Question’s #3
Question: The net BBLS requirement was corrected and Sections C, L, M are aligned however, it did not confirm that the Maximum Deadweight requirement is based on the contract required capacity of 250,000 BBLS. The current DWT requirement identified in Section C of the solicitation is stated as "Shall not exceed a maximum DWT of 50,000 Metric Tons (MT)." Please clarify.
DWT is not based on cargo but based on the size of the vessel and the restrictions placed on the intended loading and discharging ports. "Shall not exceed a maximum DWT of 50,000 Metric Tons (MT)." is correct and re-measuring will not be allowed.
Question: Confirms that there is a requirement for a CBRD decontamination station in accordance with COMSCINST 3541.5 Series Part 1, Appendix C. This instruction and drawings are not readily available. Please provide in sufficient time to determine cost requirements. When will this be released?
Please see attached word doc.
Question: Confirms that there is a requirement for CMWDS under this RFP, but does not stipulate to any standard or referenced DWGS. Please provide full particulars of CMWDS requirements. What standards? Please provide any DWGS.
See attached Standard Plan for Decontamination Station.