1. CONTRACT ID CODE PAGE OF PAGES
J 1 19
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0003 11/16/2022
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSYSCOM
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-22-R-2811
9B. DATED (SEE ITEM 11)
10/17/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-22-R-2811, DESIGN-BID-BUILD, BUILDING P-1066, CH-53K GEARBOX & TEST FACILITY, MARINE CORPS
AIR STATION, CHERRY POINT, NORTH CAROLINA
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil
N40085-22-R-2811
SF 30 BLOCK 14 CONTINUATION PAGE
P-1066 CH-35K Gearbox Facility - ECI
The following have been added by full text:
AMENDMENT 0003
This amendment hereby incorporates the following:
REVISIONS to RFP
1. Statement of Work for ECI: Delete section 1.2.2 Anticipated Award Period.
2. Statement of Work for ECI: Section 1.4.5 Preconstruction Onboard Review Delete design dates.
3. MACC General Requirements: page 3, Period of Performance for Preconstruction Services, delete the paragraph and add the following:
Period of Performance for Preconstruction Services: The Government anticipates that the award of preconstruction services will be no later than 6 January 2023. Preconstruction services will be performed through the design phase and continue until award of all construction options. Currently, the planned pre-final design submittal is 31 March 2023 and the final design submittal is 16 May 2023 with an anticipated award of the construction option no later than 10 NOV 2023.
4. MACC General Requirements: page 3, Time for Completion, delete the paragraph and add the following:
Time for Completion: ECI Contract completion date is 300 calendar days. The days are calculated from date of task order award, which includes the initial 15 days allowed for distribution of the task order award, submission and approval of insurance, bonding and other requirements set forth in the task order/MACC. This ECI contract completion is from task order award until Construction contract award, and does not include the Construction Option time. Task order award is considered notice to proceed.
ATTACHMENTS
1. Amendment 0003 - Attachment 6 - REV - P1066_Statement of Work for ECI Contractor
Question
Reference Question Government Response
Page Section Paragraph
3 Attachment 3a -
P-1066 H-53K
Gearbox
Facility-Geotech
Report
1.4 Purpose
and Scope of
Services
Can the Government confirm that the following statement will be addressed as a possible design change if found "The scope of services did not include an environmental assessment for determining the presence or absence of wetlands or hazardous or toxic material in the soil, bedrock, surface water, groundwater or air, on or below or around this site."?
Based on the information we have we do not anticipate hazardous, toxic material or wetlands, however, MIDLANT needs to confrim that if these are found it would constitue a design change.
Sheet
ES
Construction
Note 1 & 7
Can the Government provide electrical load and quantity of the Test Stand Equipment associated with each transformer and ductbank? It
This information will not be available until after the test stand procurement is completed.
will be virtually impossible to guess what is needed to price this. It will be virtually impossible to guess what is needed to price this.
Sheet
ES
Construction
Note 1 & 7
Can the Government provide the electrical specifications for each test stand and how many they are requiring for each of the three services designated?
This information will not be available until after the test stand procurement is completed.
15, 16, UFC 4-022-03
Security Fences and Gates (01
October 2013), A
Level 1 security fence will be provided on the eastern and southern sides of the site to connect to the existing base perimeter fence.", & 32 31
13 - Chain Link
Fences and Gates
Division 32C
- Fence and
Gates (spec
32 13 31)
Can the Government provide the details and/or requirements for a Level 1 fence?
Level One fencing is standard industrial chainlink fencing.
25 P1066 MACC
General
Requirements
HVAC
Control
System
Can the Government confirm
DDC supervisory device to be
Johnson Controls model SNE for compatibility with current
UESC upgrade project taking place? SNE will tie to Metasys
ADX server version 11.0 to maintain FIPS-140-2 compliance, graphics to be
MUI for consistency with existing conditions.
PENDING RESPONSE
11 P1066 MACC
General
Requirements
Factor 1 –
Management
Approach &
Schedule
Can the Government confirm that the CMP schedule required within Factor 1 -
Management Approach &
Schedule will only show the design submission as milestones? The RFP states
"Provide a detailed construction schedule that illustrates your ability to achieve or improve on the requirements of the RFP while keeping within the RFP’s requirements." and therefore does not call out the need for the design (Pre-Final and
Final Design only) to be provided in the schedule.
The schedule is for construction
(post-award), not design.
General Due to the unusually high market volatility, we request the Government provide an
Economic Price Adjustment
PENDING RESPONSE
(EPA) Clause in the Contract as an appropriate tool to equitably balance the risk of inflation between the
Government and contractor.
As communicated by the DoD
Principal Director of Defense
Pricing and Contracting
“Guidance on Inflation and
Economic Price Adjustments” memo dated 2022.05.25, an
EPA clause would enable the contractor to provide the Firm
Fixed Price (FFP) without having to develop pricing based on potential worst-case projections to cover the unstable market conditions and the potential added risk to the success of the project. The
EPA clause should consider the extended period of performance beyond 1 year due to the design-build delivery where design effort and Government review are required prior to procurement of building materials and equipment. Reference FAR
Clause 16.203-4(d) Fixed
Price Contracts with EPA, which provides for adjustments based on cost indexes of labor and material.
Adding the appropriate EPA clause will benefit the successful outcome of the project. Please confirm the
Government will provide an
EPA clause to this project.
Statement of
Work; 1.2.2
Anticipated Award
Period
The RFP states: “The
Government anticipates award of
Preconstruction Services in Sept
2021. Potential award of the
Construction Services (Option) is targeted for August 2022”
As these dates have passed, please provide new dates for the
Offerors to use in the proposal schedule and proposal.
SOW dates are incorrect. See MACC
General Redquirements for correct dates.
17 3 of 26 Time for
Completion
The RFP states: "Contract completion date is 1,063 calendar days." Please clarify if the 1,063 days is inclusive of preconstruction and construction phases.
Yes, it is inclusive.
12 of
(ii) Basis of
Evaluation
The basis of evaluation for Factor
1 Management Approach &
Schedule doesn't provide a higher ranking for completing the project
See Revised General Requirements with
Amendment 0003.
earlier than the allotted 1,063 day contract duration. Please confirm that a higher rating will not be given to the Offeror’s if their proposed schedule is shorter than the 1,063 RFP duration.
11 of
Factor 1 –
Management
Approach &
Schedule
(i) Solicitation
Submittal
Requirements
Factor 1 Management Approach
& Schedule requires a critical path schedule and summary level schedule. Please clarify if a full project schedule is being requested for the CPM source file.
Full construction schedule is required.
12 of
(ii) Basis of
Evaluation
The basis of evaluation for Factor
1 Management Approach &
Schedule states "Offerors who address risks in resource management through the proposed use of key personnel with demonstrated experience on relevant projects contracted with the United States Government may be rated higher."; however, the RFP does not provide any requirements for key personnel to be discussed within the narrative.
Please confirm the aforementioned basis of evaluation does not apply and will be removed from the RFP.
See Revised General Requirements with
Amendment 0003.
13 of
Price
Page 13 of 26 lists "Copy of
Representation and Certifications and proof of registration in
System for Award Management
(SAM)" as an item for submittal within the Price Proposal. Please clarify if the Governments is requesting for Offerors to provide the downloaded FAR & DFARS
Report from beta.SAM.
Yes
ES101 Electrical Site
Plan
Construction
Notes 1 & 7
Construction Notes 1 and 7 indicate that the three transformers and associated primary feeders are to be sized in the next submittal. a) Please clarify if this submittal will be part of this project or bid at a later date? b) If it is to be included in this project when can we expect to receive it?
This information will not be available until after the test stand procurement is completed.
4 Statement of
Work
1.3.3.2.2 The SOW requires submission
of an FTP at both the pre-final and final (IFC) drawing production points. Please confirm that this is the intent.
FTP is required at Pre-final and Final
(revised from pre-final)
3 Statement of
Work
1.2.2 Paragraph 1.2.2 says that the
Government anticipates the award of Preconstruction services in September of 2021, with award of construction anticipated in August 2022.
The MACC General
Requirements indicate an
See Amendment 003 for updates to dates.
anticipated date of award of
Preconstruction services NLT
30 December 2022. Please confirm the 30 December
2022 date is the most current.
9 Statement of
Work
1.4.5 Paragraph 1.4.5 indicates that
100% drawings were planned for submittal in Sept of 2022, with Final Design drawings planned for October of 2022.
The MACC General
Requirements indicate the Pre-final drawings submittal is due on 07 March 2023 and the
Final Design is due 20 April
2023. Please confirm the dates outlined in the MACC
General Requirements are the most recent.
See Amendment 003 for updates to dates.
3 MACC General
Requirements
The paragraph containing the
Period of Performance for
Preconstruction Services says that the Final Design package will be issued on 20 April
2023. The SOW requires that the contractor must provide their FTP 14 days later, which would be around May 4th
2023. The MACC General
Requirements says the construction option is anticipated for award NLT 10
November 2023. Is it possible that the construction option will be awarded sooner, or is the date of the award of the construction option contingent on other factors, such as project funding?
Contingent upon funding and acceptable pricing.
3 MACC General
Requirements
Please confirm that preconstruction services may begin on 30 December 2022 and continue until the construction option is awarded, which is currently anticipated as 10 November
2023 which is a duration of
315 days.
Pre-Con services will run from
Contract Award to Award of
Construction Option.
11 Statement of
Work
1.4.10 Paragraph 1.4.10 Cost
Estimates requires that each estimate is to include projected escalation of costs as may occur due to the schedule for construction award. Please confirm that the
Initial Target Price is intended to be priced without escalation, and that as noted in the paragraph, it is the
Confirmed.
contractor's responsibility to inform the AE and the
Government regarding escalation costs at each production point.
11 Statement of
Work
1.4.10 Paragraph 1.4.10 Cost
Estimates requires that each estimate is to include projected escalation of costs as may occur due to the schedule for construction award. If it is the
Government's intent that the
ITP be escalated through 10
November 2023 (anticipated construction award date,) please provide a percentage of escalation desired. This will foster fairness in competition, and will diminish the potential for increased costs to the
Government later due to guessing since there is no data available for future events.
PENDING RESPONSE
MACC General
Requirements
The MACC General
Requirements, with the amended words " See CLIN
0002" states that in accordance with FAR clause
52.216-17, the Initial Target
Ceiling Price cannot be exceeded during the negotiation for the construction modification.
This puts the contractor in the position of pricing requirements which are not known, since the design documents are currently in the
50% phase and requirements, systems, and levels of quality have not yet been established.
In addition, it allows the
Government to make decisions and product selections for work which has yet to be designed, and requires the contractor to maintain a fixed price without the possibility of price adjustment for customer initiated design changes.
Please clarify.
Propose to RFP.
MACC General
Requirements
The MACC General
Requirements, with the amended words " See CLIN
0002" states that in accordance with FAR clause
52.216-17, the Initial Target
Propose to RFP.
Ceiling Price cannot be exceeded during the negotiation for the construction modification.
This is in conflict with RFP
Part 1 Final, FAR 52-216-17 in the RFP, which describes the prescribed method for adjusting the contractor's profit up or down for successive targets - the
Prefinal and Final design. If the Final Target is higher than the Initial Target, the contractor's profit is adjusted down. If the Final Target is lower than the Initial Target, the contractor's profit is adjusted up. Please clarify the above noted conflict.
MACC General
Requirements
The MACC General
Requirements, with the amended words " See CLIN
0002" states that in accordance with FAR clause
52.216-17, the Initial Target
Ceiling Price cannot be exceeded during the negotiation for the construction modification.
This is in conflict with The
Statement of Work, Page 4, Paragraph 1.3.3.2, which requires the contractor to provide a report of variances related to cost impacts arising from design decisions, whether it relates to an increase or a decrease in costs.
1.3.3.2 correctly acknowledges that the
Government may make design decisions during
Preconstruction which will have a cost impact on the
Contractor. Please confirm that the contractor will be allowed to price customer initiated design changes, and still be awarded the construction contract even if it exceeds the Initial Target
Price.
PENDING RESPONSE
AE101
AE103
BOD AE101 & AE103 show two 4-ton crane locations, however, AE103 does not call the second crane out. Please confirm there are two 4-ton cranes required in room #125
Two 4-ton cranes are required.
Assembly.
AF601 Interior Design The BOD document and 50% drawings both call for double-tier, "Z" style HDPE lockers, however no dimensions are given in the RFP documents.
Please specify the required dimensions for the HDPE lockers for bidding purposes.
18" wide x 24" deep x 72" high with sloped top.
IF101
A
FF&E Cost
Summary
IF101A General Note C indicates that Fire
Extinguishers are FF&E, however no fire extinguishers are listed on the FF&E Cost
Summary in the BOD document. Please confirm whether or not fire extinguishers are to be included in the construction contract, and if yes please specify size and type requirements.
Fire extinguishers will be included with FF&E and added to the cost summary for the next submittal.
23 BOD The BOD document's
Appendix A Draft DD1391 states that a "deep foundation system is included to support the building superstructure."
but the structural section of the same BOD Document mentioned the utilization of a shallow foundation system. In addition, the Geotech reports are suggesting shallow foundations. Please confirm that shallow foundations should be considered for pricing.
Provide shallow foundations as shown on drawings.
4 Statement of
Work
Please confirm that the list of documents in 1.3.3.1 Basis for
Initial Target Price in the
Statement of Work has been superseded by the list found in the MACC General
Requirements, CLIN 0002
Construction Services, page
15.
No the lists are complimentary.
8 BOD Please confirm all interior partitions will be CMU and that a gypsum board finish is not required.
Walls will be CMU, not gypsum board finish.
8 BOD Please confirm CMU partitions will not be topped with framing and drywall above the ceilings.
Confirmed
9 SOW 1.4.6 Preconstruction services include attendance at "bi-weekly conference call meetings." Please clarify whether the intent is one conference call every two weeks, or twice per week.
Once every two weeks.
AE601 DD (50%) 16
May 2022
Can the Government provide a preliminary hardware schedule for this project?
This has not been developed at this time, to be generated when project design resumes.
AE601 DD (50%) 16
May 2022
Can the Government provide the DFH types for 127A, 129B and 130B?
These are all steel doors/frames, hardware sets are not yet established.
AE601 DD (50%) 16
May 2022
Can the Government confirm the multiple doors that are missing “material” information (including interior, exterior and coiling doors) are to be of steel construction?
Doors 113D & 113E are noted (12) as aluminum; door 121B will be steel; door 123B & 124C will be steel
AE201 DD (50%) 16
May 2022
Can the Government provide additional information for aluminum translucent wall panel system (size, type, R-
Value, etc..)? AE201, key note
23, states that information for aluminum translucent wall panel system is located on
AE704. There is no AE704 in this drawing set.
The basis of design for translucent wall panels is Kingspan Uniquad.
AE704 will be developed when the project design resumes.
ES
Detail B1 Can the Government provide addition information/clarification of what the stabilized gravel detail will be?
Call out for stabilized gravel is shown in error and is not required.
Provide compacted earth backfill in lieu of stabilized gravel.
46 13 BOD 50pct and
PROD
M.
Paragraph "Environmental
Permits" states that the project will require permitting to
NCDEQ and EAD and water/fire sewer extensions. In addition the PROD identifies various permits from, E&SC, Storm water, Traffic, FAA, etc.… Please confirm that
ALL design dependent permits requiring the AE1 to complete documents to the required levels of completion by each agency will be completed and then submitted by the Government "prior to and/or in-time" to allow for the contractors proposed start of construction date.
The DOR and /or Government will provide all design dependent permits.
47 10
P1066 MACC
General
Requirements
Basis of
Award
For scheduling purposes what is the anticipated submittal date of the Prefinal
Site/Civil/Structural Package
See Amendment 0003.
mentioned in the last paragraph of page 10?
48 9 RFP
The RFP notes that in addition to the electronic PIEE submission One original, one
CD-ROM, and one copy of the proposal is requried.
Since there is an electronic
PIEE submission please confirm a CD-ROM is still required.
No CD-ROM required. See
Amendment 0003 with revised
General Requirements.
49 3 RFP
The RFP notes in Period of
Performance for
Preconstruction Servies the
Pre-final design is planned for
7 March 2023 and the Final design submittal is planned for
20 April 2023. This does not offeror much time for the
Contractor to offorer many
VE, Constructability, or other cost schedule concepts to be incorporated in the final design.
Will NAVFAC consider cost savings concepts and extend the design period since they do not anticpate awarding construction option until no later than 10 November 2023?
New submittal dates will be posted by Amendment. The typical review period is 21 calendar days. Extension of schedule will be considered after
Prefinal design.
50 3 Statement of
Work For ECI
1.2.2 & 1.4.5
The Statement of Work for
ECI section 1.2.2 notes the government anticpates awarding Preconstruction services in Sept. 2021 with potential award of the construction services (option) targted for August 2022.
Further section 1.4.5 states the
Prefinal 100% is expected in
September 2022 and FInal
October 2022. Both sets of these do not match the dates provided in the RFP.
Please clarify the correct dates.
SOW dates are incorrect. See
MACC General Redquirements for correct dates. Amendment 0003
51 3 RFP
The RFP notes the Time for complete is 1,063 calendar days from award of the preconstruction option through construction.
NAVFAC notes they anticpate final design in April 2023 which will establish the total firm target price (firm fixed price) for the construction option. However, the RFP
Propose to RFP.
notes the government anticpates awarding the construction option no later than 10 November 2023.
What pre-construction acticites is the contractor expected to perform between
April 2023 and award of the construction option in
November 2023?
What are potential delays that would impact the Government from awarding the construction option right after final design?
52 4 RFP & Statement of Work for ECI 52.216-17
52.216-17 notes for establishing a final firm fixed price the team will use the pre-final construction documents.
The Statement of Work for
ECI document notes the contractor shall provide a final firm fixed price based on the
"Final Design." The
Statement of Work for ECI document section 1.3.3.2.2 notes the Contractor may have to submit package at pre-final and final if revision is necessary. Per the RFP the pre-final and final will be issued only a month apart.
Please confirm how many cost estimates, schedule, construability, etc submissions are required.
See updated dates in Amendment
0003.
53 4 Statement of
Work For ECI 1.3.3.1
1.3.3.1 states the basis for
Intital Target Price is on the
"Final 20% Conceptual
Design Workshop Report
Dated, date TBD" The RFP included drawings and Basis of Design marked Design
Development 50% as well as a
Final Charrette Report.
1 - Please confirm the Intital
Target Price should be based on the 50% Design
Development submittals.
2 - If there are discrepancies between the Design
Develpment 50% submittal and Final Charrette report which takes precedence?
See correction in Amendment 003.
the 50% Design submittal is the most current document and takes precedence.
54 5 Statement of
Work For ECI 1.3.4.2
The Statement of Work for
ECI section 1.3.4.2 notes section 01 30.01.00 22
Design, Procurement, and
Installation of FF&E, AV, Yes - the offerer is responsible for the Design and BVD of the FF&E, AV, and Security as part of the CLIN
002 construction option and will
NOT be the responsiblity of
Security. Section 1.3.4.7 states the Design of the FF&E and AV is performed under
Base Bid and included in
CLIN 2.
Please confirm the offeror is responsible for the Design and
BVD of the FF&E, AV, and
Security as part of the CLIN
002 construction option and will not be the responsiblity of
NAVFAC's Designer.
NAVFAC's Designer.
55 5 Statement of
Work for ECI
1.3.4.2 &
1.4.2.3
The Statement of Work for
ECI section 1.3.4.2, 1.4.2.3, and other locations identify
RFP Division 01 specifications. These were not provided with the RFP package only a TOC outline in the 50% Design Development
Basis of Design.
Please provide the Division 01 specifications that apply to this project.
There are no specifications to date, just the TOC.
56 9 Statement of
Work for ECI 1.4.5
The statement of work notes for planning purposes the contractor shall plan on bi-weekly conference call meetings and shall attend a minimum of eight, 2-hour coordination meetings, and three on-board review meetings of one day each during the preconstruction phase.
1 - only the bi-weekly meetings are noted as
"conference calls" Are any of the eight coordination meetings or 3 on-board review meetings in person or virtural?
If in person, where will they be located?
2 - Confirm 3 on-board review meetings is correct if there are only 2 design submissions that the contractor is to price; pre-final and final.
1. no in -person or on site meetings are planned. 2. See Amendment
003, there will be two onboard meetings.
57 10 Statement of
Work For ECI 1.4.8
The statement of work section
1.4.8 notes immediately after the 65% submittal the contractor shall develop a conprehensive project procurment plan. Only Pre-final and Final submissions are identified in the documents.
Is there a 65% submittal, if so when will it be submitted?
There is no 65% submittal. The next scheduled submittal is 100%
Prefinal.
58 11 Statement of
Work For ECI 1.4.10
The statement of work section
1.4.10 states Cost Estimates shall be provided within 14 calendar days of receipt of each design submittal. Other sections including FAR
52.216-17 notes 30 days.
Please confirm Cost Estimates are to be provided within 30 days receipt of each design submittal.
PENDING RESPONSE
59 11 Statement of
Work For ECI 1.4.10
The statement of work section
1.4.10 states Cost Estimates shall be provided for each of the four (4) design milestones listed above. Only 2 design milestones are listed above, prefinal and final.
Please confirm number of cost estimates.
Yes, there are only two milestones.
60 11 Statement of
Work For ECI 1.4.10
Section 1.4.10 and 1.4.10.1 states the estimate format shall match the AE's estimate format. Please confirm what this formatt is or if any special estimate software is required to match the AE's format.
PENDING RESPONSE
61 10 RFP & Statement of Work For ECI
1.4 & 1.4.6, 1.4.9.2
Page 10 of the RFP notes, Upon complete of the Pre-
Final Site/Civil/Structural design by the Government's
AE, the gover will provide the
Pre-Final Site/Civil/Structural design package to the contractor and the government will request the contractor to provide a firm fixed price. There is not a note about a Pre-Final
Building Envelope/MEP design. Section 1.4 & 1.4.6 of the Statement of Work notes the Contractor is to provide recommendation for the use of fast tracking or multiple construction document packages.
1 - Please confirm if there are multiple Pre-final Fast
Tracked or Critical Path
Design Submittals, ie. one for
Site/Civil/Structural Design and one for the building envelopment and MEP?
2 - Since this project is already beyond 50% design, please confirm the government will not entertain fast tracked construction document package that will allow the contractor to be awarded portions of the construction option early such as Site/Civil/Structural or long lead materials?
62 8 RFP
The RFP notes that PPIs are due 14 days prior to proposal due date and should use the
PPI form Attachement C.
1 - Please considered extending this to 10 days prior to the proposal due date to give offerors more time.
2 - Attachment C was not provide in the RFP. Please confirm it is Attachment D.
PPI deadline remains unchanged.
Attachment G
DD3150
Contractor
Visitor
Certification of
Vaccination
The RFP included Attachment
G with is a Contractor
Personnel and Visitor
Certification of Vaccination.
There is a section, Consequences of Failure to
Provide Information that states, the information is voluntary however, failure to provide will be treated as not fully vaccinated with the potentil fo denied access to
DoD Facilities.
In regards to Attachment G, because of the shortage of manpower in Eastern Carolina and the competitive, non federal, markets. Contractor fear subcontractors will not pursue this work or will not execute a subcontract if successful. Therefore, contractor is requesting this attachment be deleted from the
RFP.
PENDING RESPONSE
64 8 Attachment 5, II
Architectural
II.B General
Scope of
Work
Attachment 5, Basis Of
Design Design Criteria, II.B notes brick veneer to 14' high.
AE203 has the brick veneer to
16'. Please clarify desired brick height is to be 16' above
FFE.
Brick veneer is to 16' AFF
65 25
Attachment 5, Bais of Design
VIII Structural
C.
Foundations
Attachment 5, Section C.
Foundations notes that a portion of work area will be equiped with sump pits.
Please provide locations on drawings and details/size of pits.
Items shown indicate the best information to date at the time of the
50% drawing submittal and was based on NAVFAC/Activity input.
Additional equipment clarifications and information is still to be developed
66 8 Attachment 5, II
Architectural
II.B General
Scope of
Work
Would the owner consider removing the LW concrete slab on the roofs and implementing an accoustical deck?
This will required additional evaluation as design progresses.
67 17 Basis of Design
VIII
paragraph B
The project documents are requiring two of the 14' x 14' high speed coiling doors to withstand a wind load of 139 mph. To our knowledge no manufacturers of a spiral high speed overhead door can meet this wind load. Please advise if the wind load is correct for the high speed coiling doors.
139mph is the code-required ultimate design wind speed for this site.
68 AE601
Architectural
On the door schedule AE601, several doors (121B, 123B, 124C, 127A, 129B & 130B) no not have door types listed.
Please provide the door type for each of these openings.
Doors 121B, 123B & 124C to be D7;
door 127A, 129B & 130B to be D1
69 AE601
door schedule comments #4 &
#5 are not listed on the door schedule. Several doors have note #6 listing the highest
STC rating. Please confirm if any of the STC 55 doors can carry a lower rating to save costs.
Negative, ratings are as scheduled for the STC 55 doors, the remaining doors to be sound rated will be coordinated when project design resumes
70 AE601
please provide the hardware sets required per each door opening.
Door hardware sets will be developed when project design resumes
71 GI102
According to drawing GI102 none of the partitions are fire rated. Please confirm that none of the interior partitions are fire rated.
No fire rated separations required
AE201
AE202
AE203
The building elevation drawings (AE201, AE202, AE203) call for aluminum translucent panels and translucent canopy systems.
A specification section for translucent panels was not shown in the RFP BOD documents. Please provide a specification section for translucent panels.
Specifications are not available at this point in design.
AE201
AE202
AE203
The building elevation drawings (AE201, AE202, AE203) do not show an expansion Joint (nor EJ covers) where the building changes height profiles.
Please confirm if expansion joints and expansion joint covers will be required at
There is no building expansion joint these locations.
74 AE303
The wall sections on drawing
AE303 do not show any bituminous dampproofing around the perimeter foundations. Please confirm if dampproofing is required at these locations.
The Air Barrier material will continue to top of footings, dampproofing is called for at the turn-down slab edge at openings
Will any interior structural steel need to be coated per
UFGS 09 97 13.27?
This is not anticipated to be required.
We understand the timing of award, however, as a result of the saturated market the subcontracing community is requesting a two week extension to December 1st, in order to provide the most compeitive pricing and value to the government.
See Amendment 0002.
77 3
P1066 MACC
General
Requirements
Time for
Completion
Can the Government confirm the contract completion duration is 1,063 calendar days from NTP of the Pre-
Construction services award?
PENDING RESPONSE
78 3
Attachment 6 -
P1066_ATT 24-
Statement of
Work for ECI
Contractor
1.2.2
Anticipated
Award Period
Can the Government confirm that this section is incorrect and we should follow the
P1066 MACC General
Requirements, Time for
Completion?
Revised SOW for ECI issued with
Amendment 0003 with corrections.
79 22
Attachment 5
BOD 50 pct
Plumbing
Compressed
Air System
(Tool/Shop/A ir)
The BOD is calling for a single 7.5 hp single oil-flooded rotary screw two stage air compressor. A 7.5 hp compressor is typically rated for around 32 cfm. There is supposed to be a total of 116 air drops throughout the building rated at 40 cfm each.
My AC supplier is concerned that the compressor will be underrated. With this load will a larger compressor be required?
This information will not be finalized until after the test stand procurement is completed. The air compressor may be larger to accommodate all equipment.
Drawi ng P-
Plumbing Fixture
Schedule
P-7 Roll-in
ADA Shower
Plumbing Fixture P-7 Shower-
Fiberglass-Roll-IN Type-ADA references to two different shower applications. The shower Type references "Solid
Surface" material whereas the
Manufacturer's model number/accessories references the shower as being a single piece, molded glass fixture?
Which shower enclosure
Showers will be solid surface.
Plumbing schedule will be modified to reflect solid surface.
material is correct?
Drawi ngs
MP-
101, M-
401, M-602
& EP-
Equipment
Schedule
Hot Water
Unit Heater
Schedule
Drawings MP-101 and M-401 do not show any heating hot water piping routed to UH-1, UH-2 or UH-3. I notice on drawing EP-601 unit heaters
UH-1 & UH-2 are receiving
120V 20a service connections.
Please clarify if these three unit heaters be hot water unit heaters or electric unit heaters or a mix of both?
Unit heaters are hot water units.
Drawings are preliminary and only show piping mains.
Drawi ng M-
General Notes Note # 19
Note # 19 references extending condensate drain lines to nearest roof drain or as indicated. There is no roof drains to pipe the condensate drain to and there is no condensate drain lines shown in the drawings. Where will the condensate drain need to be piped to for disposal?
Condensate drains will be grouped where possible and routed to splash blocks outside of the building.
Drawi ng M-
General Notes Note # 19
There is no mention of the condensate drain piping material within the drawings or the 50% basis of design.
What pipe material shall be used for condensate drains?
Type "L" copper
84 25
Attachment 5
BOD 50 pct
Mechanical
E. Cooling
System
This section does not state what pipe material to use for the chilled water system.
Paragraph D. Heating System states to use type "L" copper for the heating hot water.
What pipe material is to be used for Chilled Water?
Chilled water piping will be one of the following:
-Schedule 40 steel, Type E or S
-Type "L" copper
-Schedule 40 Polypropylene, copolymer
85 3
Attachment 6 -
P1066_ATT 24-
Statement of
Work for ECI
Contractor
1.2.2
Anticipated
Award Period
Can the Government provide the CLIN 0001 Pre-
Construction Contract
Completion Date (CCD)? Will this be at submission of IFC design documents to
NAVFAC?
Pre-construction CCD is scheduled for 15 Jun 2023. This correpsondes with the IFC design delivery.
86 4
Attachment 6 -
P1066_ATT 24-
Statement of
Work for ECI
Contractor
1.3.3.1 Basis
for Initial
Target Price
Can the Government update the 1.3.3.1 Basis for Initial
Target Pricing documents?
The documents listed are outdated and/or have not been provided. The DD Form 1391 for FY 23 MCON Project P-
1066, H-53K Gearbox Facility
1) Final 20% Conceptual
Design Workshop report date
TBD; 2) Preliminary
Geotechnical Report dated
14/05/2021; 3) Final Charrette
SOW for ECI will be corrected by
Amendment. In lieu of the
20%Concept Design Workshop, the
50% Design has been provided in
Attachment 4.
Report, date 31/03/2022
87 7
Attachment 6 -
P1066_ATT 24-
Statement of
Work for ECI
Contractor
1.4.2 Key
Personnel
Can the Government confirm that CLIN 0001 Pre-
Construction Services will not be required to be on site @
MCAS Cherry Point, NC? All work can be performed off site. If meetings are required to be on site, please provide the quantity required and the number of hours?
There are no site visits or on-site review meetings scheduled.
88 11
P1066 MACC
General
Requirements
Non-
Cost/Price
Evaluation
Factors
Factor 1 –
Management
Approach &
Schedule
Can the Government confirm the Pre-Construction and
Construction is to be addressed in Factor 1 -
Management Approach &
Schedule?
Factor 1 applies to the construction phase, not design
AE
Can the Government provide a current copy of the BEAP?
This will help with selections in pricing of materials such as aluminum translucent skylight, prefinished un-insulated metal wall panels
(WP-1),aluminum translucent wall panel system, and aluminum translucent canopy system. Reference Key Note
AE704 and missing detail on
AE202.
PENDING RESPONSE
90 25
50% Design
Development
Submittal
Part X -
“Mechanical”
, Section I –
HVAC
Controls
System
Can the Government provide a
Control Points List and
Sequence of Operations to accurately price/budget the
BACnet DDC scope? The
Basis of Design states to provide “A New BACnet direct digital control (DDC) system will be provided for the building and configured to provide remote monitoring to the existing base-wide Energy
Monitoring Control System
(EMCS)”. However, there’s no control points list or sequence of operations included in the Drawings nor
Basis of Design
(End of Summary Changes)