WI_1011_-_TROLLEY_STOWAGE_ARMS_MOD_ARCTICROH14R2.pdf

PDF 13 KB Posted

Attached to
REGULAR OVERHAUL/DRYDOCK FOR USNS ARCTIC
Solicitation number
N32205-14-R-2000
Issued by

About this file

WORK ITEM 1011

View the file

Other files

File Type Posted
N32205-14-R-2000-0008.doc DOC document
USNS_ARCTIC_Amend_0005.doc DOC document
Copy_of_J_-_2_Category_A_Items_-_USNS_ARCTIC_2014.xlsx XLSX spreadsheet
Copy_of_J_-_2_Category_A_Items_-_USNS_ARCTIC_2014.xlsx XLSX spreadsheet
P0004_(Amendment_4).doc DOC document
P0002.doc DOC document
Q_ _A_USNS_ARCTIC_14-R-2000.docx DOCX document
SIGNED_J_A1.pdf PDF
DD Form 1423-1 SWI-017 Sep12.pdf PDF
DD Form 1423-1 SWI-901 Sep2012.pdf PDF
0408_A_UHF Transceiver Groom_ARCTICROH14R2.doc DOC document
DD Form 1423-1 SWI-016 14Sep12.pdf PDF
DD Form 1423-1 SWI-021 Sep12.pdf PDF
0108_A_Modifications for Load Line.docx DOCX document
DD Form 1423-1 SWI-013 Sep12.pdf PDF
DD Form 1423-1 SWI-011 T-AOE Sep12.pdf PDF
DD Form 1423-1 SWI-008 Sep12.pdf PDF
0910_A_ Main Propulsion Shafting_ARCTICROH14R1.doc DOC document
DD Form 1423-1 SWI-004 Sep12.pdf PDF
DD Form 1423-1 SWI-006 Sep12.pdf PDF
DD Form 1423-1 SWI-002.pdf PDF
ARCTIC ROH-DD Work Item IndexR3.doc DOC document
DD Form 1423-1 SWI-023 Sep12.pdf PDF
0402_A_Radar Preventitive Maintenance_ARCTICROH14R2.doc DOC document
0406_A_Underwater Speed Log PM_ARCTICROH14R2.doc DOC document
USNS_ARCTIC_Amend_0003.doc DOC document
0404_A_ Antenna Preventative Maintance_ARCTICROH14R2.doc DOC document
DD Form 1423-1 SWI-020 14Sep12.pdf PDF
DD Form 1423-1 SWI-014 Sep12.pdf PDF
DD Form 1423-1 SWI-022 Sep12.pdf PDF
0801_A_Ventilation System Cleaning —
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS REV OCT 2012 - ARCTICROH14R3.doc DOC document
DD Form 1423-1 SWI-010 Sep12.pdf PDF
Copy_of_J-3_Category_B_Items_123013.xls XLS spreadsheet
0407_A_OE-82C-WSC-1-V Antenna Group Maintenance_ARCTICROH14R2.doc DOC document
DD Form 1423-1 SWI-012 Sep12.pdf PDF
DD Form 1423-1 SWI-007 Sep12.pdf PDF
DD Form 1423-1 SWI-019 Sep12.pdf PDF
DD Form 1423-1 SWI-003 Sep12.pdf PDF
DD Form 1423-1 SWI-018 Sep12.pdf PDF
DD Form 1423-1 SWI-015 Sep2012.pdf PDF
0405_A_TV-DTS and TV Distribution System PM_ARCTICROH14R2.doc DOC document
DD Form 1423-1 SWI-001 14Sep12.pdf PDF
DD Form 1423-1 SWI-024 Sep12.pdf PDF
0919_B_Replace Stern Tube Shaft Bearing LinersARCTICROH14R2.doc DOC document
WI_025_Attachment.pdf PDF
WI_1013_-_EQUIPMENT_INSPECTION_SPEC_ARCTICROH14R3.pdf PDF
Q_AND_A_FPR_N32205-14-R-2000.docx DOCX document
WI_024_Attachment.pdf PDF
Copy_of_USNS_Supply_Configuration_List.xls XLS spreadsheet
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS ARCTIC

(T-AOE 8)

UNREP GEAR RFP NO. N32205-14-R-2000

6 January, 2014 ITEM NO. 1011 Category "A" PHDNSWC/KRUG/jb

STATION NO.6 TROLLEY STOWAGE ARMS MODIFICATIONS

1011-1

1.0 ABSTRACT

This item describes the requirements for modifications to the Station No. 6 Trolley Stowage Arms

2.0 REFERENCES

2.1 NAVSEA Drawing No. 8287352, Stowage Arm, Machining

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity

3.1.1 Location: Various

3.1.2 Quantity: 2

3.2 Item Description/Manufacturer's Data

3.2.1 Bill of Materials

PC No. QTY Description 1 2 Right and left hand trolley stowage arms. See Reference 2.1.

3.2.2 Quantities are considered estimates. The

Contractor shall provide the exact quantities and additional material such as miscellaneous pipe fittings, elbows, caps, valves, pipe hangers, weld material, cable hangers, cable tags, buswork, etc., which are not included in the List of Materials, in order to install a fully functional system which meets the requirements of this specification.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES

4.1 Government Furnished Equipment (GFE): None Additional.

4.2 Government Furnished Material (GFM): None Additional.

1011-2

4.3 Government Furnished Services (GFS)

Port Hueneme representative will provide technical support/guidance during the accomplishment of this work item.

4.4 Government Furnished Information (GFI): None Additional.

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of

tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTR’s including but not limited to GTR’s 1-7, 22, 23, 24, 28 and 29.

5.2 The contractor and all subcontractors, regardless of

tier, are advised to review other work items under this contract to determine their effect on the work required under this work item.

5.3 Contractor Furnished Materials (CFM)

Contractor is to supply Anti-seize compound (MIL-PRF- 907), Grease (MIL-PRF-24139A), and other consumables as required.

5.4 All equipment identified for removal and re-installation

shall be tagged, segregated and preserved to ensure equipment availability upon request of installing activity

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional.

7.0 STATEMENT OF WORK REQUIRED

7.1 Arrangements/Outfitting: None Additional.

7.2 Structural: None Additional.

7.3 Mechanical/Fluids

1011-3

7.3.1 Fabrication

Fabricate right and left hand trolley stowage arms in accordance with Reference 2.1.

7.3.2 Removals

Remove existing trolley stowage arms on Station No. 6 Heavy Unrep Transfer Head.

7.3.3 Installations

Install fabricated trolley stowage arms on Station No. 6 Heavy Unrep Transfer Head.

7.4 Electrical: None Additional.

7.5 Electronics: None Additional.

7.6 Preparation of Drawings/Documentation/Test Memo: None

Additional.

7.7 Inspection/Test

7.7.1 Operational test

a. Trolley arms will be tested by swinging open and closed to ensure freedom of movement.

b. During system operation, trolley should seat properly in the trolley stowage arms. Proper seating can be verified by Port Hueneme and/or ship personnel.

7.8 Painting

Paint all new and modified surfaces to match surrounding surfaces.

1011-4

7.9 Marking

Install name plates, notices, and markings for all new and modified systems (or areas).

7.10 Manufacturer's Representative

Government representatives from NSWC will be on site to provide technical oversight and guidance upon request from contractor

8.0 GENERAL REQUIREMENTS: None Additional.