SF30_Amendment_0005.pdf

PDF 614 KB Posted

Attached to
P990 F-35B Vertical Lift Fan Test Facility, MCAS Cherry Point NC
Solicitation number
N4008519R9019
Issued by

About this file

This document contains an amendment to a solicitation for the construction of a reinforced concrete vertical lift fan test facility at Marine Corps Air Station Cherry Point in North Carolina. Key details include:

  • The amendment provides pre-proposal inquiry responses and revised drawings in response to bidder questions, and confirms the proposal due date remains June 27, 2019 at 2:00 PM Eastern Time.

  • The project involves construction of a test facility building with concrete floors, walls and roof along with related site infrastructure. The building will include areas for staging, control rooms, equipment rooms, an inlet house, test area, intake plenum, exhaust rooms and a 40,000 HP electric motor prime mover with intake and exhaust stacks.

  • The solicitation is being conducted as an unrestricted full and open competition by the Naval Facilities Engineering Command Mid-Atlantic requiring both price and non-price proposals, evaluated using best value tradeoff procedures.

  • The magnitude of construction is between $10-25 million, using NAICS code 236220 for Commercial and Institutional Building Construction with a small business size standard of $36.5 million. A sources sought notice found no reasonable expectation of adequate small business participation.

SF30_Amendment_0005.pdf

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5526275

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide PPI Responses and Revised Draw ings, please see SF30 Continuation Page.

Proposal Due Date Remains Thursday, 27 June 2019 by 2PM EST.

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jun-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008519R9019

X 9B. DATED (SEE ITEM 11)

30-Apr-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jun-2019

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9019

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0005

SOLICITATION NO. N40085-19-R-9019

PROJECT TITLE/LOCATION: P990 F-35B Vertical Lift Fan Test Facility MCAS Cherry Point, North Carolina

PREAWARD INQUIRY FORM

Question No.

Date Received

REFERENCE QUESTION GOVERNMENT RESPONSE Posted on

Amend No.

Page Sectio n

Para.

1 6/5/2019 3.9.3.

All Section states finishes that are for publick view and not expossed to public view. Please give areas on plans to show what finish is for each area.

The references to “not exposed to public view” and “exposed to public view” are in paragraphs

3.9.3.2 and 3.9.3.3, respectively, of specification section 03 30 00 Cast-In-Place Concrete.

Surfaces never to be seen after construction must be considered “not exposed to public view” and therefore governed by paragraph

3.9.3.2. This includes, but is not limited to: the

interior surfaces of the parallel concrete walls along column lines 6 and 7, concrete covered by interior or exterior finish assemblies. Concrete surfaces visible after construction, including those painted, sealed, or in the air flow path, must be considered “exposed to public view” and therefore governed by paragraph 3.9.3.3.

For clarity, the following rooms are considered in the air flow path: Exhaust Stack, Exhaust Tunnel, Test Cell 209, Intake Plenum, and Intake House 300.

2 6/6/2019 AE201 Key note #9 calls for insulated hollow metal door and frame. On cl 2 not 9 looks like it is pointing to metal Parapet Cap Please advise?

6/6/2019 - Key note by column line 2 should read "8", not "9".

3 6/6/2019 32 92

2.5 Section 2.5 States water

shall be approved by Contracting officer.

Pleas show location on drawing for bidding porposes. Will irrigation system be installed if so specification will be needed

Permanent irrigation systems are not called for in the design. This section applies to the establishment of sod and plants during final site stabilization and the source of water used during the vegetation establishment period.

Water is to be provided by the Contractor.

4 6/11/2019 DWG S-003, Test Cell Allowances table, This table indicates the prime mover and sole plates are not part of the contract. Please confirm 5 ton ready room crane and dual 5 ton in in test shown A2/S003 are in contractors scope of work.

Correct, per S-003, prime mover and soleplates are not in contract (but anchor rods are in contract).

Confirmed, there are three cranes in contractors scope for this project—5 ton ready room crane, dual 5-ton-hoist test cell crane, and 6-ton prime mover crane. All are shown on S-003, indicated by overhead crane notes on S-002 and details on SF503, and also indicated on other drawings where applicable.

5 6/11/2019 What is extent of contractors scope for the LCI Drive Building and the power Filter Building. If contractor is to receive, set make ready please provide the following:

1. Anticipated weights, deminisions

2. Preliminary drawings and Lifting arraignments

3. LCI building measures approx. 16' x 46'. Is this building split in half and shipped in two 8' x 46' pieces?

4. If LCI is shipped in sections what is scope of contractors repsonsibility for interior assembly.

5. Are there Special instructions for these items.

Extent of contractors scope is to provide the supporting infrastructure shown and detailed on the drawings. LCI and power filter equipment are under separate contract, requested parameters are the scope of separate contract.

6 6/11/2019 Does CLIN 0001AA pretain to all building work inclusive of the Control Building in the switch yard since it is a building or is CLIN 0001AA asking for the price of the actual testing facility and the Control Building falls under CLIN 001AB since it is outside of the actual Test facility?

Include the Control Building (or Enclosure - as identifed on the Architecture drawings) with

CLIN 0001AB.

7 6/11/2019 P-001 On Drawing P-001, the Plumbing Air Compressor Schedule says the basis of design is a Gardner-Denver HR10D-12 which is a splash lubricated compressor without oil filter. Note (3. A.) under the schedule calls for a pressure lubricated pump with oil filter.

That would change the basis of design model number to: HPL10D-12.

Can you verify which type of Air Compressor the government would require?

Bid on model number HPL10D-12. 0004

8 6/11/2019 Drawi ng

MH-

Drawing MH-101 shows Condenser Water (CDWS) running to four different types of Heat Exchangers. In the Condenser Water Piping Diagram on Drawing M- 701, these heat exchangers are labeled HX-2, HX-3, HX-4, and HX-5. The pipe sizes running to these heat exchangers on M-701 are not the same as the pipe sizes on MH-101, notably, the 3-inch CDWS pipe on MH-101 is shown as 5-inch pipe on M-701. These Heat Exchangers are not shown in the Mechanical Equipment schedules. Please clarify pipe sizing, what room this equipment is located, additional piping detail if needed, and who is providing the equipment.

The pipe sizes shown on M-701 is correct.

MH101 and MH102 shows the locations of the test fan equipment, that is provided by others.

The drawings will be revised to clarify the equipment location and to udpate the pipe sizing.

9 6/11/2019 Drawin g P-001

On Drawing P-001, the Compressed Air Dryer Schedule calls for a heatless desiccant air dryer. On drawing P- 501, this same Air Dryer (AD-1) is shown to be a refrigerated air dryer.

Can you verify which type of Air Dryer the government would require?

Bid per Drawing P-001. 0004

10 6/11/2019 C/SF20

2, E1/

SF203

F/SF203

C/SF202, E1/ SF203 &

F/SF203. On each of these wall elevations, there is a Note 6 calling for multiple unsized slotted channels to be embedded in the walls.

What are these channels? Please provide a channel size and/or clarify if these are a cold-formed unistrut type channel.

“Slotted channel” is the generic term for Unistrut. Size these as 1-5/8” wide x 1-3/8” deep Unistrut-type channels with concrete embedment tabs.

11 6/11/2019 AE403 AE403; What is the desired finish for the exterior stair frames, tread, stringers and rails?

Exterior stair steel must be hot-dip galvanized, per sheet SF101.

12 6/11/2019 AE404 AE404; What is the desired finish for the interior mezzanine stair frames, tread, stringers and rails? Similar to PT4 & PT5 for the interior stairs on AF601?

The specified finish for the interior stairs, including railings, stringers and other stair structure must be PT3 per General Note F, on sheet AF601.

13 6/11/2019 DWG AE101 Has mention of GFGI's for equipment items such as Lube Oil Cart, Hydraulic unit, Lift hydraulic unit, FCOC unit. Are any of these equipment items part of contract. If so where can technical information be found?

The equipment listed as GFGI (Government Furnished Government Installed) is shown for reference only and is not part of the contract.

(End of Summary of Changes)