About this file

This document is an amendment to a federal solicitation for the Design-Bid-Build, P-226 Maintenance Facility and Marine Air Group Headquarters at the Marine Corps Air Station in Cherry Point, North Carolina. The key details are:

The purpose of this amendment is to extend the proposal due date to November 19, 2024, provide responses to pre-proposal inquiries, and issue revised specifications and drawings. The pre-proposal inquiries cover topics such as control device locations, ductless split system requirements, gas and water meter locations, and AHU fan configurations. The revised drawings and specifications include updates to the control system details, ventilation equipment, plumbing, and architectural elements.

The original solicitation was issued by the Department of the Navy, Naval Facilities Engineering Command for the construction of a maintenance facility, headquarters building, and renovation work. The project includes site improvements, demolition, and upgrades to electrical distribution. This amendment provides clarification and changes to the technical requirements in response to contractor feedback.

View the file

Other files

File Type Posted
AMENDMENT 0012.pdf PDF
AMENDMENT 0011.pdf PDF
AMENDMENT 0010.pdf PDF
Amendment 0009 - JA ML-25-15 P226 Interior Finishes Redacted.pdf PDF
Amendment 0009 - JA ML-25-14 P226 Network Switches Redacted.pdf PDF
Amendment 0009 - JA ML-25-13 P226 Fire Protection Redacted.pdf PDF
AMENDMENT 0009.pdf PDF
AMENDMENT 0008.pdf PDF
AMENDMENT 0007.pdf PDF
Amendment 0007 - Attachment G - P226 Price Schedule_Rev3.docx DOCX document
Amendment 0006 - P226_F35 MCAS Cherry Point_HazMat Rpt.pdf PDF
AMENDMENT 0006.pdf PDF
Amendment 0006 - P226 F35 MCAS Cherry Point Geotech Report.pdf PDF
Amendment 0005 - 1712284 SPEC Rev.pdf PDF
Amendment 0005 - Attachment G - P226 Price Schedule_Rev2.docx DOCX document
AMENDMENT 0004.pdf PDF
AMENDMENT 0003.pdf PDF
Amendment 0002 - 1712284 REGISTER.pdf PDF
Amendment 0002 - 1712284 SPEC.pdf PDF
AMENDMENT 0002.pdf PDF
AMENDMENT 0001.pdf PDF
Amendment 0001 - Site Visit Sign-In Sheet.pdf PDF
Amendment 0001 - Attachment G - P226 Price Schedule_Rev1.docx DOCX document
Attachment E - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment B - Construction Experience Data Sheet.docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
1737342spc01of01.pdf PDF
Attachment G - P226 Price Schedule.docx DOCX document
Attachment D - Historical Small Business Utilization.docx DOCX document
N4008524R2531.pdf PDF
Attachment H - PIEE Vendor Access Instructions.pdf PDF
Attachment F - SBSP.docx DOCX document
Attachment C - Past Performance Questionnaire (PPQ).docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT J 1 40

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0005 13-Nov-2024

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

NAVFAC MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N4008524R2531

9B. DATED (SEE ITEM 11)

30-Aug-2024

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION NO. N4008524R2531 DESIGN-BID-BUILD, P-226 MAINTENANCE FACILITY & MARINE AIR GROUP

HEADQUARTERS, MARINE CORPS AIR STATION, CHERRY POINT, NORTH CAROLINA

The proposal due date has been extended to 19 November 2024 NLT than 1400 (EST)..

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil

N4008524R2531

SF 30 BLOCK 14 CONTINUATION PAGE

The purpose of this amendment is to provide the following:

1. Extend proposal due date to 19 November 2024 NLT 2:00PM EST.

2. Responses to Pre-Proposal Inquiries (PPI’s)

3. Revised Specifications

4. Revised Drawings – must be requested in accordance with the RFP

Pre-Proposal Inquiry Responses:

Question # Reference

Question Government Response Page Section Paragraph

M101 &

M703

3916. M101 and M703. RTU2 and RTU5 are shown with wall mounted room sensors. They are

VAV RTUs and should not have room sensors other than the room sensors that are wired to vav boxes that are fed by the RTUs?

Correct. RTU-2 and RTU-5 leaving air conditions should be monitored and controlled by duct mounted sensors. Space sensor should only be required for VAV terminal zones.

Revised drawings provided with Amendment 0005.

M603

3916. M101 and M603.

M101/Plan Note 4 and M603

(louver schedule) call for the wall louver to be factory provided with a motorized damper. However, M101 shows the dampers in field installed duct plenum inside the building. Please clarify which location is applicable to prevent duplication.

Intent is to include a class 1A motorized damper as close to exterior penetration as possible to comply with ATFP UFC requirements. Whether that be integral to the louver or in the duct plenum behind the louver is at the discretion of the contractor.

A2/M70

3916. A2/M701 shows a Cisco

Catalyst 3560-CX switch connecting the building to the offsite EMCS. We believe that switch is obsolete and has been superseded by the following terminology: "Cisco switch

C9200CX-8P-2X2G, Cisco

Network Advantage, Software

License, 3-year term, and Cisco

Fiber SFP Transceiver, GLC-LX-

SM-RGD". This also applies to

MAG HQ/M701 and MALS

14B/M701.

Correct. MALS DDC System

Architecture detail has been updated to reflect this in the latest MALS 14B MOD revision 2 drawing set. 3916 and MAG HQ drawing sets will be revised to match.

A1/M70

3916. A1/M702. Notes for the emergency gas shutdown switch say, "locate in mechanical building near exit door". There are many building exit doors, and no building area is called

"mechanical building". Please add a Plan Note indicating the desired location.

Gas shutdown switch should be located in area not accessible by public. 113 Comm or 110

Elec. Revised drawings provided with Amendment

0005.

M703 &

M704

3916. M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a similar demarcation or note to provide the same information about the control devices in the

Outside Air stream upstream of the mix with Return Air.

Only components explicitly labeled field provided/installed are typically field provided/installed.

Factory/field installed will ultimately be dependent on what equipment is submitted.

Contractor is responsible for ensuring components shown on drawings are provided, whether field or factory installed.

Revised drawings provided with Amendment 0005.

12 M703

3916. M703. Is the SA duct static pressure transmitter provided loose with the RTU for field mounting and wiring?

Duct static pressure sensor is provided loose for field installation. Duct static pressure sensor should be installed in location to provide manufacturer's required clearances and straight duct lengths for proper operation.

13 M101

3916. M101. Please indicate the desired location of the duct static pressure transmitters for RTU2 and RTU5. Likewise for SA duct

DP transmitters for all multizone vav AHUs in all buildings.

Provide duct static pressure transmitters approximately 2/3 of the duct static pressure drop from the fan outlet to the furthest terminal unit inlet

(multi-zone) and 2/3 of the duct static pressure drop from the fan outlet to the furthest duct runout off main (single zone).

Duct static pressure sensor should be installed in location to provide manufacturer's required clearances and straight duct lengths for proper operation.

14 M603

3916. M603. Should BACnet

MS/TP communication capability be added to schedule notes for the ductless split system? Alternately maybe copy-paste-site adapt the points list/sequence/drawing for ductless splits that are in

A1/M704 in the MAG HQ drawing set? That MAG HQ points list mentions BACnet interface.

Control detail added via

Amendment 0005.

15 M702

MAG HQ. M702. Sequence for

AHU1 requires fan shut down on operation of a high SA duct static pressure safety switch, however, no switch is shown on the control drawing or points list. Same situation occurs in MALS 14 on

M702.

Provided with Amendment

0005.

M603 and

M703

MAG HQ. M603 and M703.

This is in regard to AHU-2 which has a dx split system to provide emergency cooling or heating if the CHW or HW system is not

Revise control detail for operation clarification via

Amendment 0005.

functioning. The intent is clear, but additional requirements for the dx system are needed. At anything less than full load it is impossible to maintain a stable discharge air temperature on a dx vav AHU unless at least one compressor is variable speed.

Cycling a constant speed compressor on/off results in swings in discharge air temperature the timing and size of which is load dependent and uncontrollable. Although it is not specifically stated, the two separate sets of equally sized refrigerant suction and liquid lines indicates a vertically split refrigerant coil, i.e. the compressors do not share suction or discharge and are probably the same capacity. We recommend the following note be added to the

AHU schedule and be applied to

AHU-2: "The refrigerant coil shall be vertically split with each portion of the coil carrying half the load at system full load. The portion of the split coil that is second in the air stream in the direction of air flow is called

Circuit #2. The first in the airstream is Circuit #1. Each portion of the coil shall be served exclusively by one compressor, i.e. the compressors do not share suction or discharge. The compressor serving Circuit #2 must be variable speed from 5% to 100% of its capacity and must be capable of being modulated over that entire range by the building digital control system

(BAS) via a hardwired analog signal (not via open protocol interface). At AHU loads less than 50% of design, Circuit #2 will be modulated by the BAS to maintain supply air temperature set point. At loads greater than

50%, Circuit #1 will be turned on by the BAS at 100% and Circuit

#2 will be modulated by the BAS to maintain supply air temperature set point. An electronic "smart" expansion valve shall be provided for Circuit

#2 and if necessary, the expansion valve shall communicate with the condensing unit (HP-1) to insure safe refrigerant pressures and oil return."

MP401

A2/M70

MAG HQ. MP401 & A2/M708.

A2/M708 requires BAS to monitor gas flow rate, presumably via a signal produced by the gas meter. Plan Note 15/MP401 requires the utility to provide the gas meter. How do we know the meter provided by the utility will have an output compatible with the building BAS? This applies to all buildings with gas meters.

Control detail is for separate gas flow meter to allow for base to monitor through DDC.

Revised drawings provided for clarification with Amendment

0005.

P102, A1/M70

8, CU101

MAG HQ. P102, CU101, and

A1/M708. Problem #1: Plan

Note 3/P102 shows domestic water entering at the northwest corner of Mechanical Room 135 but no meter is shown; the note refers to civil drawings for further information. However, Keynote

4/CU101 says "All water meters

... are located inside building.

See plumbing plans." Thus, there is a conflict between civil and plumbing drawings, and neither is presently responsible for the meter. Problem #2: A1/M708 requires BAS to monitor water flow rate, presumably via a signal produced by the water meter.

How do we know the meter will have an output compatible with the building BAS? Who is responsible for providing the water meter in all three buildings?

Sheet P-501, Detail C1 shows the water meter. It is noted to have remote ready capability to the DDC and read in US gallons or liters. All three buildings have this covered on the Backflow Preventer detail.

19 M707

MAG HQ. M707. The control drawing shows two flow meters.

They both measure the same value, but in different locations.

Could one be deleted? Same comment applies to MALS

14B/M706.

Yes, flow meter on return side can be removed. Revised drawings provided with

Amendment 0005.

20 M707

MAG HQ. M707. B-1 return water temperature and B-2 return water temperature are both in the points list, but neither is on the control drawing. The values of

B-1 and B-2 entering water temperature will be the same.

Why not delete the individual boiler return water temperatures and add one boiler return water temperature to the rturn water header in the drawing? Same comment applies to MALS

14B/M706.

Concur. Common return boiler loop temperature sensor can be provided in lieu of Individual boiler return temperature sensors. Revised drawings

0005.

MH101

A4/M70

MALS 14. MH101 and

A4/M708. EF-5 serves Hazmat

Room 140. There is no motorized damper shown in the duct on

MH101. EF-5 is included with four other EFs in the sequence and points lists in A4/M708 including references to interlocks with AHUs, shut down, and damper closure in response to

ATFP ESS operation. Inclusion of EF-5 with those other four EFs does not seem appropriate?

Should EF-5 have a motorized damper? Does it run constantly even when ATFP ESS has been activated?

PENDING RESPONSE

22 MH101

MALS 14. MH101. Should EF-4 have a motorized damper and associated louver?

Yes, motorized damper to be provided as shown in controls detail associated with EF-4.

Revised drawings provided with Amendment 0005.

A1/M50

MALS 14. A1/M501. If the gas meter is outdoors, and the emergency gas shutoff solenoid valve and manual switch are indoors, then it seems the riser diagram might need to be rearranged at the upper right end?

Same comment applicable to the other buildings.

Gas riser detail is diagrammatic only and note specifies that solenoid valve is to be provided indoors. Contractor is responsible for providing routing of gas piping in field and location of solenoid valve is dependent on exact routing of piping. Ensure solenoid valve is provided as listed in note, prior to any branch or connection to gas-fired equipment.

A1/M70

MALS 14. A1/M709. It says gas meter is to be located in mechanical room. That agrees with A1/M501. Both of those conflict with Plan Note

15/MH402. What is the actual location of the gas meter? This question is applicable to MAG

HQ also.

Gas meter on gas riser detail and floor plans is provided by utility company and installed on exterior of building. Civil contractor is to coordinate with utility company on routing from main to exterior of building as shown on floor plans. Control detail is for separate gas flow meter to allow for base to monitor through DDC. Revised drawings provided with

Amendment 0005.

M602 &

M702

MALS 14. M602 and M702.

AHU schedules note 7 is applied to all five AHUs. It says, "Unit shall have plenum style supply fan". AHU schedules note 2 is applied to all five AHUs. It says, "provide direct drive fans ... with

EC motors (VFDs not required)".

Taken together we interpret those notes to mean all AHUs have a supply air "fan wall" even if there is only one fan in the wall. Item

Provide all AHU's with supply fan with VFD. Revised drawings provided with

Amendment 0005.

1: Please clarify if "fan wall" is a correct interpretation. Item 2:

Why does M702 show only one fan for AHU-1 & 5 (two fans for each in the schedule). Item 3: If

AHUs have EC motors in lieu of

VFDs, why does M702 show

VFDs, and why are there VFDs in multiple locations on the floor plans for these AHUs?

M702 &

A3/M30

1 &

C4/MH4

MALS 14. M702, C4/MH402, &

A3/M301. M702 shows a motorized OA damper for AHU-

5. C4/MH402 shows a motorized

OA damper and associated louver

L-5 for AHU-5. Should

A3/M301 also show a motorized damper and/or louver?

Yes, provide motorized damper and louver as shown on M-702, C4/MH402 and A3/M-301.

Revised drawings provided with Amendment 0005.

M705 &

D4/M50

MALS 14. M705 and D4/M503.

D4/M503 shows a BTU meter for the CHW system. M705 does not show a BTU meter. The requirement is complicated by the fact that a BTU meter Points List is shown in A4/M709 but it is not assigned to any system ... CHW, HW, or otherwise. Is a BTU meter actually required anywhere? Same question applies to MAG HQ.

BTU meter is not required, and information provided by BTU meter can be obtained by other

DDC points. Revised drawings provided with Amendment

0005.

28 M603

MALS 14. M603. Should there be a CHW minimum flow bypass valve in the valve schedule on

M603?

CHW bypass valve should be included. Revised drawings provided with Amendment

0005.

29 C1/M709

MALS 14. C1/M709. The sequence for ductless split systems says "ATFP shutdown shall be accomplished by both a hardwired shutdown wired in series with other safeties, and a ddc shutdown requiring a manual reset". (1) No other system in the building requires such a

"hardwired" shutdown in addition to the software (ddc) shutdown.

(2) These systems do not transfer air between indoors and outdoors, nor between rooms. (3) These systems often serve mission critical equipment. Question:

Should this hardwired requirement be deleted? This question is applicable to all three buildings.

Requirement should be deleted.

Spaces served by Ductless splits must remain operational regardless of ATFP/FA shutdown. Ductless splits are to be provided with BACnet

MS/TP compatibility to provide monitoring capabilities as shown in MAG A1/M704 control detail. Details will be revised to match for MALS and

3916 in Amendment 0005.

A1/M70

9, A1/M50

1, MH402

MALS 13. A1/M709. It says gas meter is to be located in mechanical room. That agrees with A1/M501. Both of those conflict with Plan Note

Gas meter on gas riser detail and floor plans is provided by utility company and installed on exterior of building. Civil contractor is to coordinate with

15/MH402. What is the actual location of the gas meter? This question is applicable to MAG

HQ also.

utility company on routing from main to exterior of building as shown on floor plans. Control detail is for separate gas flow meter to allow for base to monitor through DDC. Revised drawings provided with

Amendment 0005.

31 SF1442 SF1442

Specifications-SF1442-Please confirm that the government will be considered the generator of any existing hazardous waste encountered at the site and will sign all manifests.

Confirmed.

Attachm ent G-

Price

Schedule

Attachment

G- Price

Schedule

Attachment G- Price Schedule-

CLIN 0005 Unit price line item for removal and disposal of contaminated stockpiled soils above North Carolina action limits. Which North Carolina soil concentration regulation (action level) is required? Is it Residential at 1.56 mg/kg or

Industrial/occupational at 260 mg/kg?

Industrial/occupational at 260 mg/kg and review section 01 57

19 Temporary Environmental

Controls for additional criteria on removal and disposal of contaminated stockpiled soils.

01 91

00.15 01 91 00.15

General-01 91 00.15-01 91 00.15 section 1.11 notes "Gov't Hired

Commissioning Provider", so Cx is employed gov't under separate contract. Please verify if this is correct.

Correct

21 13 13

-3.6

21 13 13 -

3.6

Fire Protection/ Life Safety-21 13

13 -3.6-21 13 13-3.6 notes "color code mark piping red". Please clarify if all sprinkler pipes are to be painted red, whether concealed or exposed.

Paint sprinkler piping in accordance with specification section 09 90 00. Section 21 13

13 has been revised with

Amendment 0005.

21 13 13

- 2.2.1, MAG-14

A:

FX501,

detail

A1.

21 13 13 -

2.2.1, MAG-14

A: FX501,

detail A1.

Fire Protection/ Life Safety-21 13

13 - 2.2.1, MAG-14 A: FX501,

detail A1.-21 13 13-2.2.1 notes the underground pipe from 5' out to 1' above finished floor must be stainless steel. We have seen the

Stainless-Steel requirement for hangar facilities per UFC but have seen ductile iron used most often for other facilities. Please accept ductile iron (which is shown on FX501) in lieu of stainless steel for this fire water incoming line 5' out to 1' AFFE.

Paragraph 2.2.1 allows a continuous section of welded stainless-steel pipe, such as an

"in-building riser" to be used in lieu of detail A1 on sheet

FX501. Stainless steel is not required to be used.

23 21 13

- 2.1.3.1

23 21 13 -

2.1.3.1

Mechanical-23 21 13 - 2.1.3.1-

What is the cutoff size to install copper pipe for the Low

Temperature Water (LTW)

Heating system? Paragraph

2.1.3.2 Copper Tubing does not

identify pipe sizing requirements.

Typically, in the past we have had

See response to PPI #4 provided in Amendment 0003.

the option to install type "L" copper pipe up to 4" in pipe diameter, and schedule 40 Black

Carbon Steel for piping above 4" in pipe diameter. Will this installation method be acceptable for this project?

23 64 26-

2.2

23 64 26-

2.2

Mechanical-23 64 26-2.2-

Looking through spec section 23

64 26 Chilled Water Piping

Systems, I do not see copper pipe mentioned. Paragraph 2.2 Steel

Piping only mentions piping larger than 4" in diameter shall be steel pipe. Can type "L" copper pipe be used for the Chilled

Water Piping Systems for pipe 4" in diameter and smaller?

See response to PPI #5 provided in Amendment 0003.

23 81 00-

2.4.9

23 81 00-

2.4.9

Mechanical-23 81 00-2.4.9-Spec

Section 23 81 00 Decentralized

Unitary HVAC Equipment paragraph 2.4.9 Condensate Drain

Piping refers back to section 23

30 00 HVAC Air Distribution.

Looking at section 23 30 00 it does not state what piping material is to be used for the condensate drains. What pipe material will be required to use for the HVAC condensate drain piping?

See response to PPI #6 provided in Amendment 0003.

MALS-

14: P-

601 and

P-705

MALS-14:

P-601 and

P-705

Plumbing-MALS-14: P-601 and

P-705-MALS-14: P-601 notes the

AC-2 Air Compressor is provided by the 3rd Party Vendor handling the Fluid Distribution System, see equipment notes 2 and 3. There is no pipe run to and from this unit, see P-705. Please verify the

Contractor is not responsible to provide this AC-2-unit, piping, valves, fittings, tanks and fluids for this system.

The Fluid Distribution System

(including the AC-2 compressor) is by the 3rd Party

Vendor.

40 B-P-104 B-P-104

Plumbing-B-P-104-MALS-14B:

B-P-104 Keynote 9 "250 cubic foot steel nitrogen cylinder".

Who is to provide this? This is not listed on the plumbing schedule on B-P-601.

This will be clarified in the schedule, but we plan for this to be provided by the local nitrogen supplier that will keep the tank filled.

Attachm ent G-

Price

Schedule

Civil-Attachment G- Price

Schedule-CLIN 0006 - Option

Item No. 5 - Unit Price for excavation, handling, storage, sampling, analysis, treatment, backfill and disposal of non-hazardous contaminated soil media at a permitted licensed

RCRA D facility, complete in accordance with the drawings and specifications, but excluding

Industrial/occupational at 260 mg/kg and review section 01 57

19 Temporary Environmental

Controls for additional criteria on removal and disposal of contaminated stockpiled soils.

work provided in another Line

Item. Which North Carolina soil concentration regulation (action level) is required? Is it Residential at 1.56 mg/kg or

Industrial/occupational at 260 mg/kg?

Attachm ent G-

Schedule-CLIN 0008 - Option

Item No. 7 - Unit Price for collection, storage, testing and disposal impacted groundwater from fuel and Per- and

Polyfluoroalkyl substances.

Please confirm that there are no gasoline range organics (GRO) nor diesel range organics (DRO) contaminated soils to be encountered. If there are, please provide separate unit price line items on the Price Schedule.

Design is correct as shown.

Propose in accordance with the

RFP.

I-602 /

096723.1

I-602 /

096723.13

Architectural-I-602 / 096723.13-

Drawing I-602 appears to indicate

ETZ-1 & ETZ-2 as poured terrazzo, but the specifications call for standard resinous flooring. Please clarify if the corridors are to receive poured terrazzo or standard resinous flooring. If poured terrazzo, please provide specifications.

Terrazzo spec section 09 66 23 has been added via Amendment

0005.

A-103

(MAG-

14)

A-109

(MAG-

14)

A-501

(MAG-

14)

A-103

(MAG-14)

A-109

(MAG-14)

A-501

(MAG-14)

Architectural-A-103 (MAG-14)

A-109 (MAG-14) A-501 (MAG-

14)-For MAG-14, the Secure

Areas Plan A-109 shows a secure boundary around Rooms 130

EKMS Vault and 129 EKMS

(OSS/SIPR). Sheet A-103 shows wall types E1, F1, I, F, and D as perimeter walls. Per the Wall

Types on Sheet A-501, none of these Wall Types show RF shielding. Furthermore, Wall

Types F1 and E1 do not exist.

Please clarify the intent for the secure boundary of Rooms 129 and 130."

Provide per the Contract

Documents. Per government direction, Rooms 129 and 130 are considered secure, however

RF shielding is not required around the perimeter of Rooms

129 and 130.

S-201

(MAG-

14)

A-302

(MAG-

14)

S-201

(MAG-14)

A-302

(MAG-14)

Structural-S-201 (MAG-14) A-

302 (MAG-14)-The section details on Sheet S-201 show rigid insulation between the exterior

CMU and brick veneer extending to top of footing. Per A-302, the wall sections show the rigid insulation terminating at the finished floor, and then grouting the cavity from finish floor down to top of foundation. Please clarify."

For the MAG-14 Building, the rigid insulation will extend to the top of the footing as reflected in the structural drawings. The architectural drawings are revised via

Amendment 0005 to reflect the rigid insulation extending to the top of footing.

46 I101 I101

Communications-I101-Drawing I-

101 for all three buildings contains a schedule of CFCI equipment. These schedules call out Flat Panel Display. No specifications for these displays have been found. Please confirm that these are part of the A/V equipment estimate provided for

Option Item No. 8.

Confirmed. Flat panel displays are part of A/V equipment.

47 122413 122413

Architectural-122413-There is a specification section for roller window shades, but they are also mentioned in section120001.0020 for the FF&E. Please confirm that the cost of the roller window shades is to be included in the building construction CLINS and is not part of the FF&E estimate in option 9.

Rollershades are to be included in the construction budget, not

FF&E. Section 12 00 01.00 20 has been updated to remove any reference to rollershades

48 104416 104416

Architectural-104416-There is a specification section for fire extinguishers. For all three buildings, the fire extinguishers are listed in the furniture schedule

(E8). Please confirm that the cost for the fire extinguishers is to be included in the building construction CLINS and is not part of the FF&E estimate in

Option Item No. 9

Per 35% comment 1767624, only cabinets and wall hangers are part of the construction budget. Fire Extinguishers themselves are FF&E

49 126113 126113

Architectural-126113-Sub section

2.6 of specification section 12 61

13 lists Lectern Podium. For

MALS and MAG buildings, lecturers are listed in the furniture schedule (T12). Please confirm that the cost for the lectern podium is to be included in the building construction CLINS and is not part of the FF&E estimate in Option Item No. 9

Lectern podiums are part of the

FF&E and should not be included in building construction or AV package.

50 102239 102239

Architectural-102239-Spec section 10 22 39 calls for folding panel partitions. MALS-14 drawing A-112 shows operable partitions next to gridlines A.6 and B. Please provide detail drawing of operable partitions in classroom 243.

Revised drawings provided with Amendment 0005.

MAG-14

A:

FX501

MAG-14

A: FX501

Fire Protection/ Life Safety-

MAG-14 A: FX501-Detail A4 on

FX501 for MAG-14 does not show a waveguide, is a wave guide required for secure wall penetrations?

A waveguide is not required for secure wall penetrations.

MAG-

14A: P-

MAG-14A:

P-501

It is noted that this site is Seismic

Design Category B, so low seismic. Please verify detail B2 on P-501 is not applicable. There are no seismic specs for plumbing and mechanical and it is also noted in 21 13 13 that seismic restraint is not required for Fire

Protection. Please verify seismic is not applicable for this project.

Concur. This detail is not required for this project and removed via Amendment 0005 accordingly.

MAG-

14A: P-

MAG-14A:

P-601

BFP-2 is missing on P-601, is this the Fire Protection Backflow?

It is not a Fire Protection BFP.

It is for CW makeup for HVAC equipment and added via

Amendment 0005 to sheet P-

601 as required.

MALS-

14 I-114, S-125

MALS-14

I-114, S-

Equipment-MALS-14 I-114, S-

125-Drawing I-114 indicates 5-ton linear crane. Drawing S-125 does not show monorail system to support this linear crane.

Furthermore, no specifications are given for this linear crane system.

Please confirm linear cranes are on this project.

There is no linear crane in the

MALS-14 building. Please refer to the architectural drawings Sheets A-104 & A-

105 for the crane layouts. There is a total of (4) 5-ton Cranes,

(1) in the bay between column lines A to B, (2) in the bay between column lines C to D, and (1) in the bay between column lines E to F.

"41 22

13.15 -

1.3.1.1

"41 22

13.15 -

1.3.1.1

Equipment-41 22 13.15 - 1.3.1.1

S-134, S-135-Paragraph 1.3.1.1 of

Specification 41 22 13.15 notes that there is one (1) top running crane spanning 50 feet, and four

(4) top running cranes spanning

45 feet for a total of five (5) bridge cranes. Sheets S-134 and

S-135 only show a total of a total of three (3) bridge cranes. Please clarify the total number of bridge cranes on the project."

Please refer to the architectural drawings Sheets A-104 & A-

105 for the crane layouts. There is a total of (4) 5-ton Cranes,

(1) in the bay between column lines A to B, (2) in the bay between column lines C to D, and (1) in the bay between column lines E to F.

41 22

13.15 41 22 13.15

Equipment-41 22 13.15-

Specification 41 22 13.15 has no mention of anti-spark requirements. Please confirm all bridge cranes do not need to meet the requirements of minimum or maximum anti-spark.

PENDING RESPONSE

41 22

13.15 -

1.3.1.2

41 22 13.15

- 1.3.1.2

Equipment-41 22 13.15 - 1.3.1.2-

Paragraph 1.3.1.2 of Specification

41 22 13.15 says to "provide top running single girder electric bridge crane(s), with under running trolley mounted hoist..."

The sentence continues on to say

"...conforming to MHI 27.1, CMAA 70, and CMAA 74 service class, as applicable."

CMAA 70 is for multiple girders, and CMAA 74 is for single girders. Please confirm all bridge cranes are to be single girder.

All bridge cranes are to follow

CMAA 74 for single girders.

MAG-

14A, MP102

MAG-14A,

MP102

No waveguides are shown in

HWS&R pipe, are they required?

Waveguides are only required for HVAC duct penetrations.

Piping and conduit penetrations to be installed per detail C3/M-

505.

MAG-

14A, M-

MAG-14A,

M-506

Please verify ATFP bracing shown on M-506 for MAG-14 is not applicable since this is a seismic design category B project.

ATFP bracing is separate from seismic bracing.

Implementation of standards in

ATFP UFC 4 010 01 is mandatory for all new construction. ATFP Equipment

Bracing Standard 19 (s.3-20) applies.

BLDG

A-101, A-501

BLDG

A-101, A-

Structural-BLDG 3916 A-101, A-

501-For B3916, Sheet A-501 shows Wall Type B extending to roof deck above. Please confirm that all walls denoted as Wall

Type B on Sheet A-101 are to extend to roof deck above."

Revised drawings provided via

Amendment 0005.

BLDG

3916, CU101

BLDG

3916, CU101

Keynote 2 calls for a sanitary sewer packaged pump station of like kind and size with PVC gravity. Please provide details for the pump station and a pipe size for the PVC gravity line.

PENDING RESPONSE

01 31

23.13 20

01 31 23.13

Security-01 31 23.13 20-01 31

23.13 20 - 1.5 identifies direction about Security Classification, specifically CUI and 1.6 breaks down restricted information.

1.6.2 provides a Table of Project

Documentation Types and provides remarks. Submittals and

Submittal Register the remarks are blank but Shop Drawings notes, ""Locations of sensitive areas must be labeled as either

""Controlled Area"" or

""Restricted Area” and may be shown on unclassified documents with the approval from Site

Security Manager."" 1 - Please confirm if Submittals generated by the offeror and subcontractor need to marked CUI? 2 - Please confirm if Shop Drawings, such as the reinforcing shop drawings, need to be marked CUI?

Submittals are not Controlled

Unclassified Information, unless determined by the government following submittal.

MAG

HQ -

CS101

MAG HQ -

CS101

Keynote 7 says to Remove Drive

Aisle from P-239 Scope. Please confirm that P-239 scope will not have conflicts with P-226 pavement connections.

Design is correct as shown.

Propose in accordance with the

RFP.

MAG

HQ -

CS101

MAG HQ -

CS101

Keynote 21 says to remove pavement patch from P-239

Scope. Please confirm that there are no utility conflicts with what is shown on P-226 utility

Design is correct as shown.

Propose in accordance with the

RFP.

connections and with what is shown on P-239 plans.

MAG

HQ -

CS102

MAG HQ -

CS102

Note 6 on CS102 (22 of 714) says

P-239 PLANS WERE

PROVIDED BY THE

GOVERNMENT AND IS

SHOWN FOR PLANNING

COORDINATION PURPOSES.

Please provide the P-239 plans.

Design is correct as shown.

Propose in accordance with the

RFP.

Attachm ent G-

Schedule-CLIN 0001D is Base

Price for Sitework of entire project site outside the facility's 5-foot line. Please confirm that

CLIN 0001D is for the combined sitework for both the MALS-14

Engine Maintenance Shop and the

MAG-14 Regiment al Group HQ and that the pricing for each site is not to be separate.

CLIN 0001D revised to CLIN

0001C. It is the combined sitework for the facilities.

Pricing is not separate for the 2 sites. Revised Attachment G –

Price Schedule Rev2 provided.

07 61

14.00 20

07 61 14.00

Architectural-07 61 14.00 20-07

61 14.00 20 - 1.7 says there shall be a Manufacturer's warranty for materials and workmanship not less than 30 years. It also notes to provide a 2-year contractor installation warranty. Please confirm the 2-year contractor installation warranty shall be provided by the roof installer, who may not be the offeror, due to special installer certifications.”

Propose in accordance with the

RFP.

Attachm ent G-

Schedule-CLIN 0005 for the removal and disposal of contaminated stockpiled soils.

Please confirm that this unit price includes excavation, handling, storage, sampling, analysis, transportation, any necessary treatment and disposal of PFAS impacted soil media at a permitted licensed facility and the replacement with structural backfill or NCDOT #57 crushed stone.

Refer to CLIN 0005 notes for all requirements on Attachment

G - Price Schedule Rev2.

Attachm ent G-

General-Attachment G- Price

Schedule-The Price Schedule section 1.3 A/V and FF&E Bid

Notes (CLIN 9 - 10) "F" states they can be awarded a minimum up-to 6 months prior to contract completion date. However, "G" states we must complete the

FF&E package at least 9 months to Beneficial Occupancy Date. Do to lead times on FF&E and A/V

Package and BVD must be completed at least 9 months prior to BOD. Award may be earlier, but no later than 6 months prior to completion date.

offerors need at least 12 months prior to the completion date to procure the material. Please consider changing the 6-month requirement to 12 months."

MALS-

14, S-

MALS-14,

S-101

Structural-MALS-14, S-101-On sheet S-101, the foundation plan notes the deep foundation system requirements box that calls out a minimum base bid tip elevation of

-8.00 feet (NAVD88). Please confirm that the precast pile design depth will not penetrate the aquafer.

The drawings reflect direction received from the government regarding depths, etc. Provide piles as in accordance with the

RFP.

Attachm ent G-

General-Attachment G- Price

Schedule-The Price Schedule section 1.3 A/V and FF&E Bid

Notes (CLIN 9 - 10) ""f"" states they can be awarded a minimum up-to 6 months prior to contract completion date. However, "g"" states we must complete the

FF&E package at least 9 months to Beneficial Occupancy Date.

There are 3 different buildings associated with this project, assuming Option 1 (CLIN 0002) is awarded although there is only one FF&E and 1 AV Planned

MOD for the entire project.

These buildings may all be completed at different times, some earlier than others. 1 - Will the government consider awarding the FF&E and AV in packages for each building to allow for earlier delivery? 2 -

Will the government base allowed timeline to award the FF&E and

AV based on the Contract

Completion or Beneficial

Occupancy Date for each building?

Propose in accordance with the

RFP.

MALS-

14, S-

MALS-14,

S-203

Equipment-MALS-14, S-203-

Detail A4 on Sheet S-203 does not show a crane rail on top of the bridge crane runway beam.

Please provide the desired crane rail and size.

Final design of the crane runway beam, haunch, runway beam bracing, rail stops, and connections are by the bridge crane manufacturer, however for pricing estimation purposes assume the crane runway beam is a W33x141 with top and bottom C15x33.9 channel caps and the haunches are W14x82.

MALS-

14, S-

MALS-14,

S-203

Equipment-MALS-14, S-203-

Detail A4 on Sheet S-203 says the bridge crane runway beam is to be a "W33 bridge crane rail w/

C15 cap." Please provide the desired weight of both the W33 beam and C channel.

Final design of the crane runway beam, haunch, runway beam bracing, rail stops, and connections are by the bridge crane manufacturer, however for pricing estimation purposes assume the crane runway beam is a W33x141 with top and bottom C15x33.9 channel caps and the haunches are W14x82.

74 CSP CSP

Security-CSP-Please confirm the

CSP only applies to the MAG HQ building and site.

PENDING RESPONSE

12 00 01

.00

12 00 01

.00

General-12 00 01 .00-12 00 01.00

20 - 1.2 notes the Government

FF&E estimate is $3,032,033.08, where the Attachment G - Price

Schedule CLIN 0010 states it is

$1,804,239. Please confirm which value is correct.

Combined totals for FF&E per the conceptual package is

$3,063,441.58, not including the contractors HAR. Spec

Section 12 00 01.00 has been updated to reflect this value.

12 00 01

.00 & 01

30 02.00

12 00 01

.00 & 01

30 02.00 22

Equipment-12 00 01 .00 & 01 30

02.00 22-12 00 01.00 - 1.2 notes the Design and documentation of the FF&E must be funded as

Interior Design Services in the base bid. 01 30 02.00 22 - 1.3 requires the Desing and documentation of the AV System to be funded as the AV Services

Option, this option is not identified on the Price Schedule.

1 - Please confirm if the FF&E

Interior Design Services MALS-

14 Engine Maintenance Shop should be with CLIN 0001A, MAG-14 Regimental Group HQ with CLIN 0001B. 2 - Please confirm if the FF&E Interior

Design Services BLDG 3916

Aircraft Armament shop is to be included in a Base Bind per 12 00

01.00 -1.2, if so which one, or with the Option CLIN 0002. 3 -

Please confirm where the Design and documentation of the AV

System is to be priced since there is not an AV Services Option."

"1 – FF&E Interior Design

Services for MALS-14 Engine

Maintenance is to be included in CLIN 0001A. FF&E Interior

Design Services for MAG-14

Regimental Group HQ is to be included in CLIN 0001B. 2 –

FF&E Interior Design Services for BLDG 3916 Aircraft

Armament Shop is to be included in CLIN 0002.

01 30

02.00 22

01 30 02.00

General-01 30 02.00 22-01 30

02.00 22 - 1.3 notes the

Government AV budget on the

Bid Schedule/Price Proposal

Form for the AV MOD is

$1,541,947, where the

Attachment G - Price Schedule

CLIN0009 states it is $1,511,012.

Please confirm which value is correct.

Revised Price Schedule

0005 to include updated A/V costs for CLIN 0009 – Option

08.

01 33 29

1.6.14.1.

01 33 29 -

1.6.14.1.1

Sustainability-01 33 29 -

1.6.14.1.1-01 33 29 - 1.6.14.1.1 notes the Project is already registered with Third Party

Certification (TPC) Organization.

Please confirm the offeror is not

Third Party Certification is not required because Controlled

Unclassified Information is included within the project documents.

responsible for any of the TPC costs only to complete with updating the required information to achieve final Certification or validations.

79 01 35 26 01 35 26

General-01 35 26-01 35 26 -

1.7.1.1 notes we are to provide a minimum one SSHO at each project site. Since this project has potentially multiple sites (MALS-

14 Engine Maintenance Shop, MAG-14 Regimental Group HQ, & BLDG 3916 Aircraft

Armament shop) that may be ongoing concurrently, please advise is an SSHO is required at each site.

Propose in accordance with the

RFP.

80 01 45 00 01 45 00

General-01 45 00-01 45 00-1.6.5 provide an experience Matrix for

QC specialists. The matrix identifies 2-1 Qualification and 2-

2 Experience for each specialist, however, the text is confusing.

For instance, for Mechanical it says 2-1. Graduate Mechanical

Engineer with a Professional

Engineer Registration, and 2-2 2-year experience or a person with

5 years of experience supervising mechanical features of work in the field with a construction company. Please confirm the correct interpretation for the requirement is: a Graduate

Mechanical Engineer with a

Professional Engineer

Registration and 2 years of experience OR a person 5 years of experience supervising mechanical features of work in the field with a construction company. Confirm this applies for all QC specialists in the

Matrix"

Confirmed.

81 01 45 00 01 45 00

General-01 45 00-Please confirm the Quality Control Manager can also serve as one of the QC

Specialists as long as they meet the qualification & experience requirements.

Propose in accordance with the

RFP.

82 01 45 00 01 45 00

General-01 45 00-01 45 00-1.6.5 notes the QC Specialists must be directly employed by the Prime

Contractor and cannot be employed by a supplier or subcontractor on the project.

Please confirm the QC specialist does not have to be a employee of the prime but can be from a 3rd

Party as long as they are not an employee of a supplier or subcontractor on the project?

83 B-C-501 B-C-501

Civil-B-C-501-Detail A4/C-501 for heavy duty asphalt pavement shows an 18" thick compacted select material base over an existing soil surface. Please confirm that the 18" thick select material can exist onsite material.

Provide imported select material.

84 A-B-101 A-B-101

Civil-A-B-101-On plan B-101, the geotechnical report summary refers to the final geotechnical engineering report dated February

10, 2023, as prepared by

AECOM. Refer to final geotechnical engineering report for additional information. Please provide the final geotechnical engineering report dated February

10, 2023, as prepared by

AECOM.

PENDING RESPONSE

85 A-B-501 A-B-501

Civil-A-B-501-Detail 7/B-501 calls for surcharge where applicable. Please confirm that there is no surcharge required on this project.

Surcharging is not required for this project.

86 A-B-501 A-B-501

Civil-A-B-501-Detail 8/B-501 calls for removal and replacement of existing fill beneath footing.

Please confirm that this item is to be included in CLIN 0004 Option

3-unit price for undercut and replacement with imported structural fill or with NCDOT #57 crushed stone. If this scope of work is not to be included in the unit price, please provide the depth and width of undercut and replacement that is to be included in the base bid.

Removal and replacement of geotechnically unsuitable subgrade soils will be paid for using CLIN 0004.

MAG-

14, A-

13 47 00

MAG-14,

A-109

13 47 00

Architectural-MAG-14, A-109 13

47 00-Specification 13 47 00

RADIANT BARRIERS,

Paragraph 2.1 references shielding to be tested to IEEE

299. We believe the design as shown on Sheet A-109 will not pass the IEEE 299 testing. In order to meet IEEE 299 testing requirements, the secure space must be a 6-sided enclosed area.

The plans show contradicting details/sections showing the foil only lapping 8” onto the floor and ceiling. Please clarify."

M703

M101 &

M703

Mechanical-M101 & M703-3916.

M101 and M703. RTU2 and

RTU5 are shown with wall mounted room sensors. They are

VAV RTUs and should not have room sensors other than the room sensors that are wired to vav boxes that are fed by the RTUs?

See response to PPI #7.

M101 &

M603

M101 &

M603

Mechanical-M101 & M603-3916.

M101 and M603. M101/Plan

Note 4 and M603 (louver schedule) call for the wall louver to be factory provided with a motorized damper. However, M101 shows the dampers in field installed duct plenum inside the building. Please clarify which location is applicable to prevent duplication.

See response to PPI #8.

A2/M70

A2/M701

Mechanical-A2/M701-3916.

A2/M701 shows a Cisco Catalyst

3560-CX switch connecting the building to the offsite EMCS. We believe that switch is obsolete and has been superseded by the following terminology: "Cisco switch C9200CX-8P-2X2G, Cisco Network Advantage, Software License, 3-year term, and Cisco Fiber SFP Transceiver, GLC-LX-SM-RGD". This also applies to MAG HQ/M701 and

MALS 14B/M701.

See response to PPI #9.

A1/M70

A1/M702

Mechanical-A1/M702-3916.

A1/M702. Notes for the emergency gas shutdown switch say, "locate in a mechanical building near the exit door".

There are many building exit doors, and no building area is called "mechanical building".

Please add a Plan Note indicating the desired location.

See response to PPI #10.

M703 &

M704

M703 &

M704

Mechanical-M703 & M704-3916.

M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a similar demarcation or note to provide the same information about the control devices in the

Outside Air stream upstream of the mix with Return Air.

See response to PPI #11.

M703 &

M704

M703 &

M704

Mechanical-M703 & M704-3916.

M703 and M704. The return air and supply air both have lines delineating what components are field installed and what are factory installed. Please add a

See response to PPI #11.

similar demarcation or note to provide the same information about the control devices in the

Outside Air stream upstream of the mix with Return Air.

94 M703 M703

Mechanical-M703-3916. M703.

Is the SA duct static pressure transmitter provided loose with the RTU for field mounting and wiring?

See response to PPI #12.

95 M101 M101

Mechanical-M101-3916. M101.

Please indicate the desired location of the duct static pressure transmitters for RTU2 and RTU5.

Likewise for SA duct DP transmitters for all multizone vav

AHUs in all buildings.

See response to PPI #13.

96 M603 M603

Mechanical-M603-3916. M603.

Should BACnet MS/TP communication capability be added to schedule notes for the ductless split system? Alternately maybe copy-paste-site adapt the points list/sequence/drawing for ductless splits that are in

A1/M704 in the MAG HQ drawing set? That MAG HQ points list mentions BACnet interface.

See response to PPI #14.

97 M702 M702

Mechanical-M702-MAG HQ.

M702. Sequence for AHU1 requires fan shut down on operation of a high SA duct static pressure safety switch, however, no switch is shown on the control drawing or points list. The same situation occurs in MALS 14 on

M702.

See response to PPI #15.

M603 and

M703

M603 and

M703

Mechanical-M603 and M703-

MAG HQ. M603 and M703.

This is in regard to AHU-2 which has a dx split system to provide emergency cooling or heating if the CHW or HW system is not functioning. The intent is clear, but additional requirements for the dx system are needed. At anything less than full load it is impossible to maintain a stable air discharge temperature on a dx vav

AHU unless at least one compressor is variable speed.

Cycling a constant speed compressor on/off results in swings in discharge air temperature the timing and size of which is load dependent and uncontrollable. Although it is not specifically stated, the two separate sets of equally sized

See response to PPI #16.

refrigerant suction and liquid lines indicate a vertically split refrigerant coil, i.e. the compressors do not share suction or discharge and are probably the same capacity. We recommend the following note be added to the

AHU schedule and be applied to

AHU-2: “The refrigerant coil shall be vertically split with each portion of the coil carrying half the load at system full load. The portion of the split coil that is second in the air stream in the direction of air flow is called

Circuit #2. The first in the airstream is Circuit #1. Each portion of the coil shall be served exclusively by one compressor, i.e. the compressors do not share suction or discharge. The compressor serving Circuit #2 must be variable speed from 5% to 100% of its capacity and must be capable of being modulated over that entire range by the building digital control system

(BAS) via a hardwired analog signal (not via open protocol interface). At AHU loads less than 50% of design, Circuit #2 will be modulated by the BAS to maintain supply air temperature set point. At loads greater than

50%, Circuit #1 will be turned on by the BAS at 100% and Circuit

#2 will be modulated by the BAS to maintain supply air temperature set point. An electronic "smart" expansion valve shall be provided for Circuit

#2 and if necessary, the expansion valve shall communicate with the condensing unit (HP-1) to insure safe refrigerant pressures and oil return."

MP401

A2/M70

MP401 &

A2/M708

Mechanical-MP401 & A2/M708-

MAG HQ. MP401 & A2/M708.

A2/M708 requires BAS to monitor gas flow rate, presumably via a signal produced by the gas meter. Plan Note 15/MP401 requires the utility to provide the gas meter. How do we know the meter provided by the utility will have an output compatible with the building BAS? This applies to all buildings with gas meters.

See response to PPI #17.

P102, A1/M70

8, CU101

P102, A1/M708, CU101

Mechanical-P102, A1/M708, CU101-MAG HQ. P102, CU101, and A1/M708. Problem #1: Plan

Note 3/P102 shows domestic water entering at the northwest corner of Mechanical Room 135 but no meter is shown; the note refers to civil drawings for further information. However, Keynote

4/CU101 says "All water meters

... are located inside building.

See plumbing plans." Thus, there is a conflict between civil and plumbing drawings, and neither is presently responsible for the meter. Problem #2: A1/M708 requires BAS to monitor water flow rate, presumably via a signal produced by the water meter.

How do we know the meter will have an output compatible with the building BAS? Who is responsible for providing the water meter in all three buildings?

Sheet P-501, Detail C1 shows the water meter. It is noted to have remote ready capability to the DDC and read in US gallons or liters. All three buildings have this covered on the Backflow Preventer detail.

101 M707 M707

Mechanical-M707-MAG HQ.

M707. The control drawing shows two flow meters. They both measure the same value, but in different locations. Could one be deleted? Same comment applies to MALS 14B/M706.

See response to PPI #19.

102 M707 M707

Mechanical-M707-MAG HQ.

M707. B-1 return water temperature and B-2 return water temperature are both in the points list, but neither is on the control…