0012.pdf

PDF 173 KB Posted

Attached to
AWARD OF P977, COMBAT VEHICLE WAREHOUSE, ALBANY GA
Solicitation number
N4008518R0617
Issued by

About this file

0012.pdf

View the file

Other files

File Type Posted
Amendment_0011.pdf PDF
P977_REVISEDPrice_Proposal_Form.pdf PDF
Amendment_0010.pdf PDF
Room_Requirments_Break_Room.docx DOCX document
Amendment_0009.pdf PDF
P977_REVISEDPrice_Proposal_Form.docx DOCX document
AMENDMENT_0008.pdf PDF
GEOTECH_REPORT_DATED_Feb_2_18.pdf PDF
P977_sitevisitAttendees000.pdf PDF
Map1.pdf PDF
Albany_Motels.pdf PDF
Amendment_0007__PHASE_II.pdf PDF
P977_Price_Proposal_Form.docx DOCX document
0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
Amend_0002.pdf PDF
0001.pdf PDF
Attachment_A_-_Construction_and_Design_Experience_Project_Data_Sheet.docx DOCX document
Attachment_B_-_Past_Performance_Questionnaire.docx DOCX document
Attachment_C_-_Small_Business_Subcontracting_Record.docx DOCX document
RFP.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5347625

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is issued to provide:

1. Revised Responses to previous PPIs.

2. Provide Responses to Pending PPIs.

3. Provide additional responses/clarifications as provided herein.

Proposal due date remains December 13, 2018 2:00 p.m.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008518R0617

X 9B. DATED (SEE ITEM 11)

18-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Dec-2018

CODE

NAVFAC MID ATLANTIC

MARINE CORPS IPT

9324 VIRGINIA AVE

NORFOLK VA 23511

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008518R0617

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 12 PPI RESPONSE

PLEASE REVISE RESONSE TO PPI #10 (issued on Amendment 0009) as follows:

QUESTION: The Room Requirements for the storage bays are calling for pre‐finished insulated metal panels on the building. These insulated panels are above a CMU/Brick wainscot that runs 8’ high around the entire perimeter. The BEAP reads that light industrial buildings can use either insulated metal walls, brick, or a combination. Building 1430 next door was constructed with what appears to be floor to ceiling uninsulated metal wall panels, with insulation secured to the inside face of the panels. Building 1430 represents traditional PEMB construction and is by far the most cost‐effective way to construct a PEMB building. Is it possible to match the look of Building 1430 directly adjacent to this project?

DELETE PREVIOUS RESPONSE which stated : “Yes, floor to ceiling uninsulated panels with the insulation secured to the inside face of the panel is acceptable”.

REPLACE WITH REVISED RESPONSE: "NO, Provide metal panels above 8' high CMU/brick wainscot per Room Requirements."

The following responses to previously PENDING PPIs are as follows:

PPI #79 ‐ Please confirm the power source to the facility is considered reliable per UFC 3‐600‐01.

RESPONSE: Proceed based on the assumption that power in NOT reliable.

PPI #83 ‐ Will the fire pump need an automatic transfer switch, this would switch the pump over to a generator in the event of a power loss, be required?

RESPONSE: It is assumed that the power is unreliable (see PPI #79) and as such, an automatic transfer switch will be required.

PPI #92 ‐ Please confirm the ASHRAE requirements for this project.

RESPONSE: Question is vague. ASHRAE 90.1‐2013 is the version currently in effect for energy use requirements.

ASHRAE 62.1‐2013 is in effect for indoor air quality, per IMC 2015. ASHRAE 189.1‐2014 as invoked by UFC 1‐200‐ 02 is for moisture control. For ASHRAE 90.1, Appendix G energy use comparison, in order to comply with EPACT 2005, 90.1‐2013 is to be used.

Additional PPI #1 ‐ Please clarify how the Building 1430 pavement is to connect with the new pavement for P977.

Are we required to dowel into the existing pavement or just abut the existing pavement with the new apron.

RESPONSE: Contractor will be required to dowel into the existing pavement at Building 1430 with the new apron.

Additional Clarification #1 ‐ PPI 80 and 88 both note to provide the 8' CMU wainscot on the perimeter of the building. Section B2010 in the RFP only references the 8' CMU enclosure, but doesn't reference any further details on the wainscot finish/appearance. Looking at the BEAP in Part 6, the Industrial District maintenance/industrial buildings are to have metal wall panels on the exterior. Light Industrial buildings are to have a combination of

N4008518R0617 brick and/or metal wall panels. With‐in the BEAP, the detailing/fenestration and materials/colors sections generically call for modular size red brick w/ gray accent brick as required. The BEAP Appendix C calls for Field Face Wire Cut Red Modular/Utility Brick, and Wire Cut Light Gray Modular/Utility Light Gray accent face. Our question is, does this 8' CMU wainscot require a red modular face brick veneer on the exterior face of the building?

We presume this is the case, as there will need to be a cavity section in the wall to bring the insulation and air/vapor barrier down to grade, but wanted to confirm that the Gov't wants the base standard modular red face brick on the outside face of the wall. Please note, that although this is the base standard, it will contrast the look of Building 1430, directly adjacent, which is simply metal wall panel from grade to eave.

RESPONSE: Provide red modular brick.

Additional Clarification #2 ‐ As a follow up question, PPI 86 confirmed that the only painting inside the vehicle storage bays would be the safety yellow on the steel columns up to 10' AFF. If we are now incorporating an 8' CMU wainscot on the entire perimeter of the vehicle storage bays, and C3010 notes that all CMU walls must be grout filled and epoxy painted (which matches 5.0 Room Requirements, Vehicle Storage Bays) . are we to leave the CMU walls in the storage bays unfinished, or do we need to epoxy paint all of these walls?

RESPONSE: Painting the CMU is not required.

ADDITIONAL RFI #39 ‐ Are any trench drains required inside the building? If so, what are the requirements?

RESPONSE: Trench drains are not required inside the building.

(End of Summary of Changes)