AMENDMENT 0005.pdf
PDF 448 KB Posted
- Solicitation number
- N4008524R2531
About this file
This document is an amendment to a federal solicitation for the Design-Bid-Build, P-226 Maintenance Facility and Marine Air Group Headquarters at the Marine Corps Air Station in Cherry Point, North Carolina. The key details are:
The purpose of this amendment is to extend the proposal due date to November 19, 2024, provide responses to pre-proposal inquiries, and issue revised specifications and drawings. The pre-proposal inquiries cover topics such as control device locations, ductless split system requirements, gas and water meter locations, and AHU fan configurations. The revised drawings and specifications include updates to the control system details, ventilation equipment, plumbing, and architectural elements.
The original solicitation was issued by the Department of the Navy, Naval Facilities Engineering Command for the construction of a maintenance facility, headquarters building, and renovation work. The project includes site improvements, demolition, and upgrades to electrical distribution. This amendment provides clarification and changes to the technical requirements in response to contractor feedback.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT J 1 40
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0005 13-Nov-2024
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFAC MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N4008524R2531
9B. DATED (SEE ITEM 11)
30-Aug-2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SOLICITATION NO. N4008524R2531 DESIGN-BID-BUILD, P-226 MAINTENANCE FACILITY & MARINE AIR GROUP
HEADQUARTERS, MARINE CORPS AIR STATION, CHERRY POINT, NORTH CAROLINA
The proposal due date has been extended to 19 November 2024 NLT than 1400 (EST)..
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil
N4008524R2531
SF 30 BLOCK 14 CONTINUATION PAGE
The purpose of this amendment is to provide the following:
1. Extend proposal due date to 19 November 2024 NLT 2:00PM EST.
2. Responses to Pre-Proposal Inquiries (PPI’s)
3. Revised Specifications
4. Revised Drawings – must be requested in accordance with the RFP
Pre-Proposal Inquiry Responses:
Question # Reference
Question Government Response Page Section Paragraph
M101 &
M703
3916. M101 and M703. RTU2 and RTU5 are shown with wall mounted room sensors. They are
VAV RTUs and should not have room sensors other than the room sensors that are wired to vav boxes that are fed by the RTUs?
Correct. RTU-2 and RTU-5 leaving air conditions should be monitored and controlled by duct mounted sensors. Space sensor should only be required for VAV terminal zones.
Revised drawings provided with Amendment 0005.
M603
3916. M101 and M603.
M101/Plan Note 4 and M603
(louver schedule) call for the wall louver to be factory provided with a motorized damper. However, M101 shows the dampers in field installed duct plenum inside the building. Please clarify which location is applicable to prevent duplication.
Intent is to include a class 1A motorized damper as close to exterior penetration as possible to comply with ATFP UFC requirements. Whether that be integral to the louver or in the duct plenum behind the louver is at the discretion of the contractor.
A2/M70
3916. A2/M701 shows a Cisco
Catalyst 3560-CX switch connecting the building to the offsite EMCS. We believe that switch is obsolete and has been superseded by the following terminology: "Cisco switch
C9200CX-8P-2X2G, Cisco
Network Advantage, Software
License, 3-year term, and Cisco
Fiber SFP Transceiver, GLC-LX-
SM-RGD". This also applies to
MAG HQ/M701 and MALS
14B/M701.
Correct. MALS DDC System
Architecture detail has been updated to reflect this in the latest MALS 14B MOD revision 2 drawing set. 3916 and MAG HQ drawing sets will be revised to match.
A1/M70
3916. A1/M702. Notes for the emergency gas shutdown switch say, "locate in mechanical building near exit door". There are many building exit doors, and no building area is called
"mechanical building". Please add a Plan Note indicating the desired location.
Gas shutdown switch should be located in area not accessible by public. 113 Comm or 110
Elec. Revised drawings provided with Amendment
0005.
M703 &
M704
3916. M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a similar demarcation or note to provide the same information about the control devices in the
Outside Air stream upstream of the mix with Return Air.
Only components explicitly labeled field provided/installed are typically field provided/installed.
Factory/field installed will ultimately be dependent on what equipment is submitted.
Contractor is responsible for ensuring components shown on drawings are provided, whether field or factory installed.
Revised drawings provided with Amendment 0005.
12 M703
3916. M703. Is the SA duct static pressure transmitter provided loose with the RTU for field mounting and wiring?
Duct static pressure sensor is provided loose for field installation. Duct static pressure sensor should be installed in location to provide manufacturer's required clearances and straight duct lengths for proper operation.
13 M101
3916. M101. Please indicate the desired location of the duct static pressure transmitters for RTU2 and RTU5. Likewise for SA duct
DP transmitters for all multizone vav AHUs in all buildings.
Provide duct static pressure transmitters approximately 2/3 of the duct static pressure drop from the fan outlet to the furthest terminal unit inlet
(multi-zone) and 2/3 of the duct static pressure drop from the fan outlet to the furthest duct runout off main (single zone).
Duct static pressure sensor should be installed in location to provide manufacturer's required clearances and straight duct lengths for proper operation.
14 M603
3916. M603. Should BACnet
MS/TP communication capability be added to schedule notes for the ductless split system? Alternately maybe copy-paste-site adapt the points list/sequence/drawing for ductless splits that are in
A1/M704 in the MAG HQ drawing set? That MAG HQ points list mentions BACnet interface.
Control detail added via
Amendment 0005.
15 M702
MAG HQ. M702. Sequence for
AHU1 requires fan shut down on operation of a high SA duct static pressure safety switch, however, no switch is shown on the control drawing or points list. Same situation occurs in MALS 14 on
M702.
Provided with Amendment
0005.
M603 and
M703
MAG HQ. M603 and M703.
This is in regard to AHU-2 which has a dx split system to provide emergency cooling or heating if the CHW or HW system is not
Revise control detail for operation clarification via
Amendment 0005.
functioning. The intent is clear, but additional requirements for the dx system are needed. At anything less than full load it is impossible to maintain a stable discharge air temperature on a dx vav AHU unless at least one compressor is variable speed.
Cycling a constant speed compressor on/off results in swings in discharge air temperature the timing and size of which is load dependent and uncontrollable. Although it is not specifically stated, the two separate sets of equally sized refrigerant suction and liquid lines indicates a vertically split refrigerant coil, i.e. the compressors do not share suction or discharge and are probably the same capacity. We recommend the following note be added to the
AHU schedule and be applied to
AHU-2: "The refrigerant coil shall be vertically split with each portion of the coil carrying half the load at system full load. The portion of the split coil that is second in the air stream in the direction of air flow is called
Circuit #2. The first in the airstream is Circuit #1. Each portion of the coil shall be served exclusively by one compressor, i.e. the compressors do not share suction or discharge. The compressor serving Circuit #2 must be variable speed from 5% to 100% of its capacity and must be capable of being modulated over that entire range by the building digital control system
(BAS) via a hardwired analog signal (not via open protocol interface). At AHU loads less than 50% of design, Circuit #2 will be modulated by the BAS to maintain supply air temperature set point. At loads greater than
50%, Circuit #1 will be turned on by the BAS at 100% and Circuit
#2 will be modulated by the BAS to maintain supply air temperature set point. An electronic "smart" expansion valve shall be provided for Circuit
#2 and if necessary, the expansion valve shall communicate with the condensing unit (HP-1) to insure safe refrigerant pressures and oil return."
MP401
A2/M70
MAG HQ. MP401 & A2/M708.
A2/M708 requires BAS to monitor gas flow rate, presumably via a signal produced by the gas meter. Plan Note 15/MP401 requires the utility to provide the gas meter. How do we know the meter provided by the utility will have an output compatible with the building BAS? This applies to all buildings with gas meters.
Control detail is for separate gas flow meter to allow for base to monitor through DDC.
Revised drawings provided for clarification with Amendment
0005.
P102, A1/M70
8, CU101
MAG HQ. P102, CU101, and
A1/M708. Problem #1: Plan
Note 3/P102 shows domestic water entering at the northwest corner of Mechanical Room 135 but no meter is shown; the note refers to civil drawings for further information. However, Keynote
4/CU101 says "All water meters
... are located inside building.
See plumbing plans." Thus, there is a conflict between civil and plumbing drawings, and neither is presently responsible for the meter. Problem #2: A1/M708 requires BAS to monitor water flow rate, presumably via a signal produced by the water meter.
How do we know the meter will have an output compatible with the building BAS? Who is responsible for providing the water meter in all three buildings?
Sheet P-501, Detail C1 shows the water meter. It is noted to have remote ready capability to the DDC and read in US gallons or liters. All three buildings have this covered on the Backflow Preventer detail.
19 M707
MAG HQ. M707. The control drawing shows two flow meters.
They both measure the same value, but in different locations.
Could one be deleted? Same comment applies to MALS
14B/M706.
Yes, flow meter on return side can be removed. Revised drawings provided with
Amendment 0005.
20 M707
MAG HQ. M707. B-1 return water temperature and B-2 return water temperature are both in the points list, but neither is on the control drawing. The values of
B-1 and B-2 entering water temperature will be the same.
Why not delete the individual boiler return water temperatures and add one boiler return water temperature to the rturn water header in the drawing? Same comment applies to MALS
14B/M706.
Concur. Common return boiler loop temperature sensor can be provided in lieu of Individual boiler return temperature sensors. Revised drawings
0005.
MH101
A4/M70
MALS 14. MH101 and
A4/M708. EF-5 serves Hazmat
Room 140. There is no motorized damper shown in the duct on
MH101. EF-5 is included with four other EFs in the sequence and points lists in A4/M708 including references to interlocks with AHUs, shut down, and damper closure in response to
ATFP ESS operation. Inclusion of EF-5 with those other four EFs does not seem appropriate?
Should EF-5 have a motorized damper? Does it run constantly even when ATFP ESS has been activated?
PENDING RESPONSE
22 MH101
MALS 14. MH101. Should EF-4 have a motorized damper and associated louver?
Yes, motorized damper to be provided as shown in controls detail associated with EF-4.
Revised drawings provided with Amendment 0005.
A1/M50
MALS 14. A1/M501. If the gas meter is outdoors, and the emergency gas shutoff solenoid valve and manual switch are indoors, then it seems the riser diagram might need to be rearranged at the upper right end?
Same comment applicable to the other buildings.
Gas riser detail is diagrammatic only and note specifies that solenoid valve is to be provided indoors. Contractor is responsible for providing routing of gas piping in field and location of solenoid valve is dependent on exact routing of piping. Ensure solenoid valve is provided as listed in note, prior to any branch or connection to gas-fired equipment.
A1/M70
MALS 14. A1/M709. It says gas meter is to be located in mechanical room. That agrees with A1/M501. Both of those conflict with Plan Note
15/MH402. What is the actual location of the gas meter? This question is applicable to MAG
HQ also.
Gas meter on gas riser detail and floor plans is provided by utility company and installed on exterior of building. Civil contractor is to coordinate with utility company on routing from main to exterior of building as shown on floor plans. Control detail is for separate gas flow meter to allow for base to monitor through DDC. Revised drawings provided with
Amendment 0005.
M602 &
M702
MALS 14. M602 and M702.
AHU schedules note 7 is applied to all five AHUs. It says, "Unit shall have plenum style supply fan". AHU schedules note 2 is applied to all five AHUs. It says, "provide direct drive fans ... with
EC motors (VFDs not required)".
Taken together we interpret those notes to mean all AHUs have a supply air "fan wall" even if there is only one fan in the wall. Item
Provide all AHU's with supply fan with VFD. Revised drawings provided with
Amendment 0005.
1: Please clarify if "fan wall" is a correct interpretation. Item 2:
Why does M702 show only one fan for AHU-1 & 5 (two fans for each in the schedule). Item 3: If
AHUs have EC motors in lieu of
VFDs, why does M702 show
VFDs, and why are there VFDs in multiple locations on the floor plans for these AHUs?
M702 &
A3/M30
1 &
C4/MH4
MALS 14. M702, C4/MH402, &
A3/M301. M702 shows a motorized OA damper for AHU-
5. C4/MH402 shows a motorized
OA damper and associated louver
L-5 for AHU-5. Should
A3/M301 also show a motorized damper and/or louver?
Yes, provide motorized damper and louver as shown on M-702, C4/MH402 and A3/M-301.
Revised drawings provided with Amendment 0005.
M705 &
D4/M50
MALS 14. M705 and D4/M503.
D4/M503 shows a BTU meter for the CHW system. M705 does not show a BTU meter. The requirement is complicated by the fact that a BTU meter Points List is shown in A4/M709 but it is not assigned to any system ... CHW, HW, or otherwise. Is a BTU meter actually required anywhere? Same question applies to MAG HQ.
BTU meter is not required, and information provided by BTU meter can be obtained by other
DDC points. Revised drawings provided with Amendment
0005.
28 M603
MALS 14. M603. Should there be a CHW minimum flow bypass valve in the valve schedule on
M603?
CHW bypass valve should be included. Revised drawings provided with Amendment
0005.
29 C1/M709
MALS 14. C1/M709. The sequence for ductless split systems says "ATFP shutdown shall be accomplished by both a hardwired shutdown wired in series with other safeties, and a ddc shutdown requiring a manual reset". (1) No other system in the building requires such a
"hardwired" shutdown in addition to the software (ddc) shutdown.
(2) These systems do not transfer air between indoors and outdoors, nor between rooms. (3) These systems often serve mission critical equipment. Question:
Should this hardwired requirement be deleted? This question is applicable to all three buildings.
Requirement should be deleted.
Spaces served by Ductless splits must remain operational regardless of ATFP/FA shutdown. Ductless splits are to be provided with BACnet
MS/TP compatibility to provide monitoring capabilities as shown in MAG A1/M704 control detail. Details will be revised to match for MALS and
3916 in Amendment 0005.
A1/M70
9, A1/M50
1, MH402
MALS 13. A1/M709. It says gas meter is to be located in mechanical room. That agrees with A1/M501. Both of those conflict with Plan Note
Gas meter on gas riser detail and floor plans is provided by utility company and installed on exterior of building. Civil contractor is to coordinate with
15/MH402. What is the actual location of the gas meter? This question is applicable to MAG
HQ also.
utility company on routing from main to exterior of building as shown on floor plans. Control detail is for separate gas flow meter to allow for base to monitor through DDC. Revised drawings provided with
Amendment 0005.
31 SF1442 SF1442
Specifications-SF1442-Please confirm that the government will be considered the generator of any existing hazardous waste encountered at the site and will sign all manifests.
Confirmed.
Attachm ent G-
Price
Schedule
Attachment
G- Price
Schedule
Attachment G- Price Schedule-
CLIN 0005 Unit price line item for removal and disposal of contaminated stockpiled soils above North Carolina action limits. Which North Carolina soil concentration regulation (action level) is required? Is it Residential at 1.56 mg/kg or
Industrial/occupational at 260 mg/kg?
Industrial/occupational at 260 mg/kg and review section 01 57
19 Temporary Environmental
Controls for additional criteria on removal and disposal of contaminated stockpiled soils.
01 91
00.15 01 91 00.15
General-01 91 00.15-01 91 00.15 section 1.11 notes "Gov't Hired
Commissioning Provider", so Cx is employed gov't under separate contract. Please verify if this is correct.
Correct
21 13 13
-3.6
21 13 13 -
3.6
Fire Protection/ Life Safety-21 13
13 -3.6-21 13 13-3.6 notes "color code mark piping red". Please clarify if all sprinkler pipes are to be painted red, whether concealed or exposed.
Paint sprinkler piping in accordance with specification section 09 90 00. Section 21 13
13 has been revised with
Amendment 0005.
21 13 13
- 2.2.1, MAG-14
A:
FX501,
detail
A1.
21 13 13 -
2.2.1, MAG-14
A: FX501,
detail A1.
Fire Protection/ Life Safety-21 13
13 - 2.2.1, MAG-14 A: FX501,
detail A1.-21 13 13-2.2.1 notes the underground pipe from 5' out to 1' above finished floor must be stainless steel. We have seen the
Stainless-Steel requirement for hangar facilities per UFC but have seen ductile iron used most often for other facilities. Please accept ductile iron (which is shown on FX501) in lieu of stainless steel for this fire water incoming line 5' out to 1' AFFE.
Paragraph 2.2.1 allows a continuous section of welded stainless-steel pipe, such as an
"in-building riser" to be used in lieu of detail A1 on sheet
FX501. Stainless steel is not required to be used.
23 21 13
- 2.1.3.1
23 21 13 -
2.1.3.1
Mechanical-23 21 13 - 2.1.3.1-
What is the cutoff size to install copper pipe for the Low
Temperature Water (LTW)
Heating system? Paragraph
2.1.3.2 Copper Tubing does not
identify pipe sizing requirements.
Typically, in the past we have had
See response to PPI #4 provided in Amendment 0003.
the option to install type "L" copper pipe up to 4" in pipe diameter, and schedule 40 Black
Carbon Steel for piping above 4" in pipe diameter. Will this installation method be acceptable for this project?
23 64 26-
2.2
23 64 26-
2.2
Mechanical-23 64 26-2.2-
Looking through spec section 23
64 26 Chilled Water Piping
Systems, I do not see copper pipe mentioned. Paragraph 2.2 Steel
Piping only mentions piping larger than 4" in diameter shall be steel pipe. Can type "L" copper pipe be used for the Chilled
Water Piping Systems for pipe 4" in diameter and smaller?
See response to PPI #5 provided in Amendment 0003.
23 81 00-
2.4.9
23 81 00-
2.4.9
Mechanical-23 81 00-2.4.9-Spec
Section 23 81 00 Decentralized
Unitary HVAC Equipment paragraph 2.4.9 Condensate Drain
Piping refers back to section 23
30 00 HVAC Air Distribution.
Looking at section 23 30 00 it does not state what piping material is to be used for the condensate drains. What pipe material will be required to use for the HVAC condensate drain piping?
See response to PPI #6 provided in Amendment 0003.
MALS-
14: P-
601 and
P-705
MALS-14:
P-601 and
P-705
Plumbing-MALS-14: P-601 and
P-705-MALS-14: P-601 notes the
AC-2 Air Compressor is provided by the 3rd Party Vendor handling the Fluid Distribution System, see equipment notes 2 and 3. There is no pipe run to and from this unit, see P-705. Please verify the
Contractor is not responsible to provide this AC-2-unit, piping, valves, fittings, tanks and fluids for this system.
The Fluid Distribution System
(including the AC-2 compressor) is by the 3rd Party
Vendor.
40 B-P-104 B-P-104
Plumbing-B-P-104-MALS-14B:
B-P-104 Keynote 9 "250 cubic foot steel nitrogen cylinder".
Who is to provide this? This is not listed on the plumbing schedule on B-P-601.
This will be clarified in the schedule, but we plan for this to be provided by the local nitrogen supplier that will keep the tank filled.
Attachm ent G-
Price
Schedule
Civil-Attachment G- Price
Schedule-CLIN 0006 - Option
Item No. 5 - Unit Price for excavation, handling, storage, sampling, analysis, treatment, backfill and disposal of non-hazardous contaminated soil media at a permitted licensed
RCRA D facility, complete in accordance with the drawings and specifications, but excluding
Industrial/occupational at 260 mg/kg and review section 01 57
19 Temporary Environmental
Controls for additional criteria on removal and disposal of contaminated stockpiled soils.
work provided in another Line
Item. Which North Carolina soil concentration regulation (action level) is required? Is it Residential at 1.56 mg/kg or
Industrial/occupational at 260 mg/kg?
Attachm ent G-
Schedule-CLIN 0008 - Option
Item No. 7 - Unit Price for collection, storage, testing and disposal impacted groundwater from fuel and Per- and
Polyfluoroalkyl substances.
Please confirm that there are no gasoline range organics (GRO) nor diesel range organics (DRO) contaminated soils to be encountered. If there are, please provide separate unit price line items on the Price Schedule.
Design is correct as shown.
Propose in accordance with the
RFP.
I-602 /
096723.1
I-602 /
096723.13
Architectural-I-602 / 096723.13-
Drawing I-602 appears to indicate
ETZ-1 & ETZ-2 as poured terrazzo, but the specifications call for standard resinous flooring. Please clarify if the corridors are to receive poured terrazzo or standard resinous flooring. If poured terrazzo, please provide specifications.
Terrazzo spec section 09 66 23 has been added via Amendment
0005.
A-103
(MAG-
14)
A-109
(MAG-
14)
A-501
(MAG-
14)
A-103
(MAG-14)
A-109
(MAG-14)
A-501
(MAG-14)
Architectural-A-103 (MAG-14)
A-109 (MAG-14) A-501 (MAG-
14)-For MAG-14, the Secure
Areas Plan A-109 shows a secure boundary around Rooms 130
EKMS Vault and 129 EKMS
(OSS/SIPR). Sheet A-103 shows wall types E1, F1, I, F, and D as perimeter walls. Per the Wall
Types on Sheet A-501, none of these Wall Types show RF shielding. Furthermore, Wall
Types F1 and E1 do not exist.
Please clarify the intent for the secure boundary of Rooms 129 and 130."
Provide per the Contract
Documents. Per government direction, Rooms 129 and 130 are considered secure, however
RF shielding is not required around the perimeter of Rooms
129 and 130.
S-201
(MAG-
14)
A-302
(MAG-
14)
S-201
(MAG-14)
A-302
(MAG-14)
Structural-S-201 (MAG-14) A-
302 (MAG-14)-The section details on Sheet S-201 show rigid insulation between the exterior
CMU and brick veneer extending to top of footing. Per A-302, the wall sections show the rigid insulation terminating at the finished floor, and then grouting the cavity from finish floor down to top of foundation. Please clarify."
For the MAG-14 Building, the rigid insulation will extend to the top of the footing as reflected in the structural drawings. The architectural drawings are revised via
Amendment 0005 to reflect the rigid insulation extending to the top of footing.
46 I101 I101
Communications-I101-Drawing I-
101 for all three buildings contains a schedule of CFCI equipment. These schedules call out Flat Panel Display. No specifications for these displays have been found. Please confirm that these are part of the A/V equipment estimate provided for
Option Item No. 8.
Confirmed. Flat panel displays are part of A/V equipment.
47 122413 122413
Architectural-122413-There is a specification section for roller window shades, but they are also mentioned in section120001.0020 for the FF&E. Please confirm that the cost of the roller window shades is to be included in the building construction CLINS and is not part of the FF&E estimate in option 9.
Rollershades are to be included in the construction budget, not
FF&E. Section 12 00 01.00 20 has been updated to remove any reference to rollershades
48 104416 104416
Architectural-104416-There is a specification section for fire extinguishers. For all three buildings, the fire extinguishers are listed in the furniture schedule
(E8). Please confirm that the cost for the fire extinguishers is to be included in the building construction CLINS and is not part of the FF&E estimate in
Option Item No. 9
Per 35% comment 1767624, only cabinets and wall hangers are part of the construction budget. Fire Extinguishers themselves are FF&E
49 126113 126113
Architectural-126113-Sub section
2.6 of specification section 12 61
13 lists Lectern Podium. For
MALS and MAG buildings, lecturers are listed in the furniture schedule (T12). Please confirm that the cost for the lectern podium is to be included in the building construction CLINS and is not part of the FF&E estimate in Option Item No. 9
Lectern podiums are part of the
FF&E and should not be included in building construction or AV package.
50 102239 102239
Architectural-102239-Spec section 10 22 39 calls for folding panel partitions. MALS-14 drawing A-112 shows operable partitions next to gridlines A.6 and B. Please provide detail drawing of operable partitions in classroom 243.
Revised drawings provided with Amendment 0005.
MAG-14
A:
FX501
MAG-14
A: FX501
Fire Protection/ Life Safety-
MAG-14 A: FX501-Detail A4 on
FX501 for MAG-14 does not show a waveguide, is a wave guide required for secure wall penetrations?
A waveguide is not required for secure wall penetrations.
MAG-
14A: P-
MAG-14A:
P-501
It is noted that this site is Seismic
Design Category B, so low seismic. Please verify detail B2 on P-501 is not applicable. There are no seismic specs for plumbing and mechanical and it is also noted in 21 13 13 that seismic restraint is not required for Fire
Protection. Please verify seismic is not applicable for this project.
Concur. This detail is not required for this project and removed via Amendment 0005 accordingly.
MAG-
14A: P-
MAG-14A:
P-601
BFP-2 is missing on P-601, is this the Fire Protection Backflow?
It is not a Fire Protection BFP.
It is for CW makeup for HVAC equipment and added via
Amendment 0005 to sheet P-
601 as required.
MALS-
14 I-114, S-125
MALS-14
I-114, S-
Equipment-MALS-14 I-114, S-
125-Drawing I-114 indicates 5-ton linear crane. Drawing S-125 does not show monorail system to support this linear crane.
Furthermore, no specifications are given for this linear crane system.
Please confirm linear cranes are on this project.
There is no linear crane in the
MALS-14 building. Please refer to the architectural drawings Sheets A-104 & A-
105 for the crane layouts. There is a total of (4) 5-ton Cranes,
(1) in the bay between column lines A to B, (2) in the bay between column lines C to D, and (1) in the bay between column lines E to F.
"41 22
13.15 -
1.3.1.1
"41 22
13.15 -
1.3.1.1
Equipment-41 22 13.15 - 1.3.1.1
S-134, S-135-Paragraph 1.3.1.1 of
Specification 41 22 13.15 notes that there is one (1) top running crane spanning 50 feet, and four
(4) top running cranes spanning
45 feet for a total of five (5) bridge cranes. Sheets S-134 and
S-135 only show a total of a total of three (3) bridge cranes. Please clarify the total number of bridge cranes on the project."
Please refer to the architectural drawings Sheets A-104 & A-
105 for the crane layouts. There is a total of (4) 5-ton Cranes,
(1) in the bay between column lines A to B, (2) in the bay between column lines C to D, and (1) in the bay between column lines E to F.
41 22
13.15 41 22 13.15
Equipment-41 22 13.15-
Specification 41 22 13.15 has no mention of anti-spark requirements. Please confirm all bridge cranes do not need to meet the requirements of minimum or maximum anti-spark.
PENDING RESPONSE
41 22
13.15 -
1.3.1.2
41 22 13.15
- 1.3.1.2
Equipment-41 22 13.15 - 1.3.1.2-
Paragraph 1.3.1.2 of Specification
41 22 13.15 says to "provide top running single girder electric bridge crane(s), with under running trolley mounted hoist..."
The sentence continues on to say
"...conforming to MHI 27.1, CMAA 70, and CMAA 74 service class, as applicable."
CMAA 70 is for multiple girders, and CMAA 74 is for single girders. Please confirm all bridge cranes are to be single girder.
All bridge cranes are to follow
CMAA 74 for single girders.
MAG-
14A, MP102
MAG-14A,
MP102
No waveguides are shown in
HWS&R pipe, are they required?
Waveguides are only required for HVAC duct penetrations.
Piping and conduit penetrations to be installed per detail C3/M-
505.
MAG-
14A, M-
MAG-14A,
M-506
Please verify ATFP bracing shown on M-506 for MAG-14 is not applicable since this is a seismic design category B project.
ATFP bracing is separate from seismic bracing.
Implementation of standards in
ATFP UFC 4 010 01 is mandatory for all new construction. ATFP Equipment
Bracing Standard 19 (s.3-20) applies.
BLDG
A-101, A-501
BLDG
A-101, A-
Structural-BLDG 3916 A-101, A-
501-For B3916, Sheet A-501 shows Wall Type B extending to roof deck above. Please confirm that all walls denoted as Wall
Type B on Sheet A-101 are to extend to roof deck above."
Revised drawings provided via
Amendment 0005.
BLDG
3916, CU101
BLDG
3916, CU101
Keynote 2 calls for a sanitary sewer packaged pump station of like kind and size with PVC gravity. Please provide details for the pump station and a pipe size for the PVC gravity line.
PENDING RESPONSE
01 31
23.13 20
01 31 23.13
Security-01 31 23.13 20-01 31
23.13 20 - 1.5 identifies direction about Security Classification, specifically CUI and 1.6 breaks down restricted information.
1.6.2 provides a Table of Project
Documentation Types and provides remarks. Submittals and
Submittal Register the remarks are blank but Shop Drawings notes, ""Locations of sensitive areas must be labeled as either
""Controlled Area"" or
""Restricted Area” and may be shown on unclassified documents with the approval from Site
Security Manager."" 1 - Please confirm if Submittals generated by the offeror and subcontractor need to marked CUI? 2 - Please confirm if Shop Drawings, such as the reinforcing shop drawings, need to be marked CUI?
Submittals are not Controlled
Unclassified Information, unless determined by the government following submittal.
MAG
HQ -
CS101
MAG HQ -
CS101
Keynote 7 says to Remove Drive
Aisle from P-239 Scope. Please confirm that P-239 scope will not have conflicts with P-226 pavement connections.
Design is correct as shown.
Propose in accordance with the
RFP.
MAG
HQ -
CS101
MAG HQ -
CS101
Keynote 21 says to remove pavement patch from P-239
Scope. Please confirm that there are no utility conflicts with what is shown on P-226 utility
Design is correct as shown.
Propose in accordance with the
RFP.
connections and with what is shown on P-239 plans.
MAG
HQ -
CS102
MAG HQ -
CS102
Note 6 on CS102 (22 of 714) says
P-239 PLANS WERE
PROVIDED BY THE
GOVERNMENT AND IS
SHOWN FOR PLANNING
COORDINATION PURPOSES.
Please provide the P-239 plans.
Design is correct as shown.
Propose in accordance with the
RFP.
Attachm ent G-
Schedule-CLIN 0001D is Base
Price for Sitework of entire project site outside the facility's 5-foot line. Please confirm that
CLIN 0001D is for the combined sitework for both the MALS-14
Engine Maintenance Shop and the
MAG-14 Regiment al Group HQ and that the pricing for each site is not to be separate.
CLIN 0001D revised to CLIN
0001C. It is the combined sitework for the facilities.
Pricing is not separate for the 2 sites. Revised Attachment G –
Price Schedule Rev2 provided.
07 61
14.00 20
07 61 14.00
Architectural-07 61 14.00 20-07
61 14.00 20 - 1.7 says there shall be a Manufacturer's warranty for materials and workmanship not less than 30 years. It also notes to provide a 2-year contractor installation warranty. Please confirm the 2-year contractor installation warranty shall be provided by the roof installer, who may not be the offeror, due to special installer certifications.”
Propose in accordance with the
RFP.
Attachm ent G-
Schedule-CLIN 0005 for the removal and disposal of contaminated stockpiled soils.
Please confirm that this unit price includes excavation, handling, storage, sampling, analysis, transportation, any necessary treatment and disposal of PFAS impacted soil media at a permitted licensed facility and the replacement with structural backfill or NCDOT #57 crushed stone.
Refer to CLIN 0005 notes for all requirements on Attachment
G - Price Schedule Rev2.
Attachm ent G-
General-Attachment G- Price
Schedule-The Price Schedule section 1.3 A/V and FF&E Bid
Notes (CLIN 9 - 10) "F" states they can be awarded a minimum up-to 6 months prior to contract completion date. However, "G" states we must complete the
FF&E package at least 9 months to Beneficial Occupancy Date. Do to lead times on FF&E and A/V
Package and BVD must be completed at least 9 months prior to BOD. Award may be earlier, but no later than 6 months prior to completion date.
offerors need at least 12 months prior to the completion date to procure the material. Please consider changing the 6-month requirement to 12 months."
MALS-
14, S-
MALS-14,
S-101
Structural-MALS-14, S-101-On sheet S-101, the foundation plan notes the deep foundation system requirements box that calls out a minimum base bid tip elevation of
-8.00 feet (NAVD88). Please confirm that the precast pile design depth will not penetrate the aquafer.
The drawings reflect direction received from the government regarding depths, etc. Provide piles as in accordance with the
RFP.
Attachm ent G-
General-Attachment G- Price
Schedule-The Price Schedule section 1.3 A/V and FF&E Bid
Notes (CLIN 9 - 10) ""f"" states they can be awarded a minimum up-to 6 months prior to contract completion date. However, "g"" states we must complete the
FF&E package at least 9 months to Beneficial Occupancy Date.
There are 3 different buildings associated with this project, assuming Option 1 (CLIN 0002) is awarded although there is only one FF&E and 1 AV Planned
MOD for the entire project.
These buildings may all be completed at different times, some earlier than others. 1 - Will the government consider awarding the FF&E and AV in packages for each building to allow for earlier delivery? 2 -
Will the government base allowed timeline to award the FF&E and
AV based on the Contract
Completion or Beneficial
Occupancy Date for each building?
Propose in accordance with the
RFP.
MALS-
14, S-
MALS-14,
S-203
Equipment-MALS-14, S-203-
Detail A4 on Sheet S-203 does not show a crane rail on top of the bridge crane runway beam.
Please provide the desired crane rail and size.
Final design of the crane runway beam, haunch, runway beam bracing, rail stops, and connections are by the bridge crane manufacturer, however for pricing estimation purposes assume the crane runway beam is a W33x141 with top and bottom C15x33.9 channel caps and the haunches are W14x82.
MALS-
14, S-
MALS-14,
S-203
Equipment-MALS-14, S-203-
Detail A4 on Sheet S-203 says the bridge crane runway beam is to be a "W33 bridge crane rail w/
C15 cap." Please provide the desired weight of both the W33 beam and C channel.
Final design of the crane runway beam, haunch, runway beam bracing, rail stops, and connections are by the bridge crane manufacturer, however for pricing estimation purposes assume the crane runway beam is a W33x141 with top and bottom C15x33.9 channel caps and the haunches are W14x82.
74 CSP CSP
Security-CSP-Please confirm the
CSP only applies to the MAG HQ building and site.
PENDING RESPONSE
12 00 01
.00
12 00 01
.00
General-12 00 01 .00-12 00 01.00
20 - 1.2 notes the Government
FF&E estimate is $3,032,033.08, where the Attachment G - Price
Schedule CLIN 0010 states it is
$1,804,239. Please confirm which value is correct.
Combined totals for FF&E per the conceptual package is
$3,063,441.58, not including the contractors HAR. Spec
Section 12 00 01.00 has been updated to reflect this value.
12 00 01
.00 & 01
30 02.00
12 00 01
.00 & 01
30 02.00 22
Equipment-12 00 01 .00 & 01 30
02.00 22-12 00 01.00 - 1.2 notes the Design and documentation of the FF&E must be funded as
Interior Design Services in the base bid. 01 30 02.00 22 - 1.3 requires the Desing and documentation of the AV System to be funded as the AV Services
Option, this option is not identified on the Price Schedule.
1 - Please confirm if the FF&E
Interior Design Services MALS-
14 Engine Maintenance Shop should be with CLIN 0001A, MAG-14 Regimental Group HQ with CLIN 0001B. 2 - Please confirm if the FF&E Interior
Design Services BLDG 3916
Aircraft Armament shop is to be included in a Base Bind per 12 00
01.00 -1.2, if so which one, or with the Option CLIN 0002. 3 -
Please confirm where the Design and documentation of the AV
System is to be priced since there is not an AV Services Option."
"1 – FF&E Interior Design
Services for MALS-14 Engine
Maintenance is to be included in CLIN 0001A. FF&E Interior
Design Services for MAG-14
Regimental Group HQ is to be included in CLIN 0001B. 2 –
FF&E Interior Design Services for BLDG 3916 Aircraft
Armament Shop is to be included in CLIN 0002.
01 30
02.00 22
01 30 02.00
General-01 30 02.00 22-01 30
02.00 22 - 1.3 notes the
Government AV budget on the
Bid Schedule/Price Proposal
Form for the AV MOD is
$1,541,947, where the
Attachment G - Price Schedule
CLIN0009 states it is $1,511,012.
Please confirm which value is correct.
Revised Price Schedule
0005 to include updated A/V costs for CLIN 0009 – Option
08.
01 33 29
1.6.14.1.
01 33 29 -
1.6.14.1.1
Sustainability-01 33 29 -
1.6.14.1.1-01 33 29 - 1.6.14.1.1 notes the Project is already registered with Third Party
Certification (TPC) Organization.
Please confirm the offeror is not
Third Party Certification is not required because Controlled
Unclassified Information is included within the project documents.
responsible for any of the TPC costs only to complete with updating the required information to achieve final Certification or validations.
79 01 35 26 01 35 26
General-01 35 26-01 35 26 -
1.7.1.1 notes we are to provide a minimum one SSHO at each project site. Since this project has potentially multiple sites (MALS-
14 Engine Maintenance Shop, MAG-14 Regimental Group HQ, & BLDG 3916 Aircraft
Armament shop) that may be ongoing concurrently, please advise is an SSHO is required at each site.
Propose in accordance with the
RFP.
80 01 45 00 01 45 00
General-01 45 00-01 45 00-1.6.5 provide an experience Matrix for
QC specialists. The matrix identifies 2-1 Qualification and 2-
2 Experience for each specialist, however, the text is confusing.
For instance, for Mechanical it says 2-1. Graduate Mechanical
Engineer with a Professional
Engineer Registration, and 2-2 2-year experience or a person with
5 years of experience supervising mechanical features of work in the field with a construction company. Please confirm the correct interpretation for the requirement is: a Graduate
Mechanical Engineer with a
Professional Engineer
Registration and 2 years of experience OR a person 5 years of experience supervising mechanical features of work in the field with a construction company. Confirm this applies for all QC specialists in the
Matrix"
Confirmed.
81 01 45 00 01 45 00
General-01 45 00-Please confirm the Quality Control Manager can also serve as one of the QC
Specialists as long as they meet the qualification & experience requirements.
Propose in accordance with the
RFP.
82 01 45 00 01 45 00
General-01 45 00-01 45 00-1.6.5 notes the QC Specialists must be directly employed by the Prime
Contractor and cannot be employed by a supplier or subcontractor on the project.
Please confirm the QC specialist does not have to be a employee of the prime but can be from a 3rd
Party as long as they are not an employee of a supplier or subcontractor on the project?
83 B-C-501 B-C-501
Civil-B-C-501-Detail A4/C-501 for heavy duty asphalt pavement shows an 18" thick compacted select material base over an existing soil surface. Please confirm that the 18" thick select material can exist onsite material.
Provide imported select material.
84 A-B-101 A-B-101
Civil-A-B-101-On plan B-101, the geotechnical report summary refers to the final geotechnical engineering report dated February
10, 2023, as prepared by
AECOM. Refer to final geotechnical engineering report for additional information. Please provide the final geotechnical engineering report dated February
10, 2023, as prepared by
AECOM.
PENDING RESPONSE
85 A-B-501 A-B-501
Civil-A-B-501-Detail 7/B-501 calls for surcharge where applicable. Please confirm that there is no surcharge required on this project.
Surcharging is not required for this project.
86 A-B-501 A-B-501
Civil-A-B-501-Detail 8/B-501 calls for removal and replacement of existing fill beneath footing.
Please confirm that this item is to be included in CLIN 0004 Option
3-unit price for undercut and replacement with imported structural fill or with NCDOT #57 crushed stone. If this scope of work is not to be included in the unit price, please provide the depth and width of undercut and replacement that is to be included in the base bid.
Removal and replacement of geotechnically unsuitable subgrade soils will be paid for using CLIN 0004.
MAG-
14, A-
13 47 00
MAG-14,
A-109
13 47 00
Architectural-MAG-14, A-109 13
47 00-Specification 13 47 00
RADIANT BARRIERS,
Paragraph 2.1 references shielding to be tested to IEEE
299. We believe the design as shown on Sheet A-109 will not pass the IEEE 299 testing. In order to meet IEEE 299 testing requirements, the secure space must be a 6-sided enclosed area.
The plans show contradicting details/sections showing the foil only lapping 8” onto the floor and ceiling. Please clarify."
M703
M101 &
M703
Mechanical-M101 & M703-3916.
M101 and M703. RTU2 and
RTU5 are shown with wall mounted room sensors. They are
VAV RTUs and should not have room sensors other than the room sensors that are wired to vav boxes that are fed by the RTUs?
See response to PPI #7.
M101 &
M603
M101 &
M603
Mechanical-M101 & M603-3916.
M101 and M603. M101/Plan
Note 4 and M603 (louver schedule) call for the wall louver to be factory provided with a motorized damper. However, M101 shows the dampers in field installed duct plenum inside the building. Please clarify which location is applicable to prevent duplication.
See response to PPI #8.
A2/M70
A2/M701
Mechanical-A2/M701-3916.
A2/M701 shows a Cisco Catalyst
3560-CX switch connecting the building to the offsite EMCS. We believe that switch is obsolete and has been superseded by the following terminology: "Cisco switch C9200CX-8P-2X2G, Cisco Network Advantage, Software License, 3-year term, and Cisco Fiber SFP Transceiver, GLC-LX-SM-RGD". This also applies to MAG HQ/M701 and
MALS 14B/M701.
See response to PPI #9.
A1/M70
A1/M702
Mechanical-A1/M702-3916.
A1/M702. Notes for the emergency gas shutdown switch say, "locate in a mechanical building near the exit door".
There are many building exit doors, and no building area is called "mechanical building".
Please add a Plan Note indicating the desired location.
See response to PPI #10.
M703 &
M704
M703 &
M704
Mechanical-M703 & M704-3916.
M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a similar demarcation or note to provide the same information about the control devices in the
Outside Air stream upstream of the mix with Return Air.
See response to PPI #11.
M703 &
M704
M703 &
M704
Mechanical-M703 & M704-3916.
M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a
See response to PPI #11.
similar demarcation or note to provide the same information about the control devices in the
Outside Air stream upstream of the mix with Return Air.
94 M703 M703
Mechanical-M703-3916. M703.
Is the SA duct static pressure transmitter provided loose with the RTU for field mounting and wiring?
See response to PPI #12.
95 M101 M101
Mechanical-M101-3916. M101.
Please indicate the desired location of the duct static pressure transmitters for RTU2 and RTU5.
Likewise for SA duct DP transmitters for all multizone vav
AHUs in all buildings.
See response to PPI #13.
96 M603 M603
Mechanical-M603-3916. M603.
Should BACnet MS/TP communication capability be added to schedule notes for the ductless split system? Alternately maybe copy-paste-site adapt the points list/sequence/drawing for ductless splits that are in
A1/M704 in the MAG HQ drawing set? That MAG HQ points list mentions BACnet interface.
See response to PPI #14.
97 M702 M702
Mechanical-M702-MAG HQ.
M702. Sequence for AHU1 requires fan shut down on operation of a high SA duct static pressure safety switch, however, no switch is shown on the control drawing or points list. The same situation occurs in MALS 14 on
M702.
See response to PPI #15.
M603 and
M703
M603 and
M703
Mechanical-M603 and M703-
MAG HQ. M603 and M703.
This is in regard to AHU-2 which has a dx split system to provide emergency cooling or heating if the CHW or HW system is not functioning. The intent is clear, but additional requirements for the dx system are needed. At anything less than full load it is impossible to maintain a stable air discharge temperature on a dx vav
AHU unless at least one compressor is variable speed.
Cycling a constant speed compressor on/off results in swings in discharge air temperature the timing and size of which is load dependent and uncontrollable. Although it is not specifically stated, the two separate sets of equally sized
See response to PPI #16.
refrigerant suction and liquid lines indicate a vertically split refrigerant coil, i.e. the compressors do not share suction or discharge and are probably the same capacity. We recommend the following note be added to the
AHU schedule and be applied to
AHU-2: “The refrigerant coil shall be vertically split with each portion of the coil carrying half the load at system full load. The portion of the split coil that is second in the air stream in the direction of air flow is called
Circuit #2. The first in the airstream is Circuit #1. Each portion of the coil shall be served exclusively by one compressor, i.e. the compressors do not share suction or discharge. The compressor serving Circuit #2 must be variable speed from 5% to 100% of its capacity and must be capable of being modulated over that entire range by the building digital control system
(BAS) via a hardwired analog signal (not via open protocol interface). At AHU loads less than 50% of design, Circuit #2 will be modulated by the BAS to maintain supply air temperature set point. At loads greater than
50%, Circuit #1 will be turned on by the BAS at 100% and Circuit
#2 will be modulated by the BAS to maintain supply air temperature set point. An electronic "smart" expansion valve shall be provided for Circuit
#2 and if necessary, the expansion valve shall communicate with the condensing unit (HP-1) to insure safe refrigerant pressures and oil return."
MP401
A2/M70
MP401 &
A2/M708
Mechanical-MP401 & A2/M708-
MAG HQ. MP401 & A2/M708.
A2/M708 requires BAS to monitor gas flow rate, presumably via a signal produced by the gas meter. Plan Note 15/MP401 requires the utility to provide the gas meter. How do we know the meter provided by the utility will have an output compatible with the building BAS? This applies to all buildings with gas meters.
See response to PPI #17.
P102, A1/M70
8, CU101
P102, A1/M708, CU101
Mechanical-P102, A1/M708, CU101-MAG HQ. P102, CU101, and A1/M708. Problem #1: Plan
Note 3/P102 shows domestic water entering at the northwest corner of Mechanical Room 135 but no meter is shown; the note refers to civil drawings for further information. However, Keynote
4/CU101 says "All water meters
... are located inside building.
See plumbing plans." Thus, there is a conflict between civil and plumbing drawings, and neither is presently responsible for the meter. Problem #2: A1/M708 requires BAS to monitor water flow rate, presumably via a signal produced by the water meter.
How do we know the meter will have an output compatible with the building BAS? Who is responsible for providing the water meter in all three buildings?
Sheet P-501, Detail C1 shows the water meter. It is noted to have remote ready capability to the DDC and read in US gallons or liters. All three buildings have this covered on the Backflow Preventer detail.
101 M707 M707
Mechanical-M707-MAG HQ.
M707. The control drawing shows two flow meters. They both measure the same value, but in different locations. Could one be deleted? Same comment applies to MALS 14B/M706.
See response to PPI #19.
102 M707 M707
Mechanical-M707-MAG HQ.
M707. B-1 return water temperature and B-2 return water temperature are both in the points list, but neither is on the control…
This is the start of the file's text. The full file is on GovTribe.