P6_Prime_Cost_Summary_Spreadsheet_(TES).xls
XLS spreadsheet 1 MB Posted
- Attached to
- AIR-4. 11, N00421-16-R-0059 Technical and Engineering Services (TES) supporting AD-4. 11. 3
- Solicitation number
- N00421-16-R-0059
About this file
P6 Prime Cost Summary Spreadsheet
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| Instructions | |
| (Please note that the cells referenced below correspond to the Cost Type sheets. The Summary sheet is numbered slightly differently. ) | |
| Contractor: | |
| 1 | On Header Tab for each worksheet, insert the proposal number. |
| 2 | On Footer Tab for the worksheet, insert the firm's name after colon. |
| 3 | A worksheet has been prepared for each year of the period of performance. Summary sheets exist for both term and completion CLINs. The information in the summary tabs should automatically carry over from the other tabs. Verify that the summary sheets are correct after completing the separate tabs for each year for both Term and Completion. |
| 4 | A worksheet has been prepared for the ODC CLINs. Offeror should fill in the material handling and G&A rates, if any, for material and travel. If no material handling or G&A is being applied, the cells should read 0%. ODCs have no fee associated with them. |
| 5 | Every worksheet should have items 1 and 2 completed. |
| 6 | The worksheets of the workbook should all be formatted for printing on letter-size paper, without requiring "adjustments." It may be formatted for either landscape or portrait. DO NOT FORMAT FOR LEGAL SIZE PAPER. |
| 7 | Within the work sheets any cell colored cells should not be edited. Formulas should not be edited. |
| 8 | All dollar figures shall be carried out no further than two decimal places. Values with additional decimal places shall not be used within any calculations. |
| 9 | In column A, starting at row 5, the Government Labor Categories have been inserted. In column B, the Offeror can insert the title of the labor category it will be utilizing if unable to match the Government supplied labor categories. The Offeror is not required to utilize the Government's labor categories. However, in evaluation, the Offeror's proposal will be compared to the Government Estimate in terms of hours and labor categories. This applies to the Prime Contractor's section and those sections for its subcontractors. If necessary, insert additional rows--but ensure integrity of formulas. Also, labor categories with more than one person providing service shall be listed multiple times for each person performing work. For example, if the offeror proposes four Senior Analysts, then the labor category Senior Analyst shall be listed four times along with their applicable rates and information. |
| 10 | In column C, for both the prime contractor's own workforce and that of the individual subcontractors' workforces, the Offeror should insert a "CF" if the worker will be performing at the Contractor's facility or a "O" if it will be performing in Government spaces. |
| 11 | In column D, for the prime contractor's own workforce, the field is colored "green" indicating no input. (This reflects that the prime contractor is proposing its own employees or contingency hires--it does not include any subcontractors.) For the subcontractors, their fields are in yellow. No input is required by the Offeror in this column. Please note if more subcontractors are needed, the contractor may add additional rows to accommodate them, but ensure integrity of formulas. |
| 12 | In column E, for both the prime contractor's own workforce and that of the individual subcontractors' workforces, identify for the specific labor category individual whether they are full-time on this acquisition or part-time. Enter "F" for full-time or "P" for part-time. |
| 13 | In column F, enter the name of the proposed individual for that position. |
| 14 | In column G: |
| (a) for the prime contractor, enter the unburdened labor rate for each proposed individual for each worksheet (both term and competion for all 5 years) | |
| b) In row 57 for the term worksheets and in row 19 for the completion worksheets, the prime contractor should insert its fringe rate for full time, if it is not included in its overhead rate. If the fringe is included in the overhead rate, this cell should be left as 0%. | |
| (c) In Row 58 for the term worksheets and in row 20 for the completion worksheets, the prime contractor should insert its fringe rate for part-time, if it is not included in its overhead rate. If the fringe is included in the overhead rate, this cell should be as 0%. If no part-time employees are proposed this should also be left as 0% | |
| (d) In row 61 for the term worksheets and in row 23 for the completion worksheets, the prime contractor should insert its overhead rate for work performed at the contractor's facility. | |
| (e) In row 62 for the term worksheets and in row 24 for the completion worksheets, the prime contractor should insert its overhead rate for work performed at the Client/Government's facility. | |
| (f) In row 65 for the term worksheets and in row 27 for the completion worksheets, the prime contractor should insert its G&A rate being applied for work being performed at the Contractor's facility. | |
| (g) In row 66 for the term worksheets and row 28 for the completion worksheets, the prime contractor should insert its G&A rate being applied for work being performed at the Client/Government's facility. | |
| (h) For the subcontractor, enter the fully burdened cost including subcontractor's fixed fee associated with each proposed labor category (e.g., for term worksheets rows 72-121, 125-174, 178-227, 231-280, 284-333, 337-386, 390-439, and 443-492 and for completion worksheets rows 34-45, 48-59, 62-73, 76-87, 90-101, 104-115, 118-129, 132-143) | |
| (i) In Cell G495 on the term worksheets and in cell G146 on the completion worksheets, the prime should insert the subcontractor handling charge, if any. | |
| (j) In Cell G498 on the term worksheets and in cell G149 on the completion worksheets, the prime should insert the fixed fee rate applied to its cost excluding subcontractor labor. | |
| (k) In Cell G499 on the term worksheets and in cell G150 on the completion worksheets, the prime should insert the fixed fee rate it is applying to the subcontractor labor, if any. | |
| 15 | In column H: |
| (a) for the prime contractor and the subcontractor, enter the hours associated with each individual labor category (e.g.,for term worksheets rows 5-54, 72-121, 125-174, 178-227, 231-280, 284-333, 337-386, 390-439, and 443-492 and for completion worksheets rows 34-45, 48-59, 62-73, 76-87, 90-101, 104-115, 118-129, 132-143). | |
| 16 | Column H automatically calculates the total hours for individual worksheets (both prime and subcontractor) |
| 17 | If there is not going to be any data entry in a row or group of rows, please just hide the rows. Do not delete. For example, if the prime is only utilizing two subcontractors, then the rows concerning sub 3 through 8 (which are rows 178 through 493) would be hidden. |
| 18 | When submitting this file, the instructions may be deleted. |
&R&F
Total Summary
| Hours | Total | |
| Labor (CPFF LOE) | 250 | $ 1,250 |
| Fee (CPFF LOE) | $ - 0 | |
| Total (CPFF LOE) | $ 1,250 | |
| Labor (CPFF Completion) | 50 | $ - 0 |
| Fee (CPFF Completion) | $ 223 | |
| Total (CPFF Completion) | $ 223 | |
| TOTAL ODCs | $ 7,853,027 | |
| TOTAL EFFORT | $ 7,854,499 |
Term Year 1
| DO NOT TYPE IN ANY COLORED AREAS | ||||||||
| Period of Performance: | 10/30/2018-10/29/2019 | CLIN | 0001 | |||||
| Services | Contractor | hrs | subtotal | |||||
| Government Labor Category (* = Key) | Proposed Category | site | sub | f/p | Employee Name | Rate | Labor | |
| Program/Project Analyst, Journeyman (Onsite) | Example Category | O | f | John Doe | $ 5.00 | 50.00 | $ 250.00 | |
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Program/Project Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer I (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer II (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer III (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Electrical Engineer, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Mechanical Engineer, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Administrative Assistant (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Junior (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Junior (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Senior *(Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Logistician, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Logistician, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Program Manager) | O | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Program Manager) | CF | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| subtotal for unburdened labor | 50.00 | $250.00 | ||||||
| Base | ||||||||
| fringe fulltime | 0.00% | $ 250.00 | $0.00 | |||||
| fringe part time | 0.00% | $ - 0 | $0.00 | |||||
| subtotal for fringe | $0.00 | |||||||
| Overhead | Base | |||||||
| Contractor site | 0.00% | $ - 0 | $0.00 | |||||
| Onsite Government | 0.00% | $ 250.00 | $0.00 | |||||
| subtotal for overhead | $0.00 | |||||||
| G&A | ||||||||
| Contractor site | 0.00% | $ - 0 | $0.00 | |||||
| OnSite Government | 0.00% | $ 250.00 | $0.00 | |||||
| subtotal for G&A | $0.00 | |||||||
| Total Labor before FCCOM or profit | $250.00 | |||||||
| Subcontractors | ||||||||
| Sub: 1: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 2: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 2 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 2 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 3 | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 3 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 3 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 4: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 4 | $ - 0 | - 0 | $ - 0 | |||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 4 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 4 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 5: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 5 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 5 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 6: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 6 | $ - 0 | - 0 | $ - 0 | |||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 6 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 6 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 7 | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 7 | $ - 0 | - 0 | $ - 0 | |||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 7 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 7 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Sub: 8: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | 8 | $ - 0 | $ - 0 | ||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | 8 | $ - 0 | $ - 0 | ||||
| subtotal | - 0 | $0.00 | ||||||
| Subtotal for all subcontractors | - 0 | - 0 | ||||||
| subcontractor handling | 0.00% | - 0 | $0.00 | |||||
| subtotal for subcontractors labor | $0.00 | |||||||
| Fee/Profit - prime | 0.0% | $250.00 | $0.00 | |||||
| prime's fee/profit on subcontractor | 0.0% | - 0 | $0.00 | |||||
| Fee/Profit Pool | $0.00 | |||||||
| Prime FCCOM | 0.00% | $250.00 | $0.00 | |||||
| Total Cost | $250.00 | |||||||
| Fixed Fee | $0.00 | |||||||
| Grand Total Labor and Subcontractor Cost Plus Fee/Profit | $250.00 |
&C Solicitation N00421-16-R-0059, Attachment P6 CPFF LOE Year 1 Proposal:
&CPage &P of &N Offeror:
Term Year 2
| DO NOT TYPE IN ANY COLORED AREAS | ||||||||
| Period of Performance: | 10/30/2019-10/29/2020 | CLIN | 0001 | |||||
| Services | Contractor | hrs | subtotal | |||||
| Government Labor Category (* = Key) | Proposed Category | site | sub | f/p | Employee Name | Rate | Labor | |
| Program/Project Analyst, Journeyman (Onsite) | Example Category | O | f | John Doe | $ 5.00 | 50.00 | $ 250.00 | |
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Program/Project Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer I (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer II (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Programmer III (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Electrical Engineer, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Mechanical Engineer, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Administrative Assistant (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Junior (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Junior (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Information Security Analyst, Senior *(Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Logistician, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Logistician, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Program Manager) | O | $ - 0 | $ - 0 | |||||
| Manager/Operations Manager, Senior (Program Manager) | CF | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Journeyman (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Senior * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Journeyman (Systems Engineer) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Journeyman (Systems Engineer) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Engineer, Senior (Systems Engineer) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Engineer, Senior (Systems Engineer) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Systems Specialist) * (Onsite) | O | $ - 0 | $ - 0 | |||||
| Software Developer, Senior (Systems Specialist) * (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| Technical Writer (Technical Writer II) (SCA) (Onsite) | O | $ - 0 | $ - 0 | |||||
| Technical Writer (Technical Writer II) (SCA) (Contractor Facility) | CF | $ - 0 | $ - 0 | |||||
| subtotal for unburdened labor | 50.00 | $250.00 | ||||||
| Base | ||||||||
| fringe fulltime | 0.00% | $ 250.00 | $0.00 | |||||
| fringe part time | 0.00% | $ - 0 | $0.00 | |||||
| subtotal for fringe | $0.00 | |||||||
| Overhead | Base | |||||||
| Contractor site | 0.00% | $ - 0 | $0.00 | |||||
| Onsite Government | 0.00% | $ 250.00 | $0.00 | |||||
| subtotal for overhead | $0.00 | |||||||
| G&A | ||||||||
| Contractor site | 0.00% | $ - 0 | $0.00 | |||||
| OnSite Government | 0.00% | $ 250.00 | $0.00 | |||||
| subtotal for G&A | $0.00 | |||||||
| Total Labor before FCCOM or profit | $250.00 | |||||||
| Subcontractors | ||||||||
| Sub: 1: | site | sub | f/p | Employee Name | Rate | Labor | ||
| Program/Project Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Program/Project Analyst, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer I (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer II (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Programmer III (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Drafter/CAD Operator II (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Electrical and Electronic Engineering Technician (Electronics Technician Maintenance III) (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Electrical Engineer, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Mechanical Engineer, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Administrative Assistant (SCA) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Junior (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Information Security Analyst, Senior (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Logistician, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Manager/Operations Manager, Senior (Project Manager) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Network Architect, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Software Developer, Senior (Software Engineer, Senior) * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Journeyman (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Computer Systems Analyst, Senior * (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Onsite) | O | 1 | $ - 0 | $ - 0 | ||||
| Engineer, Junior (Systems Engineer) (Contractor Facility) | CF | 1 | $ - 0 | $ - 0 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.