19-0169 SOW REV A.pdf

PDF 12 KB Posted

Attached to
TRAINING ROAD REPAIRS AND DEBRIS REMOVAL, PHASE III
Solicitation number
N4008520R4044
Issued by

View the file

Other files

File Type Posted
19-0161 DWG REV A.pdf PDF
Amnd 0002 20R4044 FINAL.pdf PDF
19-0178 DWG REV A.pdf PDF
19-0169 GE REV A.xlsx XLSX spreadsheet
20-0022 SOW Phase 3 REV A.pdf PDF
CLNC 02 82 30 RE-ESTABLISH VEGETATION.pdf PDF
20-0022 SITE MAP.pdf PDF
31 05 19 GEOTEXTILE.pdf PDF
19-0177 DWG REV.pdf PDF
19-0158 DWG REV A.pdf PDF
19-0179 DWG REV A.pdf PDF
19-0179 GE REV A.xlsx XLSX spreadsheet
PRICE PROPOSAL FORM.pdf PDF
Waiver.pdf PDF
Amnd 0001 20R4044 FINAL.pdf PDF
Master PPI Form Template.xls XLS spreadsheet
RFP Training Road Repairs Phase 3.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev A 20 MARCH 2020

PROJECT NUMBER: 19-0169

CONTRACT NUMBER: N40085-19-B-0169

TITLE: TRAINING ROAD REPAIR PHASE 3

SCOPE OF WORK

This project will consist of repairing washouts, failed culverts and damaged pedestrian bridges caused by Hurricane Florence.

Detailed requirements are contained in the following projects:

19-0158 REPAIR CULVERT HWY 172

19-0161 REPAIR JULIAN C SMITH ROAD

19-0164 REPAIR S455 PED BRIDGE

19-0170 REPAIR CULVERT, CAMP DAVIS S

19-0171 REPAIR CULVERT, COMBAT TOWN

19-0172 REPAIR CULVERT, MAC RANGE ROAD

19-0174 REPAIR STORMWATER SYSTEM, RIFLE RANGE

19-0175 REPAIR CULVERT, HOLCOMB BLVD

19-0176 REPAIR S1668 PED BRIDGE

19-0177 REPAIR WASHOUT B ST AND C ST MARSOC

19-0178 REPAIR MULTIPLE STORMWATER GREENWAY TRAIL

19-0179 REPAIR EROSION WILSON BLVD OVERPASS

20-0022 GRAVEL ROAD REPAIR PHASE 3

The work is located on Camp LeJeune, NC. Streams, and possible wetlands, occur in several of the proposed construction footprint. Contractor shall be responsible for obtaining authorizations for impacts to streams and wetlands from the United States Army Corps of Engineers, North Carolina Division of Water Resources and the North Carolina Division of Coastal Management, in coordination with the MCB Camp LeJeune Environmental Planning section (451- 9660).

HAZARDOUS MATERIALS

19-0161 REPAIR JULIAN C SMITH ROAD is located within the boundaries of Installation Restoration (IR) site IR-28, a former burn dump. Additional information is in the documents for 19-0161 REPAIR JULIAN C SMITH ROAD.

DISTURBED AREAS

For all project, re-sod disturbed areas with centipede sod. Use High Quality sod of known genetic origin, free of noxious weeds, disease and insect problems. It should appear healthy and vigorous and conform to the following specifications:

1. Sod should be machine cut at a uniform depth of 1/2 - 2 inches (excluding shoot growth and thatch)

2. Do not cut sod in excessively wet or dry weather.

3. Sections of sod should be a standard size as determined by the supplier, uniform and un-torn.

4. Sections of sod should be strong enough to support their own weight, retain their size, and shape when lifted by one end.

5. Harvest, delivery and installation of sod should take place within a period of 36 hours.

Sod Installation:

1. Moisten the sod after it is unrolled helps maintain its viability.

Store it in the shade during installation.

Rev A 20 MARCH 2020

2. Rake the soil surface to break the crust just before laying sod.

During the summer, lightly irrigate the soil, immediately before laying the sod to cool the soil, reduce root burning and die back.

3. Do not sod on gravel, frozen soils, or soils treated recently with sterilants or herbicides.

4. Lay the first row of sod in a straight-line perpendicular to the direction of flow with subsequent rows placed parallel to and butting tightly against each other. Stagger strips tin a brick-like pattern.

Do not stretch or overlap sod. Tightly but all joints to prevent voids. Use a knife or sharp spade to trim and fit irregularly shaped areas.

5. Install strips of sod with their longest dimension perpendicular to the slope. On slope 3:1 or greater, or whenever erosion bay be a problem, secure sod with pegs or staples.

6. As sodding of clearly defined areas is completed roll sod to provide firm contact between the roots and soil.

7. After rolling, irrigate until the soil is wet 4 inches below the sod.

8. Keep sodded areas moist to a depth of 4 inches until the grass takes root. This can be determined by gently tugging on the sod - resistance indicates that rooting has occurred.

9. The sod should be firmly rooted before mowing, usually 2-3 weeks.

Maintenance:

After the first week, water as necessary to maintain adequate moisture in the root zone and prevent dormancy of the sod. Do not remove more than one-third of the shoot in any mowing. Maintain grass height between 2-3 inches unless otherwise specified. Contractor is responsible for the site, including mowing, until BOD. Contractor should delineate construction site to prevent base maintenance mowing service from mowing contractor's construction site.

After the first growing season (April 15 - October 31), established sod requires fertilization, and potentially require lime. Follow soil test recommendations.