This solicitation seeks proposals for an indefinite delivery/indefinite quantity multiple award construction contract to provide general construction services in the Hampton Roads Area of Responsibility. The contract will have a one-year base period and four one-year options, supporting sustainment, maintenance, and minor construction programs through task orders for facilities including administrative buildings, industrial structures, warehouses, hangars, maintenance buildings, communications installations, schools, personnel support buildings, recreational facilities, food service structures, lodging, medical buildings, and training areas. Task orders may include demolition, repair, replacement, modification, new construction, and renovation of buildings and infrastructure. Construction is expected to encompass a wide range of design-build and design-bid-build projects across multiple military installations in the region. Offerors must demonstrate experience with comparable projects valued at over $2 million and managing concurrent task orders. Proposals are due by June 15, 2022 through the Procurement Integrated Enterprise Environment system with hard copies to follow within five calendar days.

View the file

Other files for this federal contract opportunity

Other files attached to 8A MACC, DB/DBB General Construction - HR AOR, newest first.
File Type Posted
Amendment 0014.pdf PDF
Amendment 0013.pdf PDF
22R2627 0012 Factor 1.pdf PDF
22R2627 0011 PPI Responses.pdf PDF
22R2627 0010.pdf PDF
1576521_SP-254_Supplementary Instructions to Offerors.pdf PDF
157541_SP-254_As-Builts.pdf PDF
22R2627 0009 Addendum B.pdf PDF
22R2627 0007 Proposal Due Date.pdf PDF
22R2627 0006 Site Visit Log.pdf PDF
22R2627 0005 Proposal Due Date.pdf PDF
22R2627 0004 Proposal Due Date.pdf PDF
22R2627 0003 Site Visit.pdf PDF
22R2627 0002 Site Visit Cancel.pdf PDF
22R2627 0001 Site Visit.pdf PDF
ODP Badge Access Request.xls XLS spreadsheet
SECNAV 5512.pdf PDF
1576521_SP-254_DWGS_1of2.pdf PDF
1576521_SP-254_DWGS_2of2.pdf PDF
1576521_SP-254_SPECS.pdf PDF
1576521_SP-254_SUPPLEMENTARY INSTRUCTIONS TO OFFERORS.pdf PDF
1576521_SP-254_Completed Environmental Checklist.pdf PDF
Attachment D PIEE Vendor Access Instructions.pdf PDF
N4008522R2627 RFP.pdf PDF
Attachment C - PPI Inquiry Log.doc DOC document
Attachment B Past Performance Questionnaire (PPQ).pdf PDF
Attachment A - Construction and Design Experience Project Data Sheet 10-12.docx DOCX document
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide PPIs responses. See Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 92

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008522R2627

X 9B. DATED (SEE ITEM 11)

02-May-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jun-2022

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008522R2627

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0008

The purpose of this Amendment is to provide the following:

1. Provides PPI responses.

2. Issues 1576521_SP-254_Supplementary Instructions to Offerors.

3. Revises General Requirements, CLIN 0001-Base Price Price shall include the design, interior design and construction for the Building SP-254 Exterior Repairs & Roof Renovation, complete and in accordance with the Statement of Work.

4. Revises the Wage Determination VA20220160 5/20/2022.

5. Extend the proposal due date from 30 June 2022 to 7 July 2022.

Contract or PPI#

Section of RFP or Page Number

Paragraph Reference

Drawing Number Question RESPONSE

22 Pg. 7 -8 of 59 Pg 16 of 59

3(a)(1)

5.2.1

Would the Government please confirm the following shall be provided within the Price Proposal despite the Solicitation stating “nonprice/technical information included in the price proposal will not be considered” SF1442 (3(a)(i) Bid Bond (3(a)(iii)

VETS 4212

(3(a)(vi) Signed Bank Reference (3(a)(1) Latest 3 FY of financial statements (3(a)(2) Description of Facilities/Equipme nt (3(a)(3) List of work presently under contract (3(a)(4)

Confirmed, See Amendment 0005.

23 Pg 7-8 of 59 Would the Government please clarify if Cover

Bid per RFP.

Pages, Table of Contents, Tabs, etc.

are desired as they are not listed in Solicitation as written. If determined to be desired, please clarify if these items should be provided by Factor.

Additionally, please confirm whether Cover Pages, Table of Contents, Tabs, etc.

will be counted against any page limitations.

24 Pg 7 of 59 3(a) Please confirm if Price Proposal shall be submitted as a completely separate attachment/physica l binder than that from Factors 1-4.

Please confirm how Offeror shall name/title this separate attachment.

See Amendment

25 Pg 7 of 59 3(a) Please confirm if the Government decides to have the Price Proposal submitted as an entirely separate attachment/physica l binder, is the Government labeling these as Volume I – Price Factor and Volume II – Non- Price/Technical Information

Confirmed, See Amendment 0005.

26 Pg 7 of 59 3(a) Should the Government decide to label this proposal by Price Volume and Non- Price/Technical Information Volume, please clarify if Offeror should include Cover Pages, Table of Contents, Tabs, etc. in each Volume and if these items are excluded from any page limitations

27 Pg 11 of 59 Factor 1- 2-Design

Please confirm there is no page limitation for the required Letter of Commitment and explanation of the meaningful involvement between the Offeror and DoR.

Confirmed.

28 Pg 12 of 59 Factor 2-Safety 3(a)

Please confirm only the Safety Narrative portion is limited to 2 pages and not the entirety of Factor 2 – Safety which includes the requirement for the DART and TCR rates of the Offeror.

Should the Gov’t decide that the 2 page limitation extends to the entirety of Factor 2

– Safety, would the Gov’t please consider extending the page limit so that Offerors, especially those submitting as a Joint Venture, have space to provide all required data or consider providing a “Safety Data Sheet” to Offerors.

Confirmed, Safety narrative limited to two

(2) single sided pages or one (1) double sided page.

29 Pg 10 of 59 (a)(1) Please confirm that if the Offeror is submitting as a Mentor Protégé Joint Venture, they are to submit their original Joint Venture agreement and SBA Approval Letter of Mentor

Confirmed.

Protégé Agreement in Factor 1 Construction Experience.

Additionally, please clarify that these documents do not count against any page limitations

30 Pg 8 of 59 4 Please confirm what information is to be submitted in order to satisfy the requirement of “other Offeror’s work presently under contract” Should this be provided as a list?

If so, please confirm exactly what information shall be provided in that list (ie, project titles, locations, original contract value, contract value remaining, etc.)

The Offeror should include enough details in their narrative for the Government to understand the type and magnitude of existing work.

31 Pg. 7 -8 of 59 3(a)(1)

Please confirm if there is a page limitation for the required Financial Statements, Bank reference, description of offeror’s facilities, work on contract, VETS4212, etc.

No limit.

32 Pg. 8 of 59 2 Please clarify how Offeror is to satisfy requirement of “discuss the financial responsibility among the companies” if the Offeror is submitting as a Joint Venture.

Should this requirement be satisfied by a narrative? If so, please confirm if

This information can be a short narrative no more than one page in the price proposal.

there are page limitations associated.

33 Pg. 8 of 59 3 Please clarify how Offeror is to satisfy requirement of “description of Offeror’s facilities and equipment”.

Should this requirement be satisfied by a narrative? If so, please confirm if there are page limitations associated.

Confirmed.

34 Pg. 8 of 59 (2)(b) Please confirm no drawings are required as a part of this submission.

Confirmed.

35 Pg. 8 of 59 (2)(b) Please clarify if there are any requirements regarding page margins.

Normal, 1” page margins.

36 Pg 11 of 59 (ii) Would the evaluators rate an Offeror’s Factor 1 Experience submission more favorably If the Offeror submits past performance projects that exceed $2M (beyond the requirement of 1 project being at least $2M)

No. Bid per RFP, Factor 1, ii) Basis of evaluation for more favorable considerations

37 Pg 11 of 59 (ii) Would the evaluators rate an Offeror’s Factor 1 Experience submission more favorably If the Offeror submits past performance projects that are all Design Build projects regardless of whether they were design build projects where the Offeror and DoR worked together.

No. Bid per RFP, Factor 1, ii) Basis of evaluation for more favorable considerations

38 Pg 11 of 59 (ii) Please confirm whether an Offeror would receive a more favorable rating if it submits all past performance projects that are equal to or greater than $2M (provided all other experience factors are also met within these projects ie.

New construction, Reno, etc.) than an Offeror who only submits the 1 required past performance project equal to or greater than $2M and the rest of that Offeror’s past performance project values meet the minimum requirement of being at least $500k (provided all other experience factors are also met within these projects ie. New construction, Reno, etc.)

No. Bid per RFP, Factor 1, ii) Basis of evaluation for more favorable considerations

39 Pg 11 of 59 (ii) Please confirm whether an Offeror would receive a more favorable rating if it submits all past performance projects that are Design Build projects, regardless of whether the projects were completed with the proposed DoR/Offeror Team (provided all other experience factors are also met within these projects ie.

New construction, No. Bid per RFP, Factor 1, ii) Basis of evaluation for more favorable considerations

Reno, etc.) than an Offeror who only submits the 1 required Design- Build past performance project and the rest of the Offeror’s past performance projects were Design-Bid-Build (provided all other experience factors are also met within these projects ie.

New construction, Reno, etc.)

40 Pg. 8 of 59 3 Please clarify if the Offeror is proposing as a Joint Venture, are they to submit a “description of Offeror’s facilities” for each Joint Venture member and if so, how should they complete this requirement? Is this requirement satisfied by way of a narrative?

Confirmed. A short narrative describing the Offeror’s facilities is acceptable.

41 Pg. 8 of 59 2 Please clarify what documentation the Government is looking for when requiring the Offeror to “submit evidence of availability of working/operating capital” Additionally, if the Offeror is proposing as a Joint Venture, should whatever documentation the Government decides to require be submitting for each Joint Venture Member or for that of the Joint Venture itself?

This can be in the form of a bank letter or reference, or other narrative.

Information should be presented for the proposing

JV.

42 Pg. 8 of 59 4 Would the Government please confirm what information is required to satisfy the requirement of “other Offeror’s work presently under contract” and clarify if the Offeror is a Joint Venture, should this information be provided by each JV Member?

The Offeror should include enough details in their narrative for the Government to understand the type and magnitude of existing work.

43 01 00 00 CLIN 001 Section 01 00 00 General Requirements, Paragraph CLIN 0001 states, "Price shall include the design, interior design (FF&E) and construction for the Building SP-254 Exterior Repairs & Roof Renovation, complete and in accordance with the Statement of Work.". The Price Proposal Form for the Seed Project does not include any mention of design or FF&E. Also, the Specifications provided do not include a “Design After Award” section and the Drawings are labeled “Final”. Please clarify the design scope for the seed project.”

See Amendment.

44 Page 7 of

RFP

To ensure competitive pricing will you allow the price to be submitted in the electronic copy and

See Amendment 0005.

not the hard copies.

Mailing hard copies in advance could hinder us the ability to receive competitive pricing up until the due date and time.

45 01 14 00 1.2 Are there any scheduled activities for this facility that may impede contractors progress

No scheduled activities have been identified. Bid per RFP.

46 01 30 00 1.4 Every month the contractor is to provide two separate CDs with photos. Is this still a valid requirement, or can one disc be submitted with all photos for the closeouts

47 01 31 23 1.4.3 The contractor is to provide a computer with CAC ready for “government use only?”

Refer to Addendum B.

48 Page 8 of 59 (2)(b)

The RFP states “Minimum 11 point font, Times New Roman”. May we use smaller, legible, font for graphics and tables (e.g. the organizational chart within the management approach)?

0005.

49 Page 8 of 59

& SF 1442

(2)(b) The SF 1442 indicates that we shall submit and original and 2 copies of the proposal. Page 8 of 59 states: “None-price binder: The offeror shall submit one (1) electronic copy marked “Original” via PIEE, one hard

See copy marked “copy” in a separate three-ring binder (1.5 inch maximum), and one electronic copy on CD.

Please clarify the number of original and hard copies we shall submit for the price proposal and technical proposal.

OR shall the proposal solely be submitted via

PIEE?

50 Page 9 of 59 (a) May we provide an introduction sheet in the experience section to address meaningful involvement? If so, would this be excluded from the page limitations?

This information should be included in Factor 3, “The offeror shall provide the roles, responsibilitie s, and contractual relationships between the various firms that will perform with under this contract”

51 Page 11 of 59 (2) If a project experience example we submit achieved LEED certification, we are required to submit a copy of the certification.

Will this be excluded from the page limitations?

Yes.

52 Page 15 of 59 (i) Please confirm that the DOR may obtain PPQs from the prime contractor on the projects.

Confirmed.

53 Page 12 of 59 (i) The RFP instructs that if the Offeror is a partnership of a JV, the Offeror

Confirmed.

Please refer to the RFP for requirements shall submit separate DART and TCR rates for the specify 5 CY for each contractor who is part of the partnership or JV.

If the Offeror utilizes project experience from sister companies, please clarify that the Offeror is not required to submit separate DART/TRC rates for each of the sister companies.

for affiliate experience.

54 1576521_SP-

254_SPECS

1.4.2 What liquidated

damages will apply to the seed project?

Bid per RFP, Page 58/59, Liquidated Damages.

55 Pg 15 of 59 (i) Factor 4 Past Performance requires that the Designer must supply a CPARS if a completed CPARS is available for the submitted project. If the Designer has submitted a project under Design Experience where they were not the Prime Contractor, but rather the Design Subcontractor for a Prime Contractor and therefore a CPARS has not been provided to the Designer (ie.

CPARS would show “Name/Address of Contractor” as that of the Prime Contractor and NOT Designer information) please clarify if in that scenario should the Designer seek a

PPQ regardless of whether the Prime Contractor has received a CPARS

56 Pg 15 of 59 (i) Given that a Designer, who is submitting a Design Experience Project where the where they acted as the Design Subcontractor and not that of the Prime Contractor of awarded project, may not be aware of the Prime Contractor having received a CPARS, would the Government confirm that a Design Experience project that doesn’t contain a CPARS directly addressed to the Designer, the Designer is to acquire a PPQ.

If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which must provide contract and client information for the respective project(s).

57 Pg 15 of 59 (i) If the proposal contains a project that was completed by the Offeror and the proposed DoR to demonstrate Construction and Design Experience (separate PPIs for both) and the Offeror (Prime of project) has received a CPARS for that project, but the DoR (Design Sub on project) has NOT received a CPARS, is Factor 4 Past Experience to contain the Offeror’s CPARS twice or should the proposal contain the Offeror’s CPARS to satisfy corresponding

If a completed a CPARS is available, it shall be submitted with the proposal for each project included in Factor 1 for Design Experience. If there is not a completed

CPARS

evaluation then the offeror shall submit Past Performance Questionnaire

s. If the Offeror is unable to obtain a

Construction experience and also provide a PPQ to satisfy the requirement of corresponding Design experience?

Additionally, please confirm if in this scenario, the Offeror (Prime of submitted project) should be considered the “Client” and therefore complete boxes 5-8 of PPQ rating the Designer.

completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which must provide contract and client information for the respective project(s).

58 Pg 15 of 59 (i) Please confirm if it is acceptable for an Offeror that was a Prime Contractor on a submitted past performance project to complete a PPQ for their proposed DoR who was the Design Subcontractor on the referenced past performance project. If the Government responds that this is unacceptable, please advise what client the DoR should direct the PPQ to given that the DoR performed the work for the Offeror.

Confirmed.

59 PIEE system This solicitation is currently marked as DRAFT in the PIEE system and does not allow Offers to be submitted. Please adjust the listed in PIEE so that offers may be submitted.

Draft removed.

60 RFP, Section 5 Proposal

Requirements ; and SF 1442

5.2.4, Gen.

Requirements

- Please confirm the delivery address and point of contact for the hard copies. The address presented in 5.2.4 is different from General Requirements and SF 1442, which mention Contracting Core.

Confirmed, See Amendment 0005.

61 RFP, Section

3(b) - Will the Government allow tables, graphics, screenshots, form inserts (PPQ and CPARs), headers, and footers to be less than 11pt Times New Roman font?

See Amendment 0005.

Minimum 10-point font, Times New Roman

62 Attachment A

3(b) - The font set in the Government provided project template is Times New Roman 10 pt.

Does the project template font need to match the Volume 1 document font requirements, or can it stay at Times New Roman 10 pt?

See Amendment 0005.

Minimum 10-point font, Times New Roman

63 RFP, Section

- - Please clarify which is Volume 1 and which is Volume 2. Is the Price Volume considered Volume 1? Is the Non-Price Volume considered Volume 2?

Confirmed.

65 RFP, Section 01 00 00 –

General Requirements

- - Please provide the Davis Bacon Act Wage Determinations for seed project.

See Amendment.

66 RFP, Section

- - Will the Government allow Offerors to include a Cover Letter and not count it within the page limits?

67 RFP, Section

- - Will the Government allow Offerors to include Glossary of Acronyms and not count it within page limitations?

Confirmed.

68 Attachment A - - On the Construction and Design Experience Project Data Sheet, may we delete block 8 on construction projects and block 7 on design projects?

Bid per RFP.

69 RFP, Section

3(b), Factor 1

(2) Design Experience

- Under Design Experience, please confirm that the additional information requested for the Design Firm is not counted in the page limit for projects:

1) Designer of Record identification information and 2) the teaming agreement or other commitment documentation

Confirmed.

70 RFP, Section

3(b), Factor 3 - For Factor 3 – approach, please confirm that the management approach is for the IDIQ and not the seed project /task order.

Bid per RFP, “Offeror shall submit a detailed Management Approach describing how the offeror intends to successfully complete the work awarded under this

MACC.”

71 RFP, Section

3(b), Factor 3 - For Factor 3 – approach, please confirm that the requested org chart is for the IDIQ and not the seed project/task order.

72 RFP, Section

- Will the Government allow an Executive Summary in order to introduce team and provide overview of how Offeror meets the evaluation factor requirements?

Bid per RFP.

73 RFP, Section

5.3 - Will the Government provide an extension to the deadline for submittal of questions to at least a week after the site visit?

See Amendment.

74 RFP, Section

5.2 - Will the Government allow the hard copy submissions to be received a day after the electronic versions are uploaded to the

PIEE?

See Amendment

75 RFP

- - How will the Government account for material cost increases due to supply chain bottlenecks after proposal submittal and before contract award?

Bid per RFP.

76 RFP, Clauses and Section

00 45 00

- - Will the Government include FAR Clause 52.216-4, Economic Price Adjustment, to the contract?

No, Bid per

RFP.

77 RFP, Section

- - Will the Government rank the proposals based on lowest price as the first step in the evaluation process?

Will the Government stop reviewing

No, The Government reserves the right to reject any or all proposals at any time prior to award; to negotiate with proposals once determine the eight lowest priced Offerors are technically acceptable?

any or all offerors; to award the contracts to other than the offeror submitting the lowest total price; to award to other than the offeror submitting the highest technically rated proposal; and to award to the offeror submitting the proposal determined by the Government to be the most advantageous (best value) to the Government.

No.

78 RFP, SF 1442 Block 13 - Will the Government provide an extension to the proposal due date by three weeks after the site visit in order to allow time for vendors to provide pricing more accurately?

See Amendment.

79 1576521_SP-

254_DWGS

- HM-101 Keynote 1 states inspection survey of lead available in the Specs. This report was not provided. Please provide.

Refer to Addendum A.

80 1576521_SP-

254_DWGS

- HM-101 Keynote 7 states to remove existing lights with PCBS and ballast. There is no survey of this, and nothing shown in the drawings for lights to be

Note 7 is located in the Mech and Elect rooms.

Also called out on Arch and Elect removed. Please clarify.

drawings. Bid per RFP.

81 1576521_SP-

254_DWGS

- A-502, A-404 Regarding the precast concrete sills and caps, the note b3-a404 states to match existing.

There was no spec provided for the sills and caps.

Please provide the finish and manufacturing requirements for this item.

Bid per RFP.

82 1576521_SP-

254_DWGS

- A201-A-202 Regarding the windows to be removed and reinstalled as shown. Based on our feedback from the Glazing Subcontractors, this is not achievable.

They will be damaged in the removal process as you cannot keep frames from being bent. The age of the windows also makes this impossible. It would be advisable to ask for an alternate to replace with similar style storefront and windows. Please clarify this as an option.

Bid per RFP.

83 1576521_SP-

254_DWGS

- S-301, S302 This section calls for steel being replaced at the window headers and sill. The probabilities of matching exact openings are very unlikely, and to reinstall the existing windows in the new openings will also make this an impossible task.

This question relates to previous question and request to add an option to replace windows and storefronts. Please clarify this as an option.

84 1576521_SP-

254_DWGS

- G-003 In reference to the phasing plan, the specs state the building will be occupied. Please confirm the occupants will not be in our phase of work area.

Refer to Addendum B.

85 1576521_SP-

254_DWGS

- G-003 Assuming the occupants will not be in our phase of work, what is the transition time to move occupant out of the next phase area of work?

Refer to Addendum B.

86 1576521_SP-

254_DWGS

- SD-301- a 302 The cross section of the existing walls does not show any insulation. The new cross section on sheet a-302 shows 1-1/2” rigid insulation. Is this also part of the new work is to upgrade to the rigid insulation? Please clarify.

Yes Bid per

RFP.

87 1576521_SP-

254_DWGS

- S-501 DETAIL C2 AND

C4 show tube steel connections. Please clarify the location where this is being done.

Refer to S- 301 keyplan, S-501 sections A1, A2, and C1, and end conditions at

(E) columns shown on C2 and C4 and bid per RFP.

88 General - - Is this project wage scale? If so, please provide.

The Government needs more detail to sufficiently answer this question.

89 1576521_SP-

254_DWGS

- SHEET SD-401- Regarding SHEET

SD-401- NOTE 13,

is this note related to item - bid sheet

ADD ITEM

0001AB? If not, please clarify location in the drawings as it gives quantity, but no location.

No. Sheet A- 105 calls out the location of the ballasted guardrail / fall protection safety rails.

Bid per RFP.

90 1576521_SP-

254_DWGS

- - Are there any as-built drawings of this building?

Refer to Addendum B.

91 1576521_SP-

254_DWGS

- A-503, S-301, S-302 The notes state at these locations to replace block as needed for the window heads and sills. This is impossible to forecast. The steel lintels are supporting the block, and they will be compromised and fall apart when removed and new installed. Since the Government gave a quantity for brick to be removed and replace, can the Government please provide a quantity of block to be removed and replaced at the window heads and sills?

Refer to

92 1576521_SP-

254_DWGS

- AD-102, A-201 Note 2- on sheet AD-102, gives quantity of 9979 SF of brick to be removed. Note 1, on A201, gives quantity of 11,346 sf of new brick.

Please clarify the additional brick. Is this for the canopies and infills?

Yes, the additional brick is for canopies, infills, and additional parapet height.

93 1576521_SP-

- AD-201 NOTE 15 Note 15 states to remove Condensate line for HVAC unit. There is no new plan shown to install new line.

Please confirm if this note is correct.

The note is correct. A new condensate line has been added as part of new work.

Refer to Addendum B.

94 1576521_SP-

254_DWGS

- AD-105 NOTES 7-12 refer to mechanical work to be demolished or replaced. There were no mechanical drawings provided to know what the system is or sizing required. We will need mechanical drawings for any mechanical work.

Please provide.

Notes have been added to sheet AD105 to clarify mechanical information.

95 1576521_SP-

- AD-106 Regarding Note 10

- Mechanical unit to Remain. This is not possible since the roof structure and decking are to be replaced underneath it. Note 11 states – mechanical roof top structure to remain, see structural. The structural drawings, SD-401, clearly shows to remove all those joist, and S-401 shows new deeper joist being installed. The mechanical unit and any other items located on that area will need to be removed in order to complete this work.

Please clarify and provide mechanical drawings.

Mechanical Unit structure is not attached to joists that are scheduled to be removed. Bid per RFP.

96 1576521_SP-

254_DWGS

- S-407 The canopy for the steel stairs, note 4, states to match building 256

Details are included on sheets S-407, S-408 & S-canopy. Please provide the details of building 256 canopy. Please provide the age of canopy too.

409. SP-256’s canopy was installed in 2021. Bid per

RFP.

97 1576521_SP-

254_DWGS

- A-505 The stair canopy roof is not defined in the cross section.

What is the actual roof? Please clarify.

Refer to Structural sheets. Bid per RFP.

98 1576521_SP-

254_DWGS

- A-202-A-504 Note 14 states to match existing roof ventilator and refers to A3-A504.

This detail shows roof curbs. We need the mechanical drawings to define any mechanical systems required.

Please clarify.

Refer to Addendum B.

100 1576521_SP-

254_DWGS

- AD-201- A202 Note 8 – AD-201, states Remove outside air intake louver and prepare for new louvers-use 46 for bidding purposes. Note 8- A-202, states reinstall salvaged air intakes-assume

56. Please explain the difference in count. The elevation layouts look the same from demo to new.

Air intake louvers on the south elevations of the building are different from the ones on the north elevations.

The intent is to salvage and reinstall the louvers on the south elevations and to replace existing air intake louvers and hoods on the north elevations with louvers to match the ones on the south side.

101 1576521_SP-

254_SPECS

07-21-19.01 - Regarding the Specifications 07- 21-19.01, Self-adhered air barrier.

This is specified;

Refer to sheets A-501, A-502, and A-503. Bid per RFP.

however, it is not clear on the plans where this is being applied. Please clarify.

102 General May we have the list of plan holders for this solicitation?

No such list exists.

103 General Regarding past performance requirements will experience of our design partner firm and key managers be considered?

Yes.

104 RFP Section

- 5.2

5.2.1 – Proposal Submission Instructions

Many subcontractors will not have pricing available the day prior to bid submission. Can you please consider accepting hand-delivered bids for the original and CD-ROM versions.

No, bid per RFP. See Amendment 0005.

105 9 of 59 Experience, Para. 1

Requires one of the relevant projects to have a final construction cost of $2,000,000 or greater. The last paragraph on page 10 of 59, under Factor 1, states that “the absence of one project that has a $2,000,000 or greater final construction cost…will result in a rating of

UNACCEPTABLE

for this Factor.” This $2M requirement precludes recently certified 8(a) companies from qualifying even if they have the relevant construction experience required to perform under this contract. We respectfully request that this final construction cost requirement be lowered to allow for fair competition from all 8(a) firms.

106 PIEE system This solicitation is currently marked as DRAFT in the PIEE system and does not allow Offers to be submitted. Please adjust the listed in PIEE so that offers may be submitted.

Draft has been removed.

107 RFP Section 5.1 and 5.2

Due to mailing services not guaranteeing delivery dates, the proposal will need to be sent a few days prior to the actual due date.

Since the proposal is also being submitted via PIEE, will it be acceptable to submit the proposal on the due date via PIEE and then mail the hard copies of the proposal on the due date? The proposal hardcopies will be an exact match for the proposal submitted via

PIEE.

See Amendment 0005.

108 G003 The temp wall detail is showing the wall only going to a finished ceiling w/ poly to protect the ceiling. How is the wall to be secured to a suspended ceiling?

If wind is a consideration, the wall likely needs to be extended to the deck and the ceilings removed and replaced, suggesting likely new ceilings possibly in the rooms.

109 G003 Please confirm the entire area within each phase will not be occupied

110 G003 How much time will there be needed between phases for the bldg occupants to move from each area?

For bidding purposes assume 1 week of turnover time between phases. Refer to Addendum B.

111 Abatement HM101 Please provide a copy of the abatement reports for ease of clarifications. Did not see this in the specifications as stated

Refer to Addendum A.

112 HM101 Note 1 – is there lead paint on the stairs and railing that need to be abated or just the walls and ceilings as stated?

Abate walls and ceilings as stated. Bid

113 SD101 There are not any locations shown to have silt fence, please confirm none is required

Refer to Civil Sheets in

114 CD101 & C101 There are hatched areas at the north and south side of Bldg SP-383 without any notes.

Please confirm these areas are not to be included in this project or please define what is required at these locations.

Refer to C- 001 for work legend. Bid

115 SD101 & SD102 Note 8 on SD101 and note 7 on SD102 states to sawcut the concrete, provide smooth edges, free of exposed rebar.

What is meant by free of exposed rebar? Is the rebar to be cut only or removed from the concrete remaining? If removed, to what depth and what is the rebar spacings in these areas?

Refer to S- 003 Concrete Note #1 for cover requirements and bid per

RFP.

116 A1/A508 & C1/AD102 Please confirm this masonry replacement and expansion joint only occurs at the 2nd floor mech room 206 and does not extend down to the first floor mech room 109.

Bid per RFP.

117 Windows Is there a place on base near the site to where the windows could be stored for re-installation?

Refer to Specification 01 50 00. Bid

118 Abatement Is there lead paint on the CMU above the windows? If so, will the paint need to be abated before removal?

Refer to HM101 for hazmat information.

Bid per RFP.

119 Abatement Is there lead paint on the steel lintels that are being removed? If so, will the paint need to be abated before removal?

Refer to HM101 for hazmat information.

Bid per RFP.

120 Abatement Is there lead paint on the fire escape that is to be removed? If so, will the paint need to be abated before removal?

Refer to HM101 for hazmat information.

Bid per RFP.

121 Brick Veneer The drawings are stating 11,346 sf total exterior brick veneer project.

Confirm this quantity includes the toothing in areas as well as a decent waste factor for cuts, etc.

122 Brick Veneer Are there any areas on the east and west walls where the new brick will need tuck pointed into the corners or does all the areas stop at control joints?

Bid per RFP.

123 AD201 Note 23 Please provide specifications for the new gravity ventilators we are to provide on the roof; at least the manufacture and model number

124 Bulkhead SD301 Please confirm the bulkhead at the windows is supported to the bar joist above so when the ceiling is removed along the windows the bulkhead remains

Bulkheads at windows are supported to the bar joists.

Refer to Architectural Sheets. Bid

125 Temp Doors What will the requirements be for the temporary doors? Will any of the temp doors need to meet ADA or Life Safety egress requirements?

Temporary doors are for Construction Crews only.

Bid per RFP.

126 AD106 There appears to be a framing system of beams over the mech room supporting a piece of mech equipment area where the deck and joist are to be replaced.

Please provide pictures of this framing system. It appears this framing system and mech unit will need to be removed to replace the deck and joist, please advise. Note 29 on AD201 states rooftop unit to remain.

127 SD401 Note 1 States to remove interior partition CMU wall for removal of joist and new work.

Please provide pictures of the walls in the joist.

How many courses of CMU are to be removed?

Refer to notes on AD105.

Bid per RFP.

128 SD401 Note 4 States to disconnect all equipment and conduit from joist prior to joist removal. Please provide a list and drawings of items to be disconnect.

Please provide pictures of the items to be disconnected.

Confirm none of these items are fire protection, plumbing, nor HVAC since there are not any specifications for these trades within the project.

Refer to Architectural Sheets for additional information.

Bid per RFP.

129 AD105 Notes 8&9 Please clarify which piping and duct are to be supported and which are to be removed?

130 AD105 Note 11 Please clarify the type of piping that is to be remove and replaced shown in note 11 in the elect room 225

131 SD401 Notes 5 & 13 Please confirm notes 5 and 13 are

Yes, both notes refer to for the same location and two separate items.

the same item. Bid per

RFP.

132 AD103 &

AD105

Notes 1 The quantities are not the same for the ACT tile per the project AD103 states 132 sf and AD105 stated 350sf. Please clarify

133 AD102 Note 24 States “Tooth-out and remove existing cut interior CMU adjacent to abandoned OH door frame to be removed. Is it known if the cells of the CMU are filled with concrete? Please provide the quantity of CMU to be removed and replaced

134 S407 Note 4 States roof canopy to match adjacent bldg SP-256.

Please provide the manufacture of the adjacent canopy as well as pictures of it

135 8, 12 and 14

RFP

Page 8 of the RFP states that the font requirements must be 11 point font using Times New Roman. The Safety Narrative states that the page limitation is two

(2) single-sided pages or one (1) double-sided page (see page 12 of the RFP). The Factor 3-Management Approach narrative states that the page limitation is five

(5) single-sided pages (see page 14 of the RFP). Based on the 11 point font requirements and the safety and management content requirements, will the government consider increasing the Factor 2 Safety narrative page count to three (3) pages and increase the Factor 3 Management Approach narrative page count to fourteen

(14) pages in order that the offeror can provide more detailed responses to these critical evaluation factors.

136 Are Anti- Terrorism-Force Protection (ATFP) requirements are applicable for openings (windows, doors, etc.) for the project?

No ATFP is required. Bid per RFP.

137 Please confirm that Microsoft Project can be used for scheduling software.

Provide a Primavera P6 cost-loaded schedule per requirements.

Bid per RFP.

138 Please confirm that the seed project will not need a cost loaded schedule in P6 software.

cost-loaded schedule per requirements.

Bid per RFP.

139 RFP

5.2.1

The bidding process will not allow us to complete the price proposal until the day of the bid therefore, we are requesting 3 additional days for receipt of hard copies to your office.

RFP Page 16 5.2

Requiring mailed/shipped binders means we must print and have the binders delivered by the same time that they are due electronically on PIEE. The government would benefit if we could provide our pricing only on the PIEE site. We could then provide the most competitive pricing, which is determined greatly by our subcontractors’ bids and which we will not receive until very late.

Would the government consider allowing Offerors to submit pricing via PIEE and not requiring it to be printed and shipped?

See Amendment 0005.

141 10 1st Full n/a According to Page 10 of the solicitation under Factor 1- Experience (a)(1), if offeror is a joint venture, the firm is to include an SBA-approved JV agreement.

However, according to CFR § 124.513, Section

(e) Prior Approval, (1), “SBA will not approve joint ventures in connection with competitive 8(a) awards.” SBA no longer provides or requires prior approval of JV agreements for competitively solicited 8(a) contracts.

142 Due Date n/a n/a In the interest of providing a more accurate price estimate, ERS- CYE JV II would like to know if it is possible to extend the due date for the proposal by two weeks. We would like to have a bit more time after the site visit on May 25th to reevaluate and adjust our estimates based on site conditions.

See Amendment.

143 8 1st Full n/a On page 8, the solicitation states that offerors shall submit a “Signed Bank Reference demonstrating adequate financial resources.” Is each firm in a JV entity required to submit a bank reference of their own? Or will a joint bank reference be required?

Individual bank references are acceptable.

144 Pages 1, 7, and 16

Page 1, Block

13. Additional Submittal Requirements Page 7, Para.

3(a)(1) Solicitation Submittal Requirements Page 16, Para.

5.2.3 and 5.2.4 Proposal Submission Requirements

N/A Page 1 states to submit offer in original and (2) copies … Page 7 states to submit (1) electronic copy thru PIEE and (1) hard copy and (1)

CD…

Page 16 states “hand delivered proposals …will not be accepted”

Please clarify how we are to send the proposals. Mailing prior to bid date/time is not feasible.

145 Note 21 – AD102 Note states to provide temp power for server room HVAC units and server equip.

Is the contractor to assume the HVAC units referenced are the existing unites or does temp ac/heat need to be provided?

Temp power to the existing HVAC units is the intent.

146 Plumbing &

HVAC

specifications or drawings have not been provided.

However, numerous items of work that fall under these divisions are found on demo and architectural drawings and thereby assumed to be included in the scope of work, i.e., gas meter/gas piping, roof drain domes, insulated mechanical piping thru joist, re-support of piping and ductwork, gravity ventilators, exhaust fans, etc.

Please provide drawings and specifications for all equipment and materials required to perform all Plumbing and HVAC work.

147 A-105 Note 8 & 17 states to provide gravity ventilators to match existing. During the site visit an attempt was made to find an equipment tag that would provide adequate information to match existing. No equipment tags were found on the existing ventilators.

Please provide model and serial numbers of existing equipment.

148 There is no mention of DDC controls. Are DDC controls required for any new or existing equipment? If so are DDC controls proprietary and who is the proprietary contractor?

DDC are not required. Bid per RFP.

149 AD201 & AD202 Note 8 states that existing thru wall louver duct to remain. By adding 1 ½” polyiso insulation on top of cmu backup wall will this require alteration to the length or replacement of existing thru wall louver duct for connection to new louver?

Alteration is not required as the wall thickness is consistent from existing to new. Bid per RFP.

150 A-101 & A-601 Note 7 indicates provide HM frame and door system complete and to assume a quantity of 5. Door schedule on A-601 only shows 3 doors systems to be provided. Which is correct 5 door systems or 3 door systems? If 5, please identify the other 2 openings and their requirements.

151 AD103 & AD105 Note 1 on AD103 states to assume a qty of 132 sf of 2 x 2 ACT to be removed. Note 1 on AD105 states to assume a qty of 350 sf of 2 x 2 ACT to be removed. Which qty is correct to assume?

152 AD106 & A-105 Note 12 on AD106 states to remove condensation piping line complete from mechanical rooftop unit to remain (note 10). Note 9 on a- 105 shows the mechanical rooftop unit to remain but there is no mention of providing a new condensation piping line to this unit to replace the one removed. No mechanical drawings or specifications have been provided.

Please advise.

153 CD101 Only (IP) inlet protection and (TP) tree protection is shown on this drawing. There is no (SF) silt fence requirement shown.

Please confirm that (SF) is not required or provide drawing showing where (SF) is required.

Refer to Addendum B.

154 A101 Ref. drawing A101 Note “3” which states to replaced missing and damaged interior and exterior window mullions.

Can you please provide an estimated bid quantity so that all bidders will be pricing the same quantities?

155 Specs 01 50 00 3.5.3 Ref. Spec section 01 50 00 para.

3.5.2. Please

confirm that the contractor will be REQUIRED to provide a temporary field office trailer on site for the duration of the project.

Bid per RFP.

156 Specs 01 50 00 2.3 Ref. Spec section 01 50 00 para. 2.3.

Please advise if the contractor is to provide fencing around the entire project site during the project and what type of fencing is required (6 ft chain link w/screening, 4ft orange mesh safety fence?)

Bid per RFP.

157 Site Visit At the site visit it was noticed that above the SAPC ceiling on the first floor there were adhesive “pucks” stuck to the underside of the concrete deck above. We would assume that these are asbestos containing pucks and would need to be abated in the areas where the ceiling is to be removed. Please advise if these are to be tested and abated.

158 Site Visit At the site visit it was noticed that

Work will include there is furniture in most every room.

Please advise if the contractor is to include furniture removal, storage, and reinstallation in the proposal or if the Gov’t is handling the furniture removal.

relocation of furniture within the building.

159 Drawings G003 Please advise if there is any required downtime b/w each phase to allow for Gov’t personnel to relocate out of the following phase.

For bidding purposes assume 1 week of turnover time between phases. Refer

160 RFP pg. 16 Paragraph 5.3 on

pg. 16 of 59 states that the PPI’s are due 14 days prior to the Proposal due date which only allows 1-day after the Site Visit to submit questions.

This doesn’t allow sufficient time for offerors to receive PPI’s for our subcontractors.

Will the Gov’t please allow another week for PPI’s to be submitted?

Bid per RFP.

161 Page 12 Factor 2 N/A If an offeror’s design team is a subcontractor, are we supposed to include their TCR and DART rates in Factor 2?

No.

162 RFP The government acceptance period is listed at 120 calendar days. Can this be reduced to 60 calendar days based on the volatility of todays market?

163 8, 12 and 14

RFP

Page 8 of the RFP states that the font requirements must be 11 point font using Times New Roman. The Safety Narrative states that the page limitation is two

(2) single-sided pages or one (1) double-sided page (see page 12 of the RFP). The Factor 3-Management Approach narrative states that the page limitation is five

(5) single-sided pages (see page 14 of the RFP). Based on the 11 point font requirements and the safety and management content requirements, will the government consider increasing the Factor 2 Safety narrative page count to three (3) pages and increase the Factor 3 Management Approach narrative page count to fourteen

(14) pages in order that the offeror can provide more detailed responses to these critical evaluation factors.

Repeat of 135

164 Are Anti- Terrorism-Force Protection (ATFP) requirements are applicable for openings (windows, doors, No ATFP is etc.) for the project?

165 Please confirm that Microsoft Project can be used for scheduling software.

cost-loaded schedule per requirements.

Bid per RFP.

166 Please confirm that the seed project will not need a cost loaded schedule in P6 software.

cost-loaded schedule per requirements.

Bid per RFP.

167 RFP

5.2.1

The bidding process will not allow us to complete the price proposal until the day of the bid therefore, we are requesting 3 additional days for receipt of hard copies to your office.

Repeat of 139

168 A-103 Note 14 – Could you provide specifics for the (5) additional doors, frames and hardware. Size of the openings, steel or wood doors and what type of hardware will be required, locksets, panic devices, closers, etc.

Refer to Sheet A-601 and Division 8 Specifications . Bid per RFP.

169 A-601 Please confirm if the HM doors and frames shown on the door schedule are NOT part of the allowance of 5 door units from note 14 on sheet A-

170 01 32 17 /

1.8 Is Primavera

software proprietary to this project?

Provide a Primavera P6 cost-loaded schedule per requirements.

171 01 32 17 /

1.2.2 May the project

manager be the Project Scheduler?

Bid per RFP.

172 01 45 00.10 20 / page 2

1.5.1.1 If all positions, superintendent, SSHO and QC, may be the Superintendent are one or two people required for this project?

Refer to Addendum A.

173 5. Proposal Requirements

/ page 16

5.2 The proposal

requirements state that the “hard copy” & CD of the technical proposal and the bid must be mailed in and received the same day as the electronic bid is submitted in PIEE.

Is it acceptable to mail the required hard copies after the electronic submission to arrive within 3 days of the electronic submission in

PIEE?

0005.

174 Was a geotechnical report done for this project, if so, can a copy be provided?

No. Bid per

RFP.

175 Are there any ATFP requirements for the reused windows?

No ATFP is required. Bid per RFP.

176 AD102, AD103, AD104,

AD105, AD201, AD202,

AD301

The existing windows are to be salvaged for reinstallation. Our conversations with the needed subcontractors are that the windows are not in an existing condition that they are willing to salvage or warranty and workmanship for reinstallation. Als o, if the windows are to be reused, how are any repairs to be quantified as to everyone bidding being equal?

177 S-001 Excavation & fill note #11 states that all excavated material is assumed to be contaminated, what tests are required to be performed on the soils prior to removal from site?

Refer to 01 57 19 Temporary Environmenta l Controls Paragraph

1.2.15.6 & 3.7 and bid per

RFP.

178 SD101 Demo note #11 states to remove all expansion joint caulking, is the caulking to be assumed to be ACM? (typ for all caulking)

Refer to

HM101

requirements.

Bid per RFP.

179 SD104 The roof demo plan area A at the steel beams supporting the HVAC unit is not stated to be scraped and repainted, at the site visit the beams/columns were noticed to be in pretty rough condition, are these to be addressed? If so is the paint to be considered to be lead based?

Refer to page S-002 Note 5 under “Blasting Existing Metal Notes” and bid per

180 SD104, Note #7 Referring to Note #7, please confirm the limits of 1 ½” metal roof decking to be removed are typical only where joists are being removed/replaced?

181 02 41 00 1.3.1 SD104 & A-505 Please confirm the existing to remain metal framing support curb at the

Rooftop Mechanical equipment is supported by the load bearing CMU walls in the Mechanical Room?

The plans indicate there is existing steel column supports, but these were not observed in the Mechanical Room during the walkthrough. This information will impact Contractor shoring/bracing considerations and structural demolition methods.

182 07 52 00 2.2 A-504,505,506 Under the Modified Bituminous Membrane Section, there is no cap sheet specified.

Only a base and interplay membrane which are the same.

Please advise

Refer to Addendum B.

183 AD106,

AD503/A506

Is the intent to raise the existing steel support framing to accommodate the new flashing heights for the expansion joint?

The notes currently state the existing steel framing is to remain per Sheet AD106, Note #11, and Note #3 on SD104.