About this file

Amend0005_-_PPI.pdf

View the file

Other files

File Type Posted
Amend_0008.pdf PDF
Amend0007_18-8715.pdf PDF
Amend0007_-_PPI.pdf PDF
Existing_Air-Handling_Units_Info.pdf PDF
Amend0006_18-8715.pdf PDF
Amend0006_-_PPI.pdf PDF
B449-site_visit.pdf PDF
Amend0005_18-8715.pdf PDF
Amend0004_-_PPIs.pdf PDF
Amend0004_-_map.pdf PDF
Amend0004_18-8715.pdf PDF
Amend_0003_18-8715.pdf PDF
Amend0002_18-8715.pdf PDF
Amend0002_-_sample_ltr.pdf PDF
Amend0002_-_PPIs.pdf PDF
Amend_0001_18-8715.pdf PDF
180615_Vol_I_Specifications.pdf PDF
N4008518R8715_RFP.pdf PDF
Attachments.zip ZIP file
180615_Vol_II_Specifications.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. N4008518R8715

PROJECT TITLE/LOCATION: DBB Medical Homport Reno, NLON, Groton, CT

PRE‐PROPOSAL INQUIRY FORM

Question

No. REFERENCE QUESTION GOVERNMENT RESPONSE Posted on

Amend No.

Page Section Para.

1 230000

The phasing Plan is very specific concerning

Phase 1A. It states “Additionally work in

Occupational a Health Rooms 1133, 1134, 1135, 1136, 1138, 1167, 1168, and 1169 shall be scheduled such that no more than 3 rooms are under Construction during regular working hours at the same time”. There is VAT being removed.

A new ceiling grid and tile is being installed. New lights are being installed. The problem is that new ductwork branches off new ductwork mains that serve other phases. This will prevent the rooms from being completed until new Duct is installed in other areas. What is the designers intent?

The intent for construction in the rooms listed is that no more than three of the rooms are unable to be used for their intended purpose at one time. Work may occur simultaneously on each of these rooms provided that it is returned to a usable state prior to the next occurrence of regular business hours.

For example, it would be acceptable to complete the ductwork modifications to all of these spaces during one "down" time (either outside regular business hours or during a planned and accepted outage) and then complete the remaining work during regular working hours in groups of three rooms at one time.