notes indicate scope by the

Utility Provider (assumed to be

Dominion) but the notes and details refered to are silent as to the extent of scope by the Utility. This typically depends upon the scope of a contract between NAVFAC and Dominion. Is that scope finalized and can the scope be provided? If not, for bid purposes please provide the detailed scope that Dominion will provide. For example, ktr build ductbanks and pull cable and Dominion will make terminations, ktr build pad, install switch, Dominion will furnish the switch and make terminations, or some variation thereof.

The Utility Provider will provide the switch, concrete pad, ductbank, wiring, excavation, trench repair/site restoration, etc. associated with installation and connectivity at and upstream of the 6-way switch. This project will provide all work downstream of the switch.

For bidding and schedule purposes, how much time should be alloted for the

Government's provision of the Air

Permit for the temporary fire pump?

"Refer to specification 21 30

00 paragraph 2.3.3. ""The installation permit application process will take up to five (5) months and begins when the

Government has all information necessary from the Contractor to build and submit the permit.”

Please provide bid quantity for concrete ceiling patching after sprinkler demolition.

For keynote #2 on 2FD107, assume for bidding purposes there are 8 locations that require patching and each location is approximately 4" diameter and 10" thick.

111 2P302

Fuel Tank room - Section C3/2P302 appears to indicate that the Fuel Tank room is sitting on support beams of some sort. There is no indication of this on the structural drawings. Please clarify.

W4x13# support beams are specified to be provided with the tank in 33 56 10, Paragraph 2.4.1.g.7.

The following information has been revised:

DRAWINGS:

On NAVFAC Drawing No. 12900955 (1G002):

REPLACE the following drawing in the DRAWING INDEX under the corresponding discipline and drawing number. This drawing accompanies this Amendment:

2A152 12901126 CONTROL HOUSE - MEZZANINE PLAN – REPLACE SHEET

On NAVFAC Drawing No. 12900957 (1G004):

REPLACE the following drawing in the DRAWING INDEX under the corresponding discipline and drawing number. This drawing

2E151 12901430 FIRST FLOOR PLAN - PART A - GROUNDING – REPLACE SHEET

2E155 12901434 FIRST FLOOR PLAN - PART E - GROUNDING – REPLACE SHEET

On NAVFAC Drawing No. 12901020 (2G002):

REPLACE the following drawing in the DRAWING INDEX under the corresponding discipline and drawing number. This drawing

2A152 12901126 CONTROL HOUSE - MEZZANINE PLAN – REPLACE SHEET

On NAVFAC Drawing No. 12901022 (2G004):

REPLACE the following drawing in the DRAWING INDEX under the corresponding discipline and drawing number. This drawing

2E151 12901430 FIRST FLOOR PLAN - PART A - GROUNDING – REPLACE SHEET

2E155 12901434 FIRST FLOOR PLAN - PART E - GROUNDING – REPLACE SHEET

On NAVFAC Drawing No. 12901126 (2A152):

ADD Sheet Keynote 4.

On NAVFAC Drawing No. 12901430 (2E151):

ADD Sheet Keynote 10.

On NAVFAC Drawing No. 12901434 (2E155):

ADD Sheet Keynote 14.

SPECIFICATIONS:

PROJECT TABLE OF CONTENTS

REPLACE the following sections with the attached sections that accompany this Amendment.

01 33 00 - SUBMITTAL PROCEDURES- July 10, 2024

03 30 00 - CAST-IN-PLACE CONCRETE - July 10, 2024

21 30 00 – FIRE PUMPS – July 10, 2024

23 30 00 - HVAC AIR DISTRIBUTION - July 10, 2024

DOCUMENT 00 01 15 LIST OF DRAWINGS

1.2 CONTRACT DRAWINGS

DELETE and REPLACE the following drawings as of 7/10/2024. These drawings accompany this Amendment.

DRAWING

NO.

REVISION

NO.

NAVFAC

DWG NO.

TITLE

2A152 1 12901126 CONTROL HOUSE - MEZZANINE PLAN

2E151 1 12901430 FIRST FLOOR PLAN - PART A - GROUNDING

2E155 1 12901434 FIRST FLOOR PLAN - PART E - GROUNDING

01 33 00 - SUBMITTAL PROCEDURES- July 10, 2024

ADD Construction and movement joints submittal to page 13 of the submittal register.

03 30 00 - CAST-IN-PLACE CONCRETE - July 10, 2024

ADD Construction and movement joints submittal to paragraph 1.3.

21 30 00 – FIRE PUMPS – July 10, 2024

ADD paragraph 3.13 TEMPORARY FIRE PUMPS

Contractor is responsible for final design, installation, and operation of the temporary pump system.

Test and demonstrate to the Government all operational and alarm functions of the temporary fire pump prior to decommissioning the existing B485 fire pumps.

Test and demonstrate to the Government all operational and alarm functions of the new fire pumps prior to decommissioning the temporary fire pump.

The temporary fire pump system must be operational throughout the entire duration the new and existing B485 fire pumps are out of service. The temporary station must be installed, tested, commissioned, and demonstrated to run prior to B485 pumps being taken offline.

Contractor is responsible for fuel required to perform pump commissioning, initial startup, and to top off of the tank. For bidding purposes assume 500 gallons. Contractor is responsible for removal/disposal of excess fuel when the temporary pump assembly and house is removed after B485 is renovated.

Provide routine maintenance and inspections of the temporary fire pumps in accordance with NFPA 20 and NFPA 25 throughout the duration of time that the temporary fire pump is in service.

23 30 00 - HVAC AIR DISTRIBUTION - July 10, 2024

DELETE 3” from paragraph 2.12.1.a. (1) and REPLACE with 2”.

ATTACHMENTS:

1. Amendment 0004 - Reference Drawings

a. Amendment 0004 - Cooling Tower System – As-Built Drawings.pdf

b. Amendment 0004 - Cooling Tower System – Controls Hardware.pdf

c. Amendment 0004 - Fuel Oil System – Control Panel CP-FOPV As-Built Drawings.pdf

d. Amendment 0004 - Fuel Oil system – Modifications to Existing Panel CP-FOPV.pdf

2. Amendment 0004 - PPI 84 - NSWC Building 77H Roof Repair record drawings

3. Amendment 0004 - FFG-62 Drawings Signed

4. Amendment 0004 - FFG-62 Specifications

(End of Summary Changes)

File details come from the government source that posted it. Updated .