Amnd 0001 20R4044 FINAL.pdf

PDF 904 KB Posted

Attached to
TRAINING ROAD REPAIRS AND DEBRIS REMOVAL, PHASE III
Solicitation number
N4008520R4044
Issued by

View the file

Other files

File Type Posted
19-0161 DWG REV A.pdf PDF
Amnd 0002 20R4044 FINAL.pdf PDF
19-0178 DWG REV A.pdf PDF
19-0169 GE REV A.xlsx XLSX spreadsheet
20-0022 SOW Phase 3 REV A.pdf PDF
CLNC 02 82 30 RE-ESTABLISH VEGETATION.pdf PDF
20-0022 SITE MAP.pdf PDF
31 05 19 GEOTEXTILE.pdf PDF
19-0177 DWG REV.pdf PDF
19-0158 DWG REV A.pdf PDF
19-0169 SOW REV A.pdf PDF
19-0179 DWG REV A.pdf PDF
19-0179 GE REV A.xlsx XLSX spreadsheet
PRICE PROPOSAL FORM.pdf PDF
Waiver.pdf PDF
Master PPI Form Template.xls XLS spreadsheet
RFP Training Road Repairs Phase 3.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

19-0169 Training Road Repairs and Debris Removal, Phase III Solicitation N40085-20-R-4044 Marine Corps Base Camp Lejeune, North Carolina Amendment 0001

Block 14. DESCRIPTION OF AMENDMENT (cont.)

A. The following additional information is provided for the site visit scheduled for the subject project:

1. DATE / TIME: 05 March 2020 at 0830

2. MEETING LOCATION: Attendees will meet at the Visitor Center, Building 818 on Holcomb Boulevard, Marine Corps Base Camp Lejeune, North Carolina.

3. ADDITIONAL INFORMATION: Contractor must provide a list of all site visit attendees to casey.buell@navy.mil NLT 1400 on 04 March 2020 in order to facilitate access to the base. Names provided shall reflect the individual’s name on his/her driver’s license.

4. EMERGENCY PHONE NUMBER: Meghan Hislop’s Work Cell: (757) 675-0535

B. Instructions for the day of the site visit:

1. Attendees shall bring the following items:

a. Valid driver’s licenses

b. Driven vehicle’s current registration and proof of insurance

c. Completed waiver

2. Attendees shall park their vehicle in the back of the Visitor Center parking lot.

3. Attendees will then load the Government-provided transportation, which will also be parked in the Visitor Center parking lot. Attendees will not need to enter the Visitor Center for passes, as they will be sponsored aboard the installation.

However, the list of all site visit attendees is still required for participation in the site visit.

4. Departure from the Visitor Center will be promptly at 0830. The Government will not wait for registered attendees who are late.

5. Attendees shall be transported to the multiple site visit locations via Government-provided transportation. No personal vehicles will be allowed due to parking limitations. A maximum of four (4) seats per Contractor will be permitted. After COB 04 March 2020, any unclaimed seats will be released on a first-come first-served basis.

C. The cutoff for PPIs is extended to 12 March 2020 in order to process all inquiries by the proposal due date.

D. All other contract terms and conditions remain unchanged.